Examining the causes and effects of time overruns in construction projects promoted by rural municipalities in Nepal

被引:0
|
作者
Koirala, Madhav Prasad [1 ]
Shahi, Roshan Samrat [2 ]
机构
[1] Sch Engn Pokhara Univ, Sch Engn, Pokhara Metropolitan City 30, Gandaki Provenc, Nepal
[2] Pokhara Univ, Sch Engn, Pokhara, Nepal
关键词
Time overrun; Delay factors; Delay effects; National Competitive Bidding; DELAY;
D O I
10.1016/j.evalprogplan.2024.102436
中图分类号
C [社会科学总论];
学科分类号
03 ; 0303 ;
摘要
Time overruns are the most common issue in construction projects, which have a significant negative impact on the project and the parties involved. This also applies to National Competitive Bidding (NCB) construction projects in municipalities, jeopardizing project timelines, costs, and quality standards. Poor performance by professionals in rural municipalities has resulted in inadequate infrastructure development in these areas. The goal of this study is to understand the causes and effects of time overruns by employing an exploratory and descriptive research methodology. The data from clients, consultants, and contractors consistently highlights key factors contributing to project delays, including adverse weather conditions, limited involvement from contractor head offices, insufficient consultant experience, inadequate site management, and delays in site mobilization. These delays incur substantial costs related to materials, land acquisition, labor, and market risks. The results included that 52.17% the projects experienced time overruns ranging from 24.4% to 514.71%. Furthermore, 21.73% of projects experienced cost overruns, with the highest at 19.92%. These findings provide critical insights for improving project management and addressing construction time overruns. It recommends conducting national-scale analyses to gain a comprehensive understanding of construction delays and to implement effective mitigation strategies.
引用
收藏
页数:13
相关论文
共 49 条
  • [21] Causes, Effects, and Mitigation Measures of Time and Cost Overruns in Water Supply Projects: Case of Tigrai Region, Northern Ethiopia
    Berihu, Lielti Gebreegziabher
    Grum, Berhane
    Tariku, Zeru
    Abebe, Bizuneh Asfaw
    ADVANCES IN CIVIL ENGINEERING, 2023, 2023
  • [22] Factors influencing construction time and cost overruns on high-rise projects in Indonesia
    Kaming, Peter F.
    Olomolaiye, Paul O.
    Holt, Gary D.
    Harris, Frank C.
    Construction Management and Economics, 1997, 15 (01): : 83 - 94
  • [23] Taxonomy for change causes and effects in construction projects
    Sun, Ming
    Meng, Xianhai
    INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2009, 27 (06) : 560 - 572
  • [24] Causes of Time Overrun in Construction of Building Projects in Pakistan
    Soomro, Faheem Ahmed
    Memon, Muhammed Jaffar
    Chandio, Abdul Fattah
    Sohu, Samiullah
    Soomro, Rizwanullah
    ENGINEERING TECHNOLOGY & APPLIED SCIENCE RESEARCH, 2019, 9 (01) : 3762 - 3764
  • [25] Analysis of Causes of Delay and Time Performance in Construction Projects
    Gonzalez, Pablo
    Gonzalez, Vicente
    Molenaar, Keith
    Orozco, Francisco
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2014, 140 (01)
  • [26] SIGNIFICANT FACTORS CAUSING TIME AND COST OVERRUNS IN CONSTRUCTION PROJECTS IN THE GAZA STRIP: CONTRACTORS' PERSPECTIVE
    Enshassi, Adnan
    Kumaraswamy, Mohan
    Al-Najjar, Jomah
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2010, 10 (01) : 35 - 60
  • [27] Causes of construction cost and time overruns: The 2010 FIFA World Cup stadia in South Africa
    Baloyi, Lucius
    Bekker, Michiel
    ACTA STRUCTILIA, 2011, 18 (01) : 51 - 67
  • [28] Claims in construction projects: how causes are linked to effects?
    Kikwasi, Geraldine John
    JOURNAL OF ENGINEERING DESIGN AND TECHNOLOGY, 2023, 21 (06) : 1710 - 1724
  • [29] Identification and classification of change causes and effects in construction projects
    Padala, S. P. Sreenivas
    Maheswari, J. Uma
    Hirani, Harish
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2022, 22 (14) : 2788 - 2807
  • [30] Aggregation of factors causing cost overruns and time delays in large public construction projects Trends and implications
    Adam, Abderisak
    Josephson, Per-Erik Bertil
    Lindahl, Goran
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2017, 24 (03) : 393 - 406