Spudcans as foundations for offshore jack-up rigs - Problems and calculation methods

被引:1
|
作者
Henke, Sascha [1 ]
Qiu, Gang [1 ]
Pucker, Tim [1 ]
机构
[1] Tech Univ Hamburg, Inst Geotech & Baubetrieb, D-21073 Hamburg, Germany
关键词
spudcans; offshore; foundation; bearing capacity; design; jack-up rig; SAND OVERLYING CLAY; BEARING CAPACITY; PENETRATION; SOILS; MODEL;
D O I
10.1002/bate.201200047
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Spudcans as foundations for offshore jack-up rigs - Problems and calculation methods For the installation of wind parks jack-up rigs can be used. Jack-up rigs are founded on the seabed before start of operation to receive sufficient stability and to reduce wave induced influences. One possible foundation for jack-up rigs on the seabed is the so-called spudcan. A spudcan is a circular foundation attached to the legs of the jack-up rig to transfer the vertical loads into the ground. The use of spudcan-foundations is state-of-the-art in the oil- and gas industry. Nevertheless, the design of this type of foundation is still challenging. For example, the correct determination of the load-settlement-response with respect to different soil conditions is complex and the definition of the safe side is not always clear. Another problem related to the spudcan depositioning onto layered soil is the so-called punch-through-failure. This means that during installation onto dense sand overlying weak clay the spudcan may suddenly punch through the sand layer into the weaker layer. This can even lead to a total loss of the jack-up rig. In this contribution, different methods for spudcan design recommended in literature and international guidelines are summarized. Furthermore, open questions and results of ongoing research are discussed to give the reader an impression of the capabilities and the difficulties regarding spudcan foundations.
引用
收藏
页码:831 / 840
页数:10
相关论文
共 50 条
  • [41] Prediction Methods of Spudcan Penetration for Jack-up Units
    张爱霞
    段梦兰
    李海明
    赵军
    王建军
    ChinaOceanEngineering, 2012, 26 (04) : 591 - 602
  • [42] Prediction methods of spudcan penetration for jack-up units
    Ai-xia Zhang
    Meng-lan Duan
    Hai-ming Li
    Jun Zhao
    Jian-jun Wang
    China Ocean Engineering, 2012, 26 : 591 - 602
  • [43] Non-linear dynamic analysis of offshore jack-up units
    Williams, MS
    Thompson, RSG
    Houlsby, GT
    COMPUTERS & STRUCTURES, 1998, 69 (02) : 171 - 180
  • [44] Synchronous control of jacking system of jack-up offshore drilling platform
    He X.
    Shi L.
    2018, University of Petroleum, China (42): : 149 - 156
  • [45] Calculation and analysis of the wave load of jack-up offshore wind turbine installation vessel during dynamic positioning
    Yao, Zhenqiu
    Shen, Yun
    Gu, Xin
    Bu, Linxin
    PROCEEDINGS OF THE FIRST INTERNATIONAL CONFERENCE ON INFORMATION SCIENCES, MACHINERY, MATERIALS AND ENERGY (ICISMME 2015), 2015, 126 : 1043 - 1047
  • [46] Jack-up push-over analyses featuring a new force resultant model for spudcans in soft clay
    Zhang, Youhu
    Bienen, Britta
    Cassidy, Mark J.
    OCEAN ENGINEERING, 2014, 81 : 139 - 149
  • [47] DEVELOPMENT OF HEAVY THICK HT80 STEEL PLATES FOR RACKS OF JACK-UP RIGS
    OKANO, S
    TETSU TO HAGANE-JOURNAL OF THE IRON AND STEEL INSTITUTE OF JAPAN, 1986, 72 (12): : 1154 - 1154
  • [48] Jack-up glant ready to build next generation of offshore wind farms
    Johnson, Daniel
    Naval Architect, 2023, : 33 - 34
  • [50] CALCULATION OF THE DYNAMIC POSITIONING CAPABILITY OF AN OFFSHORE WIND FARM VESSEL DURING THE JACK-UP PROCESS IN THE EARLY DESIGN STAGE
    Liebert, Maximilian
    PROCEEDINGS OF THE ASME 38TH INTERNATIONAL CONFERENCE ON OCEAN, OFFSHORE AND ARCTIC ENGINEERING, 2019, VOL 1, 2019,