Using field data and operational constraints to maximize hard rock TBM penetration and advance rates

被引:5
|
作者
Farrokh, Ebrahim [1 ]
机构
[1] Amirkabir Univ Technol, Tehran Polytech, Tehran, Iran
关键词
TBM; cutterhead; cutter spacing; layout design; cutting force; optimization; LINEAR CUTTING TESTS; DISC CUTTER; CONFINING STRESS; PERFORMANCE; EFFICIENCY; FRAGMENTATION; EXCAVATION; SANDSTONE; GRANITE;
D O I
10.1016/j.tust.2022.104506
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
In this paper, the influence of rock type and uniaxial compressive strength on the cutter penetration is inves-tigated to provide a basic guideline for the optimum field cutter spacing. The successfully utilized cutterhead layout designs are also studied in various rock types and different categories of tunnel sizes for projects with relatively high performance. The results of the conducted analyses show that the maximum cutter penetration in uniaxial compressive strength values below 50 and above 150 MPa is achieved when the cutter spacing is close to 90 and below 80 mm respectively. The study on the layout design characteristics of the cutterhead shows the evenly distributed scheme is more used with success even in softer rocks (when the rock mass condition is good). In softer rocks, the extension of the openings may have to be well over 50% of the cutterhead radius to maximize its performance. It is also found that the linear speed of the cutters has a direct correlation with two major parameters of normal force index (NFI) and rolling force index (RFI). In this regard, two formulas are generated using statistical analysis of the data from around 260 tunnel projects to evaluate both NFI and RFI. The corre-sponding formulas have coefficients of determination of 77 and 68% respectively. These formulas are used in an optimization process to maximize cutter penetration using various operational constraints (cutter load capacity, cutterhead torque limit, cutter geometry constrains, and cutterhead penetration rate limits). The new findings of this study can provide a foundation to improve the design process of hard rock TBMs and to optimize their performance considering various project setting parameters.
引用
收藏
页数:18
相关论文
共 50 条
  • [1] Layout design specifications of hard-rock TBM cutterheads at maximum cutter penetration and TBM advance
    Farrokh E.
    Arabian Journal of Geosciences, 2021, 14 (19)
  • [2] Prediction of Hard Rock TBM Penetration Rate Using Random Forests
    Hu Tao
    Wang Jingcheng
    Zhang Langwen
    2015 27TH CHINESE CONTROL AND DECISION CONFERENCE (CCDC), 2015, : 3716 - 3720
  • [3] Performance Assessment of Hard Rock TBM and Rock Boreability Using Punch Penetration Test
    Ho-Young Jeong
    Jung-Woo Cho
    Seokwon Jeon
    Jamal Rostami
    Rock Mechanics and Rock Engineering, 2016, 49 : 1517 - 1532
  • [4] Performance Assessment of Hard Rock TBM and Rock Boreability Using Punch Penetration Test
    Jeong, Ho-Young
    Cho, Jung-Woo
    Jeon, Seokwon
    Rostami, Jamal
    ROCK MECHANICS AND ROCK ENGINEERING, 2016, 49 (04) : 1517 - 1532
  • [5] Challenges and Opportunities of Data-Driven Advance Classification for Hard Rock TBM excavations
    Erharter, Georg H.
    Unterlass, Paul
    Radoncic, Nedim
    Marcher, Thomas
    Rostami, Jamal
    ROCK MECHANICS AND ROCK ENGINEERING, 2025,
  • [6] Prediction of hard rock TBM penetration rate using particle swarm optimization
    Yagiz, Saffet
    Karahan, Halil
    INTERNATIONAL JOURNAL OF ROCK MECHANICS AND MINING SCIENCES, 2011, 48 (03) : 427 - 433
  • [7] Estimation of the TBM advance rate under hard rock conditions using XGBoost and Bayesian optimization
    Zhou, Jian
    Qiu, Yingui
    Zhu, Shuangli
    Armaghani, Danial Jahed
    Khandelwal, Manoj
    Mohamad, Edy Tonnizam
    UNDERGROUND SPACE, 2021, 6 (05) : 506 - 515
  • [8] In situ TBM penetration tests and rock mass boreability analysis in hard rock tunnels
    Gong, Q. M.
    Zhao, J.
    Jiang, Y. S.
    TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2007, 22 (03) : 303 - 316
  • [9] Realtime prediction of hard rock TBM advance rate using temporal convolutional network (TCN) with tunnel construction big data
    Liu, Zaobao
    Wang, Yongchen
    Li, Long
    Fang, Xingli
    Wang, Junze
    FRONTIERS OF STRUCTURAL AND CIVIL ENGINEERING, 2022, 16 (04) : 401 - 413
  • [10] Realtime prediction of hard rock TBM advance rate using temporal convolutional network (TCN) with tunnel construction big data
    Zaobao LIU
    Yongchen WANG
    Long LI
    Xingli FANG
    Junze WANG
    Frontiers of Structural and Civil Engineering, 2022, 16 (04) : 401 - 413