Numerical Evaluation on Dynamic Response of Existing Underlying Tunnel Induced by Blasting Excavation of a Subway Tunnel

被引:13
|
作者
Zhou, Jixue [1 ,2 ,3 ]
Luo, Yi [1 ]
Li, XinPing [1 ]
Guo, Yunhua [1 ]
Liu, Tingting [1 ]
机构
[1] Wuhan Univ Technol, Hubei Key Lab Roadway Bridge & Struct, 122 Luoshi Rd, Wuhan 430070, Peoples R China
[2] Wuhan Univ Technol, Sch Civil Engn & Architecture, 122 Luoshi Rd, Wuhan 430070, Peoples R China
[3] China Railway 20 Bur Grp Co Ltd, 89 Taihua Rd, Xian 710016, Peoples R China
基金
中国国家自然科学基金;
关键词
INDUCED VIBRATION; METRO; STRATA; SYSTEM; ROCK;
D O I
10.1155/2017/8628671
中图分类号
O42 [声学];
学科分类号
070206 ; 082403 ;
摘要
In Southwest China, most regions are mountainous, where traditional drill-and-blast method is adopted to excavate relatively harder rocks. However, blasting would cause vibration to adjacent structures and might result in damage or even failure. This paper considers a case where subway tunnel is overlying an existing railway tunnel, while the excavation requires blasting method. Vibration and stress distribution are calculated via Dynamic Finite Element Method (DFEM) for both full-face excavation and CD method. Result shows that vibration induced by CD method is only 28% of that caused by full-face blasting with same distance. Peak vibration is located on the lining facing the blasting source, while peak tensile stress is on the other side of the contour due to the reflection of stress wave on strata boundary. And peak value of tensile stress induced by full-face blasting is capable of causing lining failure; thus full-face blasting is not suggested within 40 m beyond the underlying tunnel axis. However, CD method has shown much advantage, since blasting within 25 m is also considered safe to the underlying tunnel. But when the blasting source is as near as 12 m within the underlying tunnel, the CD method is no longer safe.
引用
收藏
页数:10
相关论文
共 50 条
  • [11] Simplified method for estimating the impact of the underlying tunnel excavation on existing tunnel
    Feng, Guohui
    Xu, Changjie
    Ding, Zhi
    Liang, Luju
    Li, Yujie
    Xu, Liyang
    Fan, Xiaozhen
    INTERNATIONAL JOURNAL FOR NUMERICAL AND ANALYTICAL METHODS IN GEOMECHANICS, 2024, 48 (11) : 3017 - 3031
  • [12] Vehicle-induced dynamic response characteristics of a new subway tunnel closely undercrossing the existing subway
    Zhang, Huijian
    Liu, Gongning
    Liu, Qiuyang
    Chen, Zekun
    Wang, Zhengzheng
    Niu, Xiaoyu
    SOIL DYNAMICS AND EARTHQUAKE ENGINEERING, 2023, 164
  • [13] Numerical analysis of effect of excavation on underlying existing metro tunnel and deformation control
    Zheng Gang
    Liu Qing-chen
    Deng Xu
    ROCK AND SOIL MECHANICS, 2013, 34 (05) : 1459 - 1468
  • [14] EFFECT OF BLASTING ON THE STABILITY OF LINING DURING EXCAVATION OF NEW TUNNEL NEAR THE EXISTING TUNNEL
    Tran Tuan Minh
    Nguyen Quang Huy
    CIVIL ENGINEERING JOURNAL-STAVEBNI OBZOR, 2021, 30 (01): : 47 - 62
  • [15] Effect of Subway Tunnel Excavation by Drill-Blasting Method on Pipeline
    Yu, Yongyan
    Gao, Yongtao
    Du, Zijian
    TRANSPORTATION RESEARCH CONGRESS 2016: INNOVATIONS IN TRANSPORTATION RESEARCH INFRASTRUCTURE: PROCEEDINGS OF THE TRANSPORTATION RESEARCH CONGRESS 2016, 2018, : 521 - 529
  • [16] Deformation Response Research of the Existing Subway Tunnel Impacted by Adjacent Foundation Pit Excavation
    Dong, Xin
    Mei, Ling
    Yang, Shuyan
    He, Liang
    ADVANCES IN MATERIALS SCIENCE AND ENGINEERING, 2021, 2021
  • [17] Deformation Response Research of the Existing Subway Tunnel Impacted by Adjacent Foundation Pit Excavation
    Dong, Xin
    Mei, Ling
    Yang, Shuyan
    He, Liang
    Advances in Materials Science and Engineering, 2021, 2021
  • [18] Vibration response law of existing buildings affected by subway tunnel boring machine excavation
    Wu, Ke
    Zheng, Yang
    Li, Shuchen
    Sun, Jie
    Han, Yucong
    Hao, Dongxue
    TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2022, 120
  • [19] Numerical simulation of blasting excavation in reconstruction and expansion tunnel
    Liu, D.
    Gao, W. X.
    Sun, B. P.
    Liu, D. H.
    ROCK DYNAMICS: FROM RESEARCH TO ENGINEERING, 2016, : 469 - 474
  • [20] Safety assessment of upper water pipeline under the blasting vibration induced by Subway tunnel excavation
    Xia Yuqing
    Jiang Nan
    Zhou Chuanbo
    Luo Xuedong
    ENGINEERING FAILURE ANALYSIS, 2019, 104 : 626 - 642