Development of a risk assessment tool for deep geothermal projects: example of application in the Paris Basin and Upper Rhine graben

被引:0
|
作者
Julie Maury
Virginie Hamm
Annick Loschetter
Thomas Le Guenan
机构
[1] BRGM,
来源
Geothermal Energy | / 10卷
关键词
Risk assessment; Risk matrix; Deep geothermal; Upper Trias; Paris Basin; Upper Rhine graben;
D O I
暂无
中图分类号
学科分类号
摘要
This paper presents the development of a tool to perform risk assessment for deep geothermal projects. The tool is aimed at project developers to help them present their project to local authority, decision-makers and financers so they can highlight how they take into account risks and consider mitigation measures to minimize them. The main criteria for this tool are the simplicity of use, the quality of presentation and flexibility. It is based on results from the H2020 GEORISK project that identified risks that apply to geothermal projects and proposed insurance schemes all over Europe. A characteristic of this tool is that it considers all the categories of risks that a project may face, including geological, technical, environmental risks as well as risks related to the social, economic and political contexts. The tool can be customized: selection of risks in a list that can be completed, adaptable rating scheme for risk analysis, possibility to choose the best display for results depending on the user needs. Two case applications are presented, one in the Paris Basin considering a doublet targeting the Upper Trias, a geological layer that presents some technical challenges; and one in the Upper Rhine graben targeting a fault zone, where the risk of induced seismicity must be carefully considered. A posteriori risk assessment highlights the main issues with these types of projects, and the comparison between the two cases emphasizes the flexibility of the tool, as well as, the different ways to present the results depending on the objective of the analyses.
引用
收藏
相关论文
共 50 条
  • [31] Characterisation of the Upper Jurassic geothermal reservoir in the South German Molasse Basin as basis for a potential assessment to foster the geothermal installation development – Results from the joint research project Geothermal Alliance Bavaria
    Zosseder K.
    Pfrang D.
    Schölderle F.
    Bohnsack D.
    Konrad F.
    Geomechanik und Tunnelbau, 2022, 15 (01): : 17 - 24
  • [32] Design and implementation of project time management risk assessment tool for SME projects using oracle application express
    Sharif, Abdullahi Mohamud
    Rozan, Mohd Zaidi Abd
    World Academy of Science, Engineering and Technology, 2010, 41 : 1221 - 1226
  • [33] Towards climate-adaptive development of small hydropower projects in Himalaya: A multi-model assessment in upper Beas basin
    Shirsat, Tejal S.
    Kulkarni, Anil, V
    Momblanch, Andrea
    Randhawa, S. S.
    Holman, Ian P.
    JOURNAL OF HYDROLOGY-REGIONAL STUDIES, 2021, 34
  • [34] Development and Field Evaluation of a Spray Drift Risk Assessment Tool for Vineyard Spraying Application
    Bourodimos, Georgios
    Koutsiaras, Michael
    Psiroukis, Vasilios
    Balafoutis, Athanasios
    Fountas, Spyros
    AGRICULTURE-BASEL, 2019, 9 (08):
  • [35] DEVELOPMENT AND APPLICATION OF A RISK ASSESSMENT-TOOL (RISKAT) IN THE HEALTH-AND-SAFETY-EXECUTIVE
    HURST, NW
    NUSSEY, C
    PAPE, RP
    CHEMICAL ENGINEERING RESEARCH & DESIGN, 1989, 67 (04): : 362 - 372
  • [36] Risk assessment and prediction tool. Translation and adaptation to the Italian reality and possible role in the development of rehabilitation projects
    Levroni, L.
    Marini, M. L.
    Belluati, A.
    PROCEEDINGS OF THE XI EUROPEAN CONGRESS OF THE EUROPEAN FEDERATION FOR RESEARCH IN REHABILITATION, 2011, : 96 - 100
  • [37] A Novel Method for Evaluation of Flood Risk Reduction Strategies: Explanation of ICPR FloRiAn GIS-Tool and Its First Application to the Rhine River Basin
    Schmid-Breton, Adrian
    Kutschera, Gesa
    Botterhuis, Ton
    GEOSCIENCES, 2018, 8 (10)
  • [38] Development and application of a novel method for regional assessment of groundwater contamination risk in the Songhua River Basin
    Nixdorf, Erik
    Sun, Yuanyuan
    Lin, Mao
    Kolditz, Olaf
    SCIENCE OF THE TOTAL ENVIRONMENT, 2017, 605 : 598 - 609
  • [39] Economic Project Risk Assessment in Remediation Projects Prior to Construction: Methodology Development and Case Study Application
    Brinkhoff, Petra
    Norin, Malin
    Norrman, Jenny
    Rosen, Lars
    Ek, Kristine
    REMEDIATION-THE JOURNAL OF ENVIRONMENTAL CLEANUP COSTS TECHNOLOGIES & TECHNIQUES, 2015, 25 (02): : 117 - 138
  • [40] A Study on the Application of a Deep Thermal Reservoir by Using a Magnetotelluric Sounding Method: Taking an Example of Geothermal Resources’ Exploration in the Western Taikang Uplift of the Southern North China Basin
    Xu, Bowen
    Zhu, Huailiang
    Zhang, Min
    Yang, Zhongyan
    Ye, Gaofeng
    Liu, Zhilong
    Hu, Zhiming
    Shao, Bingsong
    Zhang, Yuqi
    Processes, 2024, 12 (12)