Simulation-based hybrid genetic algorithms for the stochastic multi-mode resource-constrained project scheduling problem with minimized financial risk

被引:2
|
作者
Liu, Wanlin [1 ]
Zhang, Haotian [1 ]
Chen, Yumeng [1 ]
Qu, Chunli [1 ,3 ]
Zhang, Jingwen [2 ]
机构
[1] Sichuan Agr Univ, Sch Architecture & Urban Rural Planning, Chengdu 611830, Peoples R China
[2] Northwestern Polytech Univ, Sch Management, Xian 710072, Peoples R China
[3] Sch Architecture & Urban Rural Planning, 288 Jianshe Rd, Chengdu 611830, Sichuan, Peoples R China
关键词
Stochastic multi-mode project scheduling; Conditional net present value at risk; Simulation-based hybrid genetic algorithms; NET PRESENT VALUE; CASH FLOWS; OPTIMIZATION; UNCERTAINTY; NETWORKS; MAXIMIZE;
D O I
10.1016/j.asoc.2024.111716
中图分类号
TP18 [人工智能理论];
学科分类号
081104 ; 0812 ; 0835 ; 1405 ;
摘要
Projects face uncertainties during implementation, and these uncertainties often lead to risk factors that disrupt successful project execution and cause a loss of profit. The stochastic project scheduling technique has been an effective avenue for reducing the risks in project management. Nevertheless, previous studies often neglected resource limits for minimizing the financial risks of projects in stochastic project scheduling problems. This study aims to optimize the conditional net present value at risk (CNPVaR), which measures a project's expected loss of net present value (NPV) in a stochastic multi-mode resource-constrained project scheduling problem (SMRCPSP). Accordingly, considering the stochastic activity duration and cash flow, we construct a scenario-based optimization model for the SMRCPSP, where the solution (strategy) of the SMRCPSP is represented by a policy that includes an activity list and execution mode list; a scheduling policy is then employed to map the start times of activities at each decision time based on the solution. Three simulation-based hybrid genetic algorithms embedded with different iteration alternatives according to activity-based (AB) or resource-based (RB) scheduling policies are used. Furthermore, computational experiments are conducted to evaluate the proposed procedures through 480 instances. With respect to the CNPVaR, expected NPV, and algorithm stability metrics, the results of the experiments demonstrate that the genetic algorithm (GA) with local search based on the RB scheduling policy performed best compared with two other hybrids of the GA, the existing vibration damping optimization (VDO) method and a pure GA for large-sized projects. However, the VDO outperforms the other approaches according to the AB scheduling policy for small-scale projects. Additionally, a case study is conducted; the findings demonstrate that the risk attitude (confidence level) of project managers and the discount factor have impacts on the CNPVaR and expected NPV, but the CNPVaR is insensitive to the number of simulations.
引用
收藏
页数:20
相关论文
共 50 条
  • [1] Solving the multi-mode resource-constrained project scheduling problem with genetic algorithms
    Alcaraz, J
    Maroto, C
    Ruiz, R
    JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 2003, 54 (06) : 614 - 626
  • [2] Hybrid genetic algorithm for multi-mode resource-constrained project scheduling problems
    School of Economics and Management, Southeast University, Nanjing 210096, China
    Dongnan Daxue Xuebao, 2008, 4 (736-740):
  • [3] SIMULATION-BASED MULTI-MODE RESOURCE-CONSTRAINED PROJECT SCHEDULING OF SEMICONDUCTOR EQUIPMENT INSTALLATION AND QUALIFICATION
    Cheng, Junzilan
    Fowler, John
    Kempf, Karl
    2012 WINTER SIMULATION CONFERENCE (WSC), 2012,
  • [4] Hybrid Heuristics for Multi-mode Resource-Constrained Project Scheduling
    Tchao, Celso
    Martins, Simone L.
    LEARNING AND INTELLIGENT OPTIMIZATION, 2008, 5313 : 234 - +
  • [5] The Multi-Mode Resource-Constrained Multi-Project Scheduling Problem
    Wauters, Tony
    Kinable, Joris
    Smet, Pieter
    Vancroonenburg, Wim
    Vanden Berghe, Greet
    Verstichel, Jannes
    JOURNAL OF SCHEDULING, 2016, 19 (03) : 271 - 283
  • [6] A hybrid genetic algorithm and fuzzy set applied to multi-mode resource-constrained project scheduling problem
    Vartouni, Ali Moradi
    Khanli, Leyli Mohammad
    JOURNAL OF INTELLIGENT & FUZZY SYSTEMS, 2014, 26 (03) : 1103 - 1112
  • [7] A hybrid approach for solving multi-mode resource-constrained project scheduling problem in construction
    Roslon, Jerzy Hubert
    Kulejewski, Janusz Edward
    OPEN ENGINEERING, 2019, 9 (01): : 7 - 13
  • [8] Multi-mode resource-constrained project scheduling problem with alternative project structures
    Tao, Sha
    Dong, Zhijie Sasha
    COMPUTERS & INDUSTRIAL ENGINEERING, 2018, 125 : 333 - 347
  • [9] Modeling of the flexible resource-constrained multi-mode project scheduling problem
    School of Management, Wuhan University of Technology, Wuhan 430070, China
    不详
    Wuhan Ligong Daxue Xuebao, 2008, 11 (176-179+188):
  • [10] Multi-mode resource-constrained project scheduling problem with activities overlapping
    Chu Z.
    Xu Z.
    Yu J.
    Xu, Zhe (xuzhebuaa@163.com), 1600, CIMS (23): : 557 - 566