Calculation of surrounding rock pressure of large section underground excavation metro station based on the construction process

被引:2
|
作者
Zhang, Y. T. [1 ]
Jin, X. G. [2 ]
Dai, Y. J. [1 ]
Li, H. L. [2 ]
Yang, W. G. [1 ]
机构
[1] China Construct Tunnel Construct Co Ltd, Chongqing, Peoples R China
[2] Chongqing Univ, Sch Civil Engn, Chongqing, Peoples R China
关键词
Large Section Tunnel; Construction Process; The pressure of surrounding strata; Numerical Simulation;
D O I
10.1088/1755-1315/626/1/012009
中图分类号
X [环境科学、安全科学];
学科分类号
08 ; 0830 ;
摘要
The traditional calculation method of the surrounding strata pressure of the tunnel does not consider the tunnel construction process. The excavation of the large-section tunnel mostly adopts the section excavation method, which is to excavate and support at the same time. The stress state of the pressure of surrounding strata changes gradually during the excavation process. The traditional calculation results of tunnel surrounding strata pressure are generally large. In this paper, the large-section tunnel is simplified into three parts, and the degree of influence (eta(1), eta(2), eta(3)) of the excavation height h and width b of the advance pilot hole and the distance d between the advance and rear pilot tunnels on the surrounding rock pressure calculation are analyzed. The regression equation for calculating the influencing factors (tunnel depth H, tunnel span B, internal friction angle phi, and rock weight gamma) of surrounding rock pressure (p) is established. Through the numerical analysis, the influence coefficient eta is obtained, the weight coefficient is introduced, and the computing formula of the pressure of surrounding strata of the large-section tunnel excavation is derived. The formula is used to the computing of the pressure of surrounding strata with a large-section subway station and the correct conclusion is obtained.
引用
收藏
页数:9
相关论文
共 50 条
  • [41] A classification method of surrounding rock mass quality based on tunnel milling excavation construction adaptability
    Cao W.
    Li S.
    Zhang Y.
    Yanshilixue Yu Gongcheng Xuebao/Chinese Journal of Rock Mechanics and Engineering, 2019, 38 (08): : 1513 - 1522
  • [42] Model test on mechanical characteristics of surrounding rock during construction process of super-large section tunnel in complex strata
    Liu Cong
    Li Shu-cai
    Zhou Zong-qing
    Li Li-ping
    Wang Kang
    Hou Fu-jin
    Qin Cheng-shuai
    Gao Cheng-lu
    ROCK AND SOIL MECHANICS, 2018, 39 (09) : 3495 - 3504
  • [43] Damage analysis and deformation early warning of surrounding rock mass during top arch excavation of underground powerhouse of Shuangjiangkou hydropower station
    Qian B.
    Xu N.
    Xiao P.
    Zhao T.
    Dong L.
    Yanshilixue Yu Gongcheng Xuebao/Chinese Journal of Rock Mechanics and Engineering, 2019, 38 (12): : 2512 - 2524
  • [44] Case Record Of Phase 1 Of Kaohsiung Metro– Geotechnical Design And Construction Of A Large-Scale Underground Station
    Hsiung B.C.B.
    Chung L.J.
    Lin M.C.
    Hsiung, Bin Chen Benson (benson@nkust.edu.tw), 1600, Taiwan Geotechnical Society (15): : 205 - 214
  • [45] Study on in-situ monitoring of the surrounding rock pressure of the shallow large-span tunnel in the tunnel construction process
    Li, Xinzhi
    Li, Shucai
    Li, Yingyong
    Li, Shuchen
    MATERIALS SCIENCE AND ENGINEERING APPLICATION II, 2012, 413 : 454 - 458
  • [46] Experimental study and prediction on large section tunnel construction deformation of surrounding rock in soft ground
    Su D.
    Luo J.
    Yanshilixue Yu Gongcheng Xuebao/Chinese Journal of Rock Mechanics and Engineering, 2016, 35 : 4029 - 4039
  • [47] Determination Method of Excavation Damage Zone Based on Surrounding Rock Damage-Fracture Ratio in Underground Engineering
    Guo, Haosen
    Tong, Jiaqi
    Sun, Qiancheng
    Yang, Xu
    Luo, Wenjun
    Yu, Yang
    FRONTIERS IN EARTH SCIENCE, 2022, 10
  • [48] Construction methods for loess tunnels with super-large cross-section based on displacement control of surrounding rock
    Cheng, X.-S. (cxs702@126.com), 1600, Chinese Society of Civil Engineering (35):
  • [49] Stability Analysis of Surrounding Rock of an Underground Cavern Group and Excavation Scheme Optimization: Based on an Optimized DDARF Method
    Ma, Hai-Ping
    Daud, Nik Norsyahariati Nik
    Yusof, Zainuddin Md
    Yaacob, Wan Zuhairi
    He, Hu-Jun
    APPLIED SCIENCES-BASEL, 2023, 13 (04):
  • [50] Calculation of Shield Tunnel Vertical Surrounding Rock Pressure Based on Dimensional Analysis
    Wu, Qixing