Modified Streamlined Optimization Algorithm for Time-Cost Tradeoff Problems of Complex Large-Scale Construction Projects

被引:4
|
作者
Wang, Jia [1 ]
Han, Congji [1 ]
Li, Xinghua [1 ]
机构
[1] Hunan Univ, Coll Civil Engn, Changsha, Hunan, Peoples R China
基金
中国博士后科学基金;
关键词
Time-cost tradeoff (TCT); Optimization; Integer programming; Critical path identification method; Network analysis; GENETIC ALGORITHMS; OFF PROBLEM; COMPRESSION;
D O I
10.1061/JCEMD4.COENG-12970
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Although research on time-cost tradeoff (TCT) problems has been extensively conducted, there are still few applications of TCT optimization methods in the scheduling of projects with practical size and complexity. As a good attempt, a streamlined optimization algorithm has recently been developed for solving TCT problems with a continuous curvilinear activity time-cost relationship. However, the algorithm encounters the difficulties of high memory requirements and computational demand when it is implemented in complex large-scale projects whose networks may involve tens of millions of paths and hundreds of activities. To overcome such difficulties, this study presents a modified version of the streamlined optimization algorithm. Particularly, a new method for identifying critical paths is proposed in the modified algorithm. Also, a modeling problem has been addressed in order to consolidate the theoretical foundation of the algorithm. As illustrated by the experimental examples, the modified streamlined algorithm outperforms the original algorithm and the commonly used genetic algorithm in terms of optimality, robustness, and computational efficiency. This study thus contributes to the development of commercial scheduling software capable of tackling practical TCT problems.
引用
收藏
页数:12
相关论文
共 50 条
  • [1] Robust Optimization for Time-Cost Tradeoff Problem in Construction Projects
    Li, Ming
    Wu, Guangdong
    ABSTRACT AND APPLIED ANALYSIS, 2014,
  • [2] Streamlined project time-cost tradeoff optimization methodology: Algorithm, automation, and application
    Nasiri, Sasan
    Lu, Ming
    AUTOMATION IN CONSTRUCTION, 2022, 133
  • [3] Time-cost optimization using harmony search algorithm in construction projects
    Zalmai, Lemar Mohammad
    Akcay, Cemil
    Manisali, Ekrem
    REVISTA DE LA CONSTRUCCION, 2019, 18 (02): : 226 - 237
  • [4] Multi-objective particle swarm optimization for construction time-cost tradeoff problems
    Zhang, Hong
    Li, Heng
    CONSTRUCTION MANAGEMENT AND ECONOMICS, 2010, 28 (01) : 75 - 88
  • [5] Resource-Constrained Time-Cost Tradeoff for Repetitive Construction Projects
    Heravi, Gholamreza
    Moridi, Saeed
    KSCE JOURNAL OF CIVIL ENGINEERING, 2019, 23 (08) : 3265 - 3274
  • [6] Resource-Constrained Time-Cost Tradeoff for Repetitive Construction Projects
    Gholamreza Heravi
    Saeed Moridi
    KSCE Journal of Civil Engineering, 2019, 23 : 3265 - 3274
  • [7] Improvement Optimization Algorithm for Stochastic Discrete Time-cost Trade-off Problems of Construction Projects
    Wang J.
    Tang J.
    Zhou Z.
    Han C.
    Hunan Daxue Xuebao/Journal of Hunan University Natural Sciences, 2023, 50 (07): : 229 - 238
  • [8] Simplification of Large Scale Network in Time-Cost Tradeoff Problem
    Qi Jian-xun
    Sun De-dong
    2012 INTERNATIONAL CONFERENCE ON FUTURE ELECTRICAL POWER AND ENERGY SYSTEM, PT A, 2012, 17 : 134 - 144
  • [9] Research on Time-Cost Optimization Model of Construction Projects
    Huang, Jian-wen
    Wang, Xing-xia
    Zhou, Yi-hong
    Huang, Jian-wen
    Wang, Xing-xia
    2008 4TH INTERNATIONAL CONFERENCE ON WIRELESS COMMUNICATIONS, NETWORKING AND MOBILE COMPUTING, VOLS 1-31, 2008, : 7710 - +
  • [10] The Mechanism of Design Activity Overlapping in Construction Projects and the Time-Cost Tradeoff Function
    Dehghan, R.
    Ruwanpura, J. Y.
    PROCEEDINGS OF THE TWELFTH EAST ASIA-PACIFIC CONFERENCE ON STRUCTURAL ENGINEERING AND CONSTRUCTION (EASEC12), 2011, 14