The accuracy of risk-based cost estimation for water infrastructure projects: preliminary evidence from Australian projects

被引:28
|
作者
Liu, Li [1 ]
Napier, Zigrid [2 ]
机构
[1] Univ Sydney, Dept Civil Engn, Civil Engn Bldg J05, Sydney, NSW 2006, Australia
[2] Evans & Peck, Sydney, NSW, Australia
关键词
Cost estimating; forecasting; accuracy; risk-based estimating; fixed contingency approach;
D O I
10.1080/01446190903431525
中图分类号
F [经济];
学科分类号
02 ;
摘要
Infrastructure projects are still being plagued by cost overruns, delays and revenue shortfalls despite decades of practice and research. Risk-based estimating (RBE) is growing in popularity and has the potential to overcome the two main cost overrun factors-optimistic bias and strategic misrepresentation. Yet, little is known about the accuracy of RBE and its performance drivers. A comparison of water projects using RBE with a sample of construction projects using the conventional estimating approach shows that the projects estimated using RBE have better estimation accuracy than those estimated using more conventional approaches. In addition, the projects using RBE appear more likely to be under-budget while the ones using the conventional approach appear more likely to be over-budget. Further, through interviews and observations of the RBE process, three main performance drivers for the RBE method were identified to include outside view/collective experience, attention focusing and probabilistic, bottom-up modelling.
引用
收藏
页码:89 / 100
页数:12
相关论文
共 50 条
  • [21] Risk-based approach to unbalanced bidding in construction projects
    Afshar, Abbas
    Amiri, Helia
    ENGINEERING OPTIMIZATION, 2010, 42 (04) : 369 - 385
  • [22] A risk-based entry decision model for international projects
    Seung Heon Han
    KSCE Journal of Civil Engineering, 2001, 5 (1) : 87 - 96
  • [23] (Un)bundling infrastructure procurement: Evidence from water supply and sewage projects
    Estache, Antonio
    Iimi, Atsushi
    UTILITIES POLICY, 2011, 19 (02) : 104 - 114
  • [24] A bibliometric review of the statistical modelling techniques for cost estimation of infrastructure projects
    Atapattu, Chinthaka Niroshan
    Domingo, Niluka
    Sutrisna, Monty
    SMART AND SUSTAINABLE BUILT ENVIRONMENT, 2023,
  • [25] Risk-Based Completion Cost Overrun Ratio Estimation in Construction Projects Using Machine Learning Classification Algorithms: A Case Study
    Turkyilmaz, Aynur Hurriyet
    Polat, Gul
    BUILDINGS, 2024, 14 (11)
  • [26] Public-Private Partnerships: A Fresh Risk-Based Approach to Water Sector Projects
    Lima, Sonia
    Brochado, Ana
    Marques, Rui Cunha
    INFRASTRUCTURES, 2023, 8 (06)
  • [27] Risk Identification of Public Infrastructure Projects Based on VFPE
    Cheng Haifang
    Jiang Shimiao
    Zou Danfeng
    2010 2ND INTERNATIONAL CONFERENCE ON COMPUTER AND AUTOMATION ENGINEERING (ICCAE 2010), VOL 4, 2010, : 173 - 176
  • [28] Knowledge-based risk identification in infrastructure projects
    De Zoysa, S
    Russell, AD
    CANADIAN JOURNAL OF CIVIL ENGINEERING, 2003, 30 (03) : 511 - 522
  • [29] Cost-influencing risk factors in infrastructure projects on soft soils
    Low, Wai Wah
    Wong, Kwong Soon
    Lee, Jun Liang
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2019, : 229 - 241
  • [30] Cost Risk in Water and Sewerage Systems Construction Projects
    Rybka, Iwona
    Bondar-Nowakowska, Elzbieta
    Polonski, Mieczyslaw
    WORLD MULTIDISCIPLINARY CIVIL ENGINEERING-ARCHITECTURE-URBAN PLANNING SYMPOSIUM 2016, WMCAUS 2016, 2016, 161 : 163 - 167