Solving the resource-constrained multi-project scheduling problem with an improved critical chain method

被引:12
|
作者
Tian, Min [1 ]
Liu, Ren Jing [1 ]
Zhang, Guang Jun [1 ]
机构
[1] Xi An Jiao Tong Univ, Sch Management, Xian 710049, Shaanxi, Peoples R China
基金
中国国家社会科学基金;
关键词
CCM; buffer settings; RCMPSP; hierarchical strategy; MANAGEMENT;
D O I
10.1080/01605682.2019.1609883
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
In view of the fact that the critical chain method (CCM) is mainly used in single project scheduling, this article improves the method and applies it to multi-project scheduling. Taking into consideration the flow of the drum resource within and among sub-projects, this study proposes methods that can be used to identify the critical chain and buffer settings, based on the concepts of the task chain, sub-project drum resource flow, and multi-project drum resource flow. The improvement of the CCM includes two aspects. First, by analysing the impact of the drum buffer and capacity constrained buffer on the project buffer and feeding buffer, the calculation methods of these buffers are optimised. Second, a risk contribution index is designed for the modification of these buffers, in order to further improve their anti-interference ability. Then, combined with the improved CCM and the different hierarchical scheduling objectives, a critical chain resource-constrained multi-project scheduling model with a hierarchical strategy is proposed as a way of solving multi-project scheduling plans. Eight theoretical test cases with different scales, and a practical example under different risk levels of uncertainty are used to test this model. The results show that the stability of the scheduling plans clearly improved, and the project duration and tardiness costs were significantly reduced, thus proving the effectiveness of the model.
引用
收藏
页码:1243 / 1258
页数:16
相关论文
共 50 条
  • [21] A variable neighborhood search approach for the resource-constrained multi-project collaborative scheduling problem
    Cui, Longqing
    Liu, Xinbao
    Lu, Shaojun
    Jia, Zhaoli
    APPLIED SOFT COMPUTING, 2021, 107
  • [22] Robust optimization for the resource-constrained multi-project scheduling problem with uncertain activity durations
    Nabipoor Afruzi E.
    Aghaie A.
    Najafi A.A.
    Scientia Iranica, 2020, 27 (1 E) : 361 - 376
  • [23] Multi-skilled resource-constrained multi-project scheduling problem with dexterity improvement of workforce
    Mozhdehi, Saleh
    Baradaran, Vahid
    Hosseinian, Amir Hossein
    AUTOMATION IN CONSTRUCTION, 2024, 162
  • [24] Characterization of a set of schedules in resource-constrained multi-project scheduling problem with multiple modes
    Artigues, C
    Roubellat, F
    Billaut, JC
    INTERNATIONAL JOURNAL OF INDUSTRIAL ENGINEERING-THEORY APPLICATIONS AND PRACTICE, 1999, 6 (02): : 112 - 122
  • [25] Modeling and algorithm for resource-constrained multi-project scheduling problem based on detection and rework
    Zhu, Hongwei
    Lu, Zhiqiang
    Lu, Chenyao
    Ren, Yifei
    ASSEMBLY AUTOMATION, 2021, 41 (02) : 174 - 186
  • [26] Solving the Multi-Mode Resource-Constrained Project Scheduling Problem with SMT
    Bofill, Miquel
    Coll, Jordi
    Suy, Josep
    Villaret, Mateu
    2016 IEEE 28TH INTERNATIONAL CONFERENCE ON TOOLS WITH ARTIFICIAL INTELLIGENCE (ICTAI 2016), 2016, : 239 - 246
  • [27] The performance of priority rules for the decentralized resource-constrained multi-project scheduling
    Mao, Hongri
    Yuan, Jianbo
    KNOWLEDGE-BASED SYSTEMS, 2024, 304
  • [28] Resource-constrained multi-project scheduling: Priority rule performance revisited
    Browning, Tyson R.
    Yassine, Ali A.
    INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2010, 126 (02) : 212 - 228
  • [29] Resource Constrained Multi-Project Scheduling Problem with Resource Transfer Times
    Suresh, M.
    Dutta, Pankaj
    Jain, Karuna
    ASIA-PACIFIC JOURNAL OF OPERATIONAL RESEARCH, 2015, 32 (06)
  • [30] New approaches for solving the resource-constrained project scheduling problem
    Kone, Oumar
    4OR-A QUARTERLY JOURNAL OF OPERATIONS RESEARCH, 2013, 11 (01): : 93 - 94