Identification of Causes of Non-excusable Delays of Construction Projects

被引:0
|
作者
Afshari, Hamidreza [1 ]
Khosravi, Shahrzad [1 ]
Ghorbanali, Abbas [1 ]
Borzabadi, Mandi [1 ]
Valipour, Mahbod [1 ]
机构
[1] Mapna Special Projects Construct & Dev Co MD 3, Planning & Informat Deputy, Tehran, Iran
来源
关键词
non-execuable delay; construction; subcontractor; performing organization;
D O I
暂无
中图分类号
F [经济];
学科分类号
02 ;
摘要
One of the key characteristics of the projects, especially construction projects. is executing the scope of work in a specific amount of time. As project time overrun may have bad consequences for the project performing organization such as cost overrun, damage of company's reputation, etc. it is important to clarify between causes of excusable delays and causes of non-excusable delays. Major purpose of this paper is to identify non-excusable delays of executive companies of Mapna Group in order to improve time performance of the project by managing better these causes. The scope of the research is the projects including thermal power plant, steam and power and utility projects which are completed or being executed by these affiliated companies. In this paper top 20 causes of non-excusable delay of construction projects have been identified by a Delphi questionnaire survey and applying Mean Rank method. To determine whether there is degree of agreement among the panel of experts with respect to their ranking of the causes of non-excusable construction delays, a test of hypothesis was developed and a significant degree of agreement among the expert was verified. "Not selecting competent subcontractors" was selected as the most important cause of none-excusable construction delays.
引用
收藏
页码:42 / 46
页数:5
相关论文
共 50 条
  • [31] Investigation into the Causes of Delays and Cost Overruns in Uganda's Public Sector Construction Projects
    Alinaitwe, Henry
    Apolot, Ruth
    Tindiwensi, Dan
    JOURNAL OF CONSTRUCTION IN DEVELOPING COUNTRIES, 2013, 18 (02) : 33 - 47
  • [32] An integrative literature review on the causes of delays in construction projects: evidence from developing countries
    Selcuk, Onur
    Turkoglu, Harun
    Polat, Gul
    Hajdu, Miklos
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2024, 24 (06) : 610 - 622
  • [33] Identifying and Ranking the Root Causes of Schedule Delays in Oil and Gas Pipeline Construction Projects
    Alshibani, Adel
    Julaih, Mohammed
    Adress, Ahamd
    Alshamrani, Othman
    Almaziad, Faris
    ENERGIES, 2023, 16 (01)
  • [34] An Approach to the Analysis of Causes of Delays in Industrial Construction Projects through Planning and Statistical Computing
    Araujo-Rey, Carlos
    Sebastian, Miguel A.
    SUSTAINABILITY, 2021, 13 (07)
  • [35] Identification and Evaluation of Causes and Effects of Change Orders in Building Construction Projects
    Pourrostam, Towhid
    Ismail, Amiruddin
    Mansournejad, Mahmood
    ADVANCES IN STRUCTURAL ENGINEERING, PTS 1-3, 2011, 94-96 : 2261 - +
  • [36] Causes of Incomplete Risk Identification in Major Transportation Engineering and Construction Projects
    Dicks, Evan P.
    Molenaar, Keith R.
    TRANSPORTATION RESEARCH RECORD, 2024,
  • [37] Delays in Building Construction Projects in Ghana
    Fugar, Frank D. K.
    Agyakwah-Baah, Adwoa B.
    CONSTRUCTION ECONOMICS AND BUILDING, 2010, 10 (1-2):
  • [38] CONCURRENT DELAYS IN CONSTRUCTION PROJECTS - CLOSURE
    KRAIEM, ZM
    DIEKMANN, JE
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1989, 115 (02): : 337 - 338
  • [39] CONCURRENT DELAYS IN CONSTRUCTION PROJECTS - DISCUSSION
    LOGCHER, RD
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1989, 115 (02): : 335 - 337
  • [40] CONCURRENT DELAYS IN CONSTRUCTION PROJECTS.
    Kraiem, Zaki M.
    Diekmann, James E.
    Journal of Construction Engineering and Management, 1987, 113 (04) : 591 - 602