Using field data and operational constraints to maximize hard rock TBM penetration and advance rates

被引:5
|
作者
Farrokh, Ebrahim [1 ]
机构
[1] Amirkabir Univ Technol, Tehran Polytech, Tehran, Iran
关键词
TBM; cutterhead; cutter spacing; layout design; cutting force; optimization; LINEAR CUTTING TESTS; DISC CUTTER; CONFINING STRESS; PERFORMANCE; EFFICIENCY; FRAGMENTATION; EXCAVATION; SANDSTONE; GRANITE;
D O I
10.1016/j.tust.2022.104506
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
In this paper, the influence of rock type and uniaxial compressive strength on the cutter penetration is inves-tigated to provide a basic guideline for the optimum field cutter spacing. The successfully utilized cutterhead layout designs are also studied in various rock types and different categories of tunnel sizes for projects with relatively high performance. The results of the conducted analyses show that the maximum cutter penetration in uniaxial compressive strength values below 50 and above 150 MPa is achieved when the cutter spacing is close to 90 and below 80 mm respectively. The study on the layout design characteristics of the cutterhead shows the evenly distributed scheme is more used with success even in softer rocks (when the rock mass condition is good). In softer rocks, the extension of the openings may have to be well over 50% of the cutterhead radius to maximize its performance. It is also found that the linear speed of the cutters has a direct correlation with two major parameters of normal force index (NFI) and rolling force index (RFI). In this regard, two formulas are generated using statistical analysis of the data from around 260 tunnel projects to evaluate both NFI and RFI. The corre-sponding formulas have coefficients of determination of 77 and 68% respectively. These formulas are used in an optimization process to maximize cutter penetration using various operational constraints (cutter load capacity, cutterhead torque limit, cutter geometry constrains, and cutterhead penetration rate limits). The new findings of this study can provide a foundation to improve the design process of hard rock TBMs and to optimize their performance considering various project setting parameters.
引用
收藏
页数:18
相关论文
共 50 条
  • [21] Influence of Subjectivity in Geological Mapping on the Net Penetration Rate Prediction for a Hard Rock TBM
    Seo, Yongbeom
    Macias, Francisco Javier
    Jakobsen, Pal Drevland
    Bruland, Amund
    ROCK MECHANICS AND ROCK ENGINEERING, 2018, 51 (05) : 1599 - 1613
  • [22] A new model for predicting the advance rate of a Tunnel Boring Machine (TBM) in hard rock conditions
    Arbabsiar, Mohammad Hossein
    Farsangi, Mohammad Ali Ebrahimi
    Mansouri, Hamid
    RUDARSKO-GEOLOSKO-NAFTNI ZBORNIK, 2020, 35 (02): : 57 - 74
  • [23] Performance prediction of hard rock TBM using Rock Mass Rating (RMR) system
    Hamidi, Jafar Khademi
    Shahriar, Kourosh
    Rezai, Bahram
    Rostami, Jamal
    TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2010, 25 (04) : 333 - 345
  • [24] A study of various models used in the estimation of advance rates for hard rock TBMs
    Farrokh, Ebrahim
    TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2020, 97
  • [25] Determination of the system behaviour based on data analysis of a hard rock shield TBM
    Analyse der Maschinenparameter zur Erfassung des Systemverhaltens beim Hartgesteins-Schildvortrieb
    1600, Ernst und Sohn (07):
  • [26] Prediction of TBM cutterhead speed and penetration rate for high-efficiency excavation of hard rock tunnel using CNN-LSTM model with construction big data
    Long Li
    Zaobao Liu
    Hongyuan Zhou
    Jing Zhang
    Wanqing Shen
    Jianfu Shao
    Arabian Journal of Geosciences, 2022, 15 (3)
  • [27] Hard rock TBM tunneling in challenging ground: Developments and lessons learned from the field
    Home, Lok
    TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2016, 57 : 27 - 32
  • [28] Forecasting of TBM advance rate in hard rock condition based on artificial neural network and genetic programming techniques
    Jian Zhou
    Behnam Yazdani Bejarbaneh
    Danial Jahed Armaghani
    M. M. Tahir
    Bulletin of Engineering Geology and the Environment, 2020, 79 : 2069 - 2084
  • [29] Forecasting of TBM advance rate in hard rock condition based on artificial neural network and genetic programming techniques
    Zhou, Jian
    Bejarbaneh, Behnam Yazdani
    Armaghani, Danial Jahed
    Tahir, M. M.
    BULLETIN OF ENGINEERING GEOLOGY AND THE ENVIRONMENT, 2020, 79 (04) : 2069 - 2084
  • [30] Performance Prediction of a Hard Rock TBM using Statistical and Artificial Intelligence Methods
    Afradi, Alireza
    Ebrahimabadi, Arash
    Hedayatzadeh, Mansour
    JOURNAL OF MINING AND ENVIRONMENT, 2024, 15 (01): : 323 - 343