Impact Analysis on Existing High-speed Railway Tunnel by the Construction of New Tunnel-Overpass

被引:0
|
作者
Pan Wei-dong [1 ]
Chen Jian-gang [1 ]
Ou Wen-jun [2 ]
机构
[1] South China Univ Technol, Sch Civil Engn & Transportat, Guangzhou 510641, Guangdong, Peoples R China
[2] China Railway 12Th Bur Grp, Engn Co LTD 4, Xian 710000, Shaanxi, Peoples R China
来源
关键词
cross project; numerical simulation; net distance; cross angle;
D O I
暂无
中图分类号
P5 [地质学];
学科分类号
0709 ; 081803 ;
摘要
In order to study the influence of the deformation and stress of the existing tunnel structure under different distance and cross angles, the actual project in Fuzhou city was taken to analyze. The finite element analysis software was used to construct the three-dimensional finite element model for numerical calculation, and obtained a variation curves of vertical displacement and stress at different distances and angles. Numerical results show that: (1) When the distance is 1.5 times less than the diameter of the new tunnel, the maximum vertical deformation of the existing tunnel occurs at the intersection of the two tunnels. When the distance is 1.5 times more than the diameter of the new tunnel, the maximum deformation of the existing tunnel is gradually moving toward the center of the existing tunnel. (2) The influence of the first principal stress and the deformation of the existing tunnel is mainly affected by the distance, and the cross angle has little effect. May the research results can provide some reference for the design and construction of similar projects.
引用
收藏
页码:5627 / 5639
页数:13
相关论文
共 50 条
  • [21] Comprehensive prediction of rockburst in high-speed railway tunnel
    Li, Bo
    Wu, Li
    Xu, Changmao
    Li, Zhigang
    Zuo, Qingjun
    APPLIED MECHANICS AND MATERIALS II, PTS 1 AND 2, 2014, 477-478 : 553 - +
  • [22] THE GRAUHOLZ HIGH-SPEED RAILWAY TUNNEL IN DIFFICULT GROUND
    STEINER, W
    TUNNELS AND WATER, VOLS 1-3: WATER AND ITS INFLUENCE ON THE DESIGN, CONSTRUCTION, AND EXPLOITATION OF TUNNELS AND UNDERGROUND WORKS, 1989, : 333 - 339
  • [23] First application of the Pretunnel system for the construction of a tunnel in the high-speed railway line in Italy
    Brino, L
    Pagliacci, F
    Campa, E
    Pelizza, S
    TUNNELS FOR PEOPLE, VOLS 1 AND 2, 1997, : 311 - 316
  • [24] Risk assessment of high-speed railway tunnel construction based on fuzzy synthetic evaluation
    Wu, Li
    Zhang, Lianggang
    Lai, Yun
    Chen, Jian
    ADVANCES IN INDUSTRIAL AND CIVIL ENGINEERING, PTS 1-4, 2012, 594-597 : 1251 - 1256
  • [25] Safety of Existing Intersection High-Speed Railway Trains Under the Condition of Sheild Tunnel Penetration Construction Considering the Stochastic Field
    Tang Q.
    Peng L.
    Deng E.
    Lei M.
    Wu B.
    Shi C.
    Huanan Ligong Daxue Xuebao/Journal of South China University of Technology (Natural Science), 2024, 52 (04): : 95 - 103
  • [26] Karst Hydrogeological Characteristics and Construction Disease Analysis of a High - speed Railway Tunnel
    Fu, Kailong
    Zhou, Yu
    Wei, Zhengxiong
    Wang, Zhijun
    Journal of Railway Engineering Society, 2023, 40 (10) : 86 - 92
  • [27] Controlled blasting for a new tunnel near an existing railway tunnel
    Gupta, R. N.
    Raina, A. K.
    TUNNELLING IN ROCK BY DRILLING AND BLASTING, 2013, : 37 - 39
  • [28] Modeling and analysis of traction network of high-speed railway tunnel/viaduct sections
    Zhang, Gui-Nan
    Liu, Zhi-Gang
    Guo, Xiao-Xu
    Gao, Shi-Bin
    Tiedao Xuebao/Journal of the China Railway Society, 2015, 37 (11): : 16 - 24
  • [29] Aerodynamic load and structure stress analysis on hood of high-speed railway tunnel
    Wang Y.
    Gao B.
    Ren W.
    2017, Chinese Society of Theoretical and Applied Mechanics (49): : 48 - 54
  • [30] Inversion Analysis of Mechanical Parameters of Surrounding Rock in High-speed Railway Tunnel
    Wang, Hao
    Chang, Xiangyu
    Zhang, Yiming
    Liang, Ruijun
    Wang, Feiqiu
    Tao, Lei
    Li, Zhaozhong
    Journal of Railway Engineering Society, 2020, 37 (09) : 47 - 53