On two-machine Flow Shop Scheduling Problem with disjoint setups

被引:0
|
作者
Gnatowski, Andrzej [1 ]
Rudy, Jaroslaw [2 ]
Idzikowski, Radoslaw [1 ]
机构
[1] Wroclaw Univ Sci & Technol, Dept Control Syst & Mechatron, Wroclaw, Poland
[2] Wroclaw Univ Sci & Technol, Dept Comp Engn, Wroclaw, Poland
关键词
discrete optimization; disjoint setups; flow shop problem; mixed-integer linear programming; MAKESPAN;
D O I
10.1109/sose50414.2020.9130513
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
We consider a variant of the Permutational Flow Shop Scheduling Problem with disjoint setups and makespan minimization. A mathematical model of the problem is presented and several properties on the feasibility of solutions are formulated. An elimination property is proposed, allowing to disregard up to 75% of the solution space. We also show an interesting connection between the number of feasible solutions and Catalan numbers. To solve the problem for a fixed job order, we propose two algorithms: Mixed-Integer Linear Programming exact formulation and a greedy heuristic algorithm. An empirical evaluation shows a promising efficiency of the heuristic, providing an optimal or near-optimal solutions for problem instances with low setup and job times time deviation.
引用
收藏
页码:277 / 282
页数:6
相关论文
共 50 条
  • [31] Approximation schemes for two-machine flow shop scheduling with two agents
    Luo, Wenchang
    Chen, Lin
    Zhang, Guochuan
    JOURNAL OF COMBINATORIAL OPTIMIZATION, 2012, 24 (03) : 229 - 239
  • [32] Two-machine Flow Shop Scheduling with Re-entrance
    Jing, Caixia
    Qian, Xingsan
    Tang, Guochun
    PROCEEDINGS OF THE INTERNATIONAL CONFERENCE ON INFORMATION MANAGEMENT, INNOVATION MANAGEMENT AND INDUSTRIAL ENGINEERING, VOL II, 2008, : 528 - +
  • [33] Two-machine flow shop scheduling of polyurethane foam production
    Lin, Bertrand M. T.
    Lin, Y-Y
    Fang, K-T
    INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2013, 141 (01) : 286 - 294
  • [34] Integrated production - Transportation scheduling in a two-machine flow shop
    Feng, Zhou
    Liang, Gao
    Li, Nie
    TIRMDCM 2007: PROCEEDINGS OF THE FIRST INTERNATIONAL CONFERENCE ON TECHNOLOGY INNOVATION, RISK MANAGEMENT AND SUPPLY CHAIN MANAGEMENT, VOLS 1 AND 2, 2007, : 142 - 146
  • [35] Batch scheduling in a two-machine flow shop with limited buffer
    Agnetis, A
    Pacciarelli, D
    Rossi, F
    DISCRETE APPLIED MATHEMATICS, 1997, 72 (03) : 243 - 260
  • [36] Coordinating scheduling with batch deliveries in a two-machine flow shop
    Pan, Jason Chao-Hsien
    Wu, Chih-Lun
    Huang, Han-Chiang
    Su, Chi-Shiang
    INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2009, 40 (5-6): : 607 - 616
  • [37] Constraint Programming for the Robust Two-Machine Flow-Shop Scheduling Problem with Budgeted Uncertainty
    Juvin, Carla
    Houssin, Laurent
    Lopez, Pierre
    INTEGRATION OF CONSTRAINT PROGRAMMING, ARTIFICIAL INTELLIGENCE, AND OPERATIONS RESEARCH, CPAIOR 2023, 2023, 13884 : 354 - 369
  • [38] The proportionate two-machine no-wait job shop scheduling problem
    Koulamas, Christos
    Panwalkar, S. S.
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2016, 252 (01) : 131 - 135
  • [39] The Two-machine Flow-shop Scheduling Problem with a Single Server and Unit Server Times
    Ling, Shi
    Guang, Cheng Xue
    JOURNAL OF INFORMATICS AND MATHEMATICAL SCIENCES, 2012, 4 (01): : 123 - 127
  • [40] A heuristic for scheduling two-machine no-wait flow shops with anticipatory setups
    Sidney, JB
    Potts, CN
    Sriskandarajah, C
    OPERATIONS RESEARCH LETTERS, 2000, 26 (04) : 165 - 173