Examining the causes and effects of time overruns in construction projects promoted by rural municipalities in Nepal

被引:0
|
作者
Koirala, Madhav Prasad [1 ]
Shahi, Roshan Samrat [2 ]
机构
[1] Sch Engn Pokhara Univ, Sch Engn, Pokhara Metropolitan City 30, Gandaki Provenc, Nepal
[2] Pokhara Univ, Sch Engn, Pokhara, Nepal
关键词
Time overrun; Delay factors; Delay effects; National Competitive Bidding; DELAY;
D O I
10.1016/j.evalprogplan.2024.102436
中图分类号
C [社会科学总论];
学科分类号
03 ; 0303 ;
摘要
Time overruns are the most common issue in construction projects, which have a significant negative impact on the project and the parties involved. This also applies to National Competitive Bidding (NCB) construction projects in municipalities, jeopardizing project timelines, costs, and quality standards. Poor performance by professionals in rural municipalities has resulted in inadequate infrastructure development in these areas. The goal of this study is to understand the causes and effects of time overruns by employing an exploratory and descriptive research methodology. The data from clients, consultants, and contractors consistently highlights key factors contributing to project delays, including adverse weather conditions, limited involvement from contractor head offices, insufficient consultant experience, inadequate site management, and delays in site mobilization. These delays incur substantial costs related to materials, land acquisition, labor, and market risks. The results included that 52.17% the projects experienced time overruns ranging from 24.4% to 514.71%. Furthermore, 21.73% of projects experienced cost overruns, with the highest at 19.92%. These findings provide critical insights for improving project management and addressing construction time overruns. It recommends conducting national-scale analyses to gain a comprehensive understanding of construction delays and to implement effective mitigation strategies.
引用
收藏
页数:13
相关论文
共 49 条
  • [1] Causes of time and cost overruns in construction projects: a scoping review
    Gomez-Cabrera, Adriana
    Gutierrez-Bucheli, Laura
    Munoz, Santiago
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2024, 24 (10) : 1107 - 1125
  • [2] Time overruns in the construction projects in Iraq: Case study on investigating and analyzing the root causes
    Al Kulabi, Ahmed Kamil
    Atiea, Huda M. Jawad
    OPEN ENGINEERING, 2022, 12 (01): : 702 - 715
  • [3] An integrated approach to investigate the causes of time delays and cost overruns in Afghanistan construction projects
    Sadat, Hafizullah
    Thomas, Nivea
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2024,
  • [4] Assessing the causes of project overruns in tunnel construction projects in Pakistan
    Ayat, Muhammad
    Rehman, Hafeezur
    Qureshi, Sheheryar Mohsin
    Kang, Chang Wook
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2023, 23 (11) : 1856 - 1866
  • [5] Major causes of construction time and cost overruns: A case of selected educational sector projects in Ghana
    Famiyeh S.
    Amoatey C.T.
    Adaku E.
    Agbenohevi C.S.
    Journal of Engineering, Design and Technology, 2017, 15 (02) : 181 - 198
  • [6] CONSTRUCTION CLAIMS AND DISPUTES - CAUSES AND COST/TIME OVERRUNS
    SEMPLE, C
    HARTMAN, FT
    JERGEAS, G
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1994, 120 (04): : 785 - 795
  • [7] Theoretical framework of the causes of construction time and cost overruns
    Ullah, K.
    Abdullah, A. H.
    Nagapan, S.
    Suhoo, S.
    Khan, M. S.
    GLOBAL CONGRESS ON CONSTRUCTION, MATERIAL AND STRUCTURAL ENGINEERING 2017 (GCOMSE2017), 2017, 271
  • [8] Construction claims and disputes: causes and cost/time overruns
    Semple, Cheryl
    Hartman, Francis T.
    Jergeas, George
    Journal of Construction Engineering and Management, 1994, 120 (04) : 785 - 795
  • [9] Factors influencing Time and Cost Overruns on Freeform Construction Projects
    Kavuma, Andrew
    Ock, Jongho
    Jang, Hyounseung
    KSCE JOURNAL OF CIVIL ENGINEERING, 2019, 23 (04) : 1442 - 1450
  • [10] Factors influencing Time and Cost Overruns on Freeform Construction Projects
    Andrew Kavuma
    Jongho Ock
    Hyounseung Jang
    KSCE Journal of Civil Engineering, 2019, 23 : 1442 - 1450