A reactive scheduling approach for the resource-constrained project scheduling problem with dynamic resource disruption

被引:3
|
作者
Xu, Jiaojiao [1 ]
Bai, Sijun [1 ]
机构
[1] Northwestern Polytech Univ, Sch Management, Xian, Peoples R China
关键词
Project scheduling; Dynamic resource disruption; Reactive schedule; Hybrid genetic algorithm; VACATIONS; ALGORITHM; SEARCH; MODELS;
D O I
10.1108/K-09-2022-1339
中图分类号
TP3 [计算技术、计算机技术];
学科分类号
0812 ;
摘要
PurposeThis paper aims to develop an algorithm to study the impact of dynamic resource disruption on project makespan and provide a suitable resource disruption ratio for various complex industrial and emergency projects.Design/methodology/approachThis paper addresses the RCPSP in dynamic environments, which assumes resources will be disrupted randomly, that is, the information about resource disruption is not known in advance. To this end, a reactive scheduling model is proposed for the case of random dynamic disruptions of resources. To solve the reactive scheduling model, a hybrid genetic algorithm with a variable neighborhood search is proposed.FindingsThe results obtained on the PSLIB instances prove the performance advantage of the algorithm; through sensitivity analysis, it can be obtained, the project makespan increases exponentially as the number of disruptions increase. Furthermore, if more than 50% of the project's resources are randomly disrupted, the project makespan will be significantly impacted.Originality/valueThe paper focuses on the impact of dynamic resource disruptions on project makespan. Few studies have considered stochastic, dynamic resource uncertainty. In addition, this research proposes a reasonable scheduling algorithm for the research problem, and the conclusions drawn from the research provide decision support for project managers.
引用
收藏
页码:2007 / 2028
页数:22
相关论文
共 50 条
  • [31] A multiobjective resource-constrained project-scheduling problem
    Ben Abdelaziz, Fouad
    Krichen, Saoussen
    Dridi, Olfa
    SYMBOLIC AND QUANTITATIVE APPROACHES TO REASONING WITH UNCERTAINTY, PROCEEDINGS, 2007, 4724 : 719 - +
  • [32] Genetic algorithm for the resource-constrained project scheduling problem
    Goncharov, E. N.
    Leonov, V. V.
    AUTOMATION AND REMOTE CONTROL, 2017, 78 (06) : 1101 - 1114
  • [33] The preemptive stochastic resource-constrained project scheduling problem
    Creemers, Stefan
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2019, 277 (01) : 238 - 247
  • [34] On the summary measures for the resource-constrained project scheduling problem
    Van Eynde, Rob
    Vanhoucke, Mario
    Coelho, Jose
    ANNALS OF OPERATIONS RESEARCH, 2024, 337 (02) : 593 - 625
  • [35] Evaluation of Heuristics for a Resource-Constrained Project Scheduling Problem
    Zhong, Shisheng
    Fu, Xuyun
    Lin, Lin
    Wang, Guolei
    MACHINING AND ADVANCED MANUFACTURING TECHNOLOGY X, 2010, 431-432 : 122 - 125
  • [36] The Proactive Resource-Constrained Project Scheduling Problem with Resource Transfer Times
    Ma, Zhiqiang
    He, Zhengwen
    Wang, Nengmin
    PROCEEDINGS OF THE 2019 INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND SYSTEMS MANAGEMENT (IESM 2019), 2019, : 642 - 647
  • [37] A dynamic resource constrained project scheduling problem
    Villela da Silva, Andre Renato
    Ochi, Luiz Satoru
    INTERNATIONAL JOURNAL OF DATA MINING MODELLING AND MANAGEMENT, 2013, 5 (04) : 370 - 379
  • [38] Resource Constrained Project Scheduling With Dynamic Disruption Recovery
    Zaman, Forhad
    Elsayed, Saber M.
    Saker, Ruhul
    Essam, Daryl
    IEEE ACCESS, 2020, 8 : 144866 - 144879
  • [39] Resource-Constrained Multi-Project Reactive Scheduling Problem With New Project Arrival
    Peng, Wuliang
    Yu, Dongmin
    Lin, Jiali
    IEEE ACCESS, 2023, 11 : 64370 - 64382
  • [40] Important classes of reactions for the proactive and reactive resource-constrained project scheduling problem
    Davari, Morteza
    Demeulemeester, Erik
    ANNALS OF OPERATIONS RESEARCH, 2019, 274 (1-2) : 187 - 210