摘要
The optimal performance of power grid depends on many factors, and one of which is the reliability of the substation communication network. These substation communication networks are required for real time monitoring and control of the power grid. Power grid operators are always eager to know the behavior of the substation communication network to enable the operators perform real time monitoring and control function of the power grid through the communication network. Substation communication network historical data and real time operating data are vital requirements for effective design of a robust and reliable communication network. These communication networks historical data are also required for predicting future performance of the grid network. This paper has demonstrated the successful use of communication network collected data (that is historical data) to determine the reliability and performance of an IEC 61850 substation communication network. The key findings of this study are that increased data rate of an IEC 61850 based communication network, reduces the network latency and the implementation of network redundancy scheme improved the network reliability. Also, increased data rate and implementation of network redundancy scheme improved the derived communication network reliability averagely by 3.8% over fifteen years period. The derived communication network improved reliability was also found to meets the IEC 61850 transfer time requirements required for performing substation protection, monitoring and control functions.
引用
收藏
页码:678 / 684
页数:7
相关论文
共 50 条
  • [21] Reliability of substation protection system based on IEC61850
    Xiong X.
    Yu J.
    Liu X.
    Shen Z.
    Transactions of Tianjin University, 2008, 14 (2) : 118 - 122
  • [22] Reliability of Substation Protection System Based on IEC61850
    熊小伏
    于军
    刘晓放
    沈智健
    Transactions of Tianjin University, 2008, (02) : 118 - 122
  • [23] A Fuzzy Cognitive Map for Data Integrity Assessment in a IEC 61850 Based Substation
    Mohagheghi, S.
    IEEE POWER AND ENERGY SOCIETY GENERAL MEETING 2010, 2010,
  • [24] Improving the performance and reliability of IEC 61850 based substation using backup IED concept
    Ali, Syed Afroz
    Thomas, Mini S.
    Rana, Ankur Singh
    2015 ANNUAL IEEE INDIA CONFERENCE (INDICON), 2015,
  • [25] Experimental Performance Analysis of DER Network Communication in IEC 61850 Server
    Yoo, Yoon-Sik
    Lee, Il-Woo
    Choi, Jun Kyun
    2016 IEEE INTERNATIONAL CONFERENCE ON CONSUMER ELECTRONICS (ICCE), 2016,
  • [26] Analysis of an IEC 61850 based Electric Substation Communication Architecture
    Gore, Rahul
    Satheesh, Hariram
    Varier, Mahesh
    Valsan, Simi
    2016 7TH INTERNATIONAL CONFERENCE ON INTELLIGENT SYSTEMS, MODELLING AND SIMULATION (ISMS), 2016, : 388 - 393
  • [27] Communication Protocols in Substation Automation and IEC 61850 based proposal
    Horalek, J.
    Matyska, J.
    Sobeslav, V.
    14TH IEEE INTERNATIONAL SYMPOSIUM ON COMPUTATIONAL INTELLIGENCE AND INFORMATICS (CINTI), 2013, : 321 - 326
  • [28] Modelling and simulation for performance evaluation of IEC61850-Based substation communication systems
    Sidhu, Tarlochan S.
    Yin, Yujie
    IEEE TRANSACTIONS ON POWER DELIVERY, 2007, 22 (03) : 1482 - 1489
  • [29] Mapping of IEC 61850 to Data Distribute Service for Digital Substation Communication
    Bi, Y. B.
    Jiang, L.
    Wang, X. J.
    Cui, L. Z.
    2013 IEEE POWER AND ENERGY SOCIETY GENERAL MEETING (PES), 2013,
  • [30] Mapping of IEC 61850 to data distribute service for smart substation communication
    Bi, Y. (byb@liv.ac.uk), 1600, Chinese Society for Electrical Engineering (33):