A model for resource-constrained project scheduling using adaptive PSO

被引:2
|
作者
Neetesh Kumar
Deo Prakash Vidyarthi
机构
[1] Jawaharlal Nehru University,School of Computer and Systems Sciences
来源
Soft Computing | 2016年 / 20卷
关键词
Particle swarm optimization; NP-hard; Heuristics ; Resource-constrained project scheduling problem; Makespan;
D O I
暂无
中图分类号
学科分类号
摘要
Resource-constrained project scheduling problem (RCPSP) is an important, but computationally hard problem. Particle swarm optimization (PSO) is a well-known and highly used meta-heuristics to solve such problems. In this work, a simple, effective and improved version of PSO i.e. adaptive-PSO (A-PSO) is proposed to solve the RCPSP. Conventional canonical PSO is improved at two points; during the particle’s position and velocity updation, due to dependent activities in RCPSP, a high possibility arises for the particle to become invalid. To overcome this, an important operator named valid particle generator (VPG) is proposed and embedded into the PSO which converts an invalid particle into a valid particle effectively with the knowledge of the in-degree and out-degree of the activities depicted by the directed acyclic graph. Second, inertia weight (ω)\documentclass[12pt]{minimal} \usepackage{amsmath} \usepackage{wasysym} \usepackage{amsfonts} \usepackage{amssymb} \usepackage{amsbsy} \usepackage{mathrsfs} \usepackage{upgreek} \setlength{\oddsidemargin}{-69pt} \begin{document}$$(\omega )$$\end{document} that plays a significant role in the quick convergence of the PSO is adaptively tuned by considering the effects of fitness value, previous value of ω\documentclass[12pt]{minimal} \usepackage{amsmath} \usepackage{wasysym} \usepackage{amsfonts} \usepackage{amssymb} \usepackage{amsbsy} \usepackage{mathrsfs} \usepackage{upgreek} \setlength{\oddsidemargin}{-69pt} \begin{document}$$\omega $$\end{document} and iteration counter. Performance of the model is evaluated on the standard benchmark data of the RCPSP problem. Results show the effectiveness of the proposed model in comparison to other existing state of the art model that uses heuristics/meta-heuristics. The proposed model has the potential to be applied to other similar problems.
引用
收藏
页码:1565 / 1580
页数:15
相关论文
共 50 条
  • [41] The proactive and reactive resource-constrained project scheduling problem
    Morteza Davari
    Erik Demeulemeester
    Journal of Scheduling, 2019, 22 : 211 - 237
  • [42] Periodically aggregated resource-constrained project scheduling problem
    Morin, Pierre-Antoine
    Artigues, Christian
    Hait, Alain
    EUROPEAN JOURNAL OF INDUSTRIAL ENGINEERING, 2017, 11 (06) : 792 - 817
  • [43] MILP Formulation for Resource-Constrained Project Scheduling Problems
    Kyriakidis, Thomas S.
    Kopanos, Georgios M.
    Georgiadis, Michael C.
    21ST EUROPEAN SYMPOSIUM ON COMPUTER AIDED PROCESS ENGINEERING, 2011, 29 : 880 - 884
  • [44] Ant colony optimization for resource-constrained project scheduling
    Merkle, D
    Middendorf, M
    Schmeck, H
    IEEE TRANSACTIONS ON EVOLUTIONARY COMPUTATION, 2002, 6 (04) : 333 - 346
  • [45] Integration of routing into a resource-constrained project scheduling problem
    Lacomme, Philippe
    Moukrim, Aziz
    Quilliot, Alain
    Vinot, Marina
    EURO JOURNAL ON COMPUTATIONAL OPTIMIZATION, 2019, 7 (04) : 421 - 464
  • [46] An efficient hybrid algorithm for resource-constrained project scheduling
    Chen, Wang
    Shi, Yan-jun
    Teng, Hong-fei
    Lan, Xiao-ping
    Hu, Li-chen
    INFORMATION SCIENCES, 2010, 180 (06) : 1031 - 1039
  • [47] Memetic algorithm for the resource-constrained project scheduling problem
    Chen, Di
    Liu, Shixin
    Qin, Shujin
    2014 11TH WORLD CONGRESS ON INTELLIGENT CONTROL AND AUTOMATION (WCICA), 2014, : 4991 - 4996
  • [48] A Flexible Heuristic Algorithm for Resource-Constrained Project Scheduling
    Seda, Milos
    Matousek, Radomil
    Osmera, Pavel
    Pivonka, Petr
    Sandera, Cenek
    WCECS 2009: WORLD CONGRESS ON ENGINEERING AND COMPUTER SCIENCE, VOLS I AND II, 2009, : 730 - +
  • [49] SMT encodings for Resource-Constrained Project Scheduling Problems
    Bofill, Miquel
    Coll, Jordi
    Suy, Josep
    Villaret, Mateu
    COMPUTERS & INDUSTRIAL ENGINEERING, 2020, 149
  • [50] Population learning algorithm for resource-constrained project scheduling
    Jedrzejowicz, P
    Ratajczak, E
    ARTIFICIAL NEURAL NETS AND GENETIC ALGORITHMS, PROCEEDINGS, 2003, : 223 - 228