Multi-stage hybrid flow shop scheduling problem with lag, unloading, and transportation times

被引:0
|
作者
Hidri, Lotfi [1 ]
Tlija, Mehdi [1 ]
机构
[1] Department of Industrial Engineering, College of Engineering, King Saud University, Riyadh, Saudi Arabia
关键词
Benchmarking - Heuristic methods - Job shop scheduling - Machine shops - Scheduling algorithms;
D O I
10.7717/PEERJ-CS.2168
中图分类号
学科分类号
摘要
This study aims to address a variant of the hybrid flow shop problem by simultaneously integrating lag times, unloading times, and transportation times, with the goal of minimizing the maximum completion time, or makespan. With applications in image processing, manufacturing, and industrial environments, this problem presents significant theoretical challenges, being classified as NP-hard. Notably, the problem demonstrates a notable symmetry property, resulting in a symmetric problem formulation where both the scheduling problem and its symmetric counterpart share the same optimal solution. To improve solution quality, all proposed procedures are extended to the symmetric problem. This research pioneers the consideration of the hybrid flow shop scheduling problem with simultaneous attention to lag, unloading, and transportation times, building upon a comprehensive review of existing literature. A two-phase heuristic is introduced as a solution to this complex problem, involving iterative solving of parallel machine scheduling problems. This approach decomposes the problem into manageable sub-problems, facilitating focused and efficient resolution. The efficient solving of sub-problems using the developed heuristic yields satisfactory near-optimal solutions. Additionally, two new lower bounds are proposed, derived from estimating minimum idle time within each stage via solving a polynomial parallel machine problem aimed at minimizing total flow time. These lower bounds serve to evaluate the performance of the developed two-phase heuristic, over measuring the relative gap. Extensive experimental studies on benchmark test problems of varying sizes demonstrate the effectiveness of the proposed approaches. All test problems are efficiently solved within reasonable timeframes, indicating practicality and efficiency. The proposed methods exhibit an average computational time of 8.93 seconds and an average gap of 2.75%. These computational results underscore the efficacy and potential applicability of the proposed approaches in real-world scenarios, providing valuable insights and paving the way for further research and practical implementations in hybrid flow shop scheduling. © 2024 Hidri and Tlija
引用
收藏
页码:1 / 38
相关论文
共 50 条
  • [31] Study of an optimal scheduling model in a multi-stage, flow-shop where setup times change due to machining sequencing
    Li, Yann-Liang
    Ueno, Toshio
    Sanbayashi, Yousuke
    Nippon Kikai Gakkai Ronbunshu, C Hen/Transactions of the Japan Society of Mechanical Engineers, Part C, 2002, 68 (08): : 2510 - 2515
  • [32] Heuristics for the Hybrid Flow Shop Scheduling Problem with Sequence-Dependent Setup times
    Yong, Liao
    Zhantao, Li
    Xiang, Li
    Chenfeng, Peng
    Mathematical Problems in Engineering, 2022, 2022
  • [33] Heuristics for the Hybrid Flow Shop Scheduling Problem with Sequence-Dependent Setup times
    Yong, Liao
    Zhantao, Li
    Xiang, Li
    Chenfeng, Peng
    MATHEMATICAL PROBLEMS IN ENGINEERING, 2022, 2022
  • [34] A Hybrid Genetic Algorithm for Flexible Job Shop Scheduling Problem With Sequence-Dependent Setup Times and Job Lag Times
    Wang, Yilun
    Zhu, Qianwen
    IEEE ACCESS, 2021, 9 : 104864 - 104873
  • [35] Multi-cyclic flow shop scheduling: an application in multi-stage, multi-product production processes
    ElNajdawi, MK
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 1997, 35 (12) : 3323 - 3332
  • [36] Integrated Production and Transportation Scheduling Method in Hybrid Flow Shop
    Li, Wangming
    Han, Dong
    Gao, Liang
    Li, Xinyu
    Li, Yang
    CHINESE JOURNAL OF MECHANICAL ENGINEERING, 2022, 35 (01)
  • [37] Integrated Production and Transportation Scheduling Method in Hybrid Flow Shop
    Wangming Li
    Dong Han
    Liang Gao
    Xinyu Li
    Yang Li
    Chinese Journal of Mechanical Engineering, 2022, 35 (01) : 123 - 142
  • [38] Integrated Production and Transportation Scheduling Method in Hybrid Flow Shop
    Wangming Li
    Dong Han
    Liang Gao
    Xinyu Li
    Yang Li
    Chinese Journal of Mechanical Engineering, 2022, (01) : 123 - 142
  • [39] Integrated Production and Transportation Scheduling Method in Hybrid Flow Shop
    Wangming Li
    Dong Han
    Liang Gao
    Xinyu Li
    Yang Li
    Chinese Journal of Mechanical Engineering, 2022, 35
  • [40] Multi-objective no-wait hybrid flowshop scheduling problem with transportation times
    Khalili, Majid
    INTERNATIONAL JOURNAL OF COMPUTATIONAL SCIENCE AND ENGINEERING, 2012, 7 (02) : 147 - 154