Isasmelt - Mount Isa Copper Smelter progress update

被引:0
|
作者
Bill, JL [1 ]
Briffa, TE [1 ]
Burrows, AS [1 ]
Fountain, CR [1 ]
Retallick, D [1 ]
Tuppurainen, JMI [1 ]
Edwards, JS [1 ]
Partington, P [1 ]
机构
[1] Mt Isa Mines Ltd, Mt Isa, Qld 4825, Australia
来源
关键词
D O I
暂无
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
The capacity of the Mount Isa Mines Limited Copper Smelter was expanded in 1998 from 180,000 tonnes per year of anode copper to 265,000 tpy. It is based on the innovative Copper ISASMELT technology, which currently treats concentrate at up to 184 tph. Increasing lance-air oxygen enrichment increased the ISASMELT furnace feed rate from 102 to 184 tph, The increased feed rate was achieved without any modifications to the ISASMELT furnace. The first refractory campaign following the upgrade lasted for two years. Future campaign lives of four years or more-without water cooling-are possible. Other Copper ISASMELT furnaces are operating in the U.S.A., Belgium, and India, with additional smelters under construction in China and Germany. In addition, Lead ISASMELT furnaces are operating in the U.K. and Malaysia. The paper discusses the performance of the MEA Copper ISASMELT furnace and the Copper Smelter since the expansion, including operating data and refractory performance.
引用
收藏
页码:181 / 193
页数:13
相关论文
共 50 条