Risk analysis in underground tunnel construction with tunnel boring machines using the Best-Worst method and data envelopment analysis

被引:6
|
作者
Koohathongsumrit, Nitidetch [1 ]
Meethom, Warapoj [2 ]
机构
[1] Ramkhamhang Univ, Fac Sci, Dept Stat, 2086 Ramkhamhaeng Rd, Bangkok 10240, Thailand
[2] King Mongkuts Univ Technol North Bangkok, Fac Engn, Dept Ind Engn, 1518 Pracharat 1 Rd, Bangkok 10800, Thailand
关键词
Metro construction; Multiple criteria decision -making; Risk assessment; Tunnel boring machine; Underground work; FUZZY-LOGIC; SUSTAINABILITY; RANKING; CHINA;
D O I
10.1016/j.heliyon.2023.e23486
中图分类号
O [数理科学和化学]; P [天文学、地球科学]; Q [生物科学]; N [自然科学总论];
学科分类号
07 ; 0710 ; 09 ;
摘要
Background: The use of tunnel boring machines is continuously increasing; however, this activity faces many risks, resulting in negative events.Methods: A novel approach using the best-worst method and a data envelopment analysis model was proposed to analyze the risks of underground tunnel construction with tunnel boring machines. The proposed approach was validated using a realistic case study of metro construction in Thailand.Results: The proposed approach efficiently analyzed the risks and produced more solid findings. The most critical and least affected risks can be identified according to risk scores in descending order. Implication: This study contributes a new method of risk analysis that benefits project managers and stakeholders who design risk management plans to reduce the occurrence and mitigate the severity of metro works.Originality: The new risk analysis can obtain the best compromise ranking of risks based on decision-makers' preferences, probabilities, and various consequences under different circumstances.
引用
收藏
页数:18
相关论文
共 50 条
  • [31] Stability analysis of a tunnel using LIDAR data and the keyblock method
    Agustín Menéndez-Díaz
    Ramón Argüelles-Fraga
    Silverio García-Cortés
    Celestino Ordóñez-Galán
    Bulletin of Engineering Geology and the Environment, 2016, 75 : 469 - 483
  • [32] Monitoring and Analysis of the Explosion Vibration of Underground Tunnel Construction in Urban Area
    Li Shaoxian
    Yu Jianxin
    Wang Hailiang
    Chen Lianjun
    THEORY AND PRACTICE OF ENERGETIC MATERIALS, VOL VIII, 2009, : 628 - 631
  • [33] Analysis of Underground Space Azimuth Measuring and Data Processing in A Tunnel
    Wang, Tao
    Duan, Hurong
    Jiang, Liutao
    Liu, Shun
    ADVANCES IN CIVIL AND INDUSTRIAL ENGINEERING IV, 2014, 580-583 : 2828 - 2832
  • [34] Wine consumers' preferences in Spain: an analysis using the best-worst scaling approach
    de-Magistris, Tiziana
    Gracia, Azucena
    Albisu, Luis-Miguel
    SPANISH JOURNAL OF AGRICULTURAL RESEARCH, 2014, 12 (03) : 529 - 541
  • [35] Estimation of penetration rate of tunnel boring machines using Monte-Carlo simulation method
    Dehghani, H.
    Beiranvand, N. Mikhak
    JOURNAL OF MINING AND ENVIRONMENT, 2016, 7 (02): : 175 - 184
  • [36] Construction prequalification using data envelopment analysis
    McCabe, B
    Tran, V
    Ramani, J
    CANADIAN JOURNAL OF CIVIL ENGINEERING, 2005, 32 (01) : 183 - 193
  • [37] Probabilistic Risk Analysis of Diversion Tunnel Construction Simulation
    Yu, Jia
    Zhong, Denghua
    Ren, Bingyu
    Tong, Dawei
    Hong, Kun
    COMPUTER-AIDED CIVIL AND INFRASTRUCTURE ENGINEERING, 2017, 32 (09) : 748 - 771
  • [38] Safety Risk Analysis and Control Of Subsea Tunnel Construction
    Zhang Ding-li
    Li Bing
    Fang Qian
    Li Peng-fei
    ACUUS2009: PROCEEDINGS OF 12TH INTERNATIONAL CONFERENCE OF THE ASSOCIATED RESEARCH CENTERS FOR URBAN UNDERGROUND SPACE, 2009, : 334 - 339
  • [39] Risk Analysis for Metro EPB Shield Tunnel Construction
    Song Shu-Guang
    Sun Chao-Qun
    Ge Yan-Hui
    Lin Peng
    Liu Hong-Liang
    PROCEEDINGS OF THE 2015 INTERNATIONAL CONFERENCE ON EDUCATION, MANAGEMENT AND COMPUTING TECHNOLOGY, 2015, 30 : 1813 - 1816
  • [40] The Construction Monitoring and Data Analysis of The Zhang JiaQu Tunnel
    Ao, Haixia
    Zhang, Yue
    PROGRESS IN INDUSTRIAL AND CIVIL ENGINEERING II, PTS 1-4, 2013, 405-408 : 1355 - 1359