Design and construction of the Karuma hydropower project in Uganda

被引:2
|
作者
Karubanga, Adolph [1 ]
Mugume, Rodgers [2 ]
机构
[1] Minist Energy & Mineral Dev, Kampala, Uganda
[2] WSP, London, England
关键词
concrete structures; dams; barrages and reservoirs; energy; renewable energy; UN SDG 7: Affordable and clean energy; UN SDG 9: Industry; innovation and infrastructure;
D O I
10.1680/jcien.22.00027
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
This paper describes the new 600 MW Karuma hydropower project in Uganda, which was completed in 2022. More than 70% of the project's structures were built underground to enhance resilience. Complexities relating to structural analysis and design, advanced engineering technologies, climatic considerations, deep excavations and tunnelling are presented. Key challenges experienced during construction, remedial measures undertaken, lessons learnt and a proposed post-construction renewable energy option are also discussed.
引用
收藏
页码:12 / 21
页数:10
相关论文
共 50 条
  • [31] Design and construction of the Ermenek project
    Kronberger, O.
    Naderer, R.
    Pekçagliyan, M.D.
    International Journal on Hydropower and Dams, 2002, 9 (05): : 72 - 75
  • [32] INTERALUMINA PROJECT DESIGN AND CONSTRUCTION
    ENGELBERGER, K
    E&MJ-ENGINEERING AND MINING JOURNAL, 1983, 184 (05): : 78 - 81
  • [33] Lesotho Highlands water project - design of the 'Muela hydropower station
    Arthur, EILJ
    Wagner, CM
    Hein, DIB
    PROCEEDINGS OF THE INSTITUTION OF CIVIL ENGINEERS-CIVIL ENGINEERING, 1997, 120 : 43 - 53
  • [34] Tensions in Sino-African labour relations: the view from the Karuma hydroelectric dam in Uganda
    Wyrod, Robert
    Chang, Kimberlee
    JOURNAL OF MODERN AFRICAN STUDIES, 2023, 61 (04): : 583 - 604
  • [35] Overview of hydropower resources and development in Uganda
    Katutsi, Vincent
    Kaddu, Milly
    Migisha, Adella Grace
    Rubanda, Muhumuza Ezra
    Adaramola, Muyiwa S.
    AIMS ENERGY, 2021, 9 (06) : 1299 - 1320
  • [36] LEARNING SKILLS FOR CONSTRUCTION PROJECT DESIGN BY PROJECT METHOD
    Calvet Rodriguez, V.
    Valcuende Paya, M.
    Haro Rodriguez, M.
    INTED2016: 10TH INTERNATIONAL TECHNOLOGY, EDUCATION AND DEVELOPMENT CONFERENCE, 2016, : 377 - 382
  • [37] Study on Information System Based on gridding management for Hydropower Project during Construction
    Cai, Hualong
    Ye, Shisui
    Xiao, Xi
    Wu, Zhiyu
    Zeng, Jingfu
    ARCHITECTURE, BUILDING MATERIALS AND ENGINEERING MANAGEMENT, PTS 1-4, 2013, 357-360 : 2366 - +
  • [38] Analysis on Construction Technology of Concrete Cutoff Wall in Water Conservancy and Hydropower Project
    Tao, Zhang
    INTERNATIONAL SYMPOSIUM 2017 - MECHANICAL AND ELECTRONICAL SYSTEMS AND CONTROL ENGINEERING, 2017, : 59 - 62
  • [39] The Triangle Link Project, design and construction
    Schaathun, H
    STRAIT CROSSINGS 2001, 2001, : 353 - 357
  • [40] Integrated Design,Construction and Debugging of Project
    Gu Peide(Northeast China Electric Power Group Corporation)
    Electricity, 1997, (02) : 13 - 16