Within ten months of the first significant intersection on the Vera deposit, approval was given to proceed with a $28.3 M underground development of the Vera-Nancy gold mine. Contrary to what the timeframe suggests, the development of the underground mine was planned in a logical and methodical manner which enabled confirmation of the resource, evaluation of the orebody for mining and sufficient production to recommence milling operations at the Pajingo treatment plant. This paper describes the underlying factors on which the project was planned and developed. The approach has successfully enabled the mine to be in production Ig months after discovery without compromising any future production or potential expansion.