Linear Optimization Model to Minimize Total Cost of Repetitive Construction Projects and Identify Order of Units

被引:25
|
作者
Monghasemi, Shahryar [1 ]
Abdallah, Moatassem [1 ]
机构
[1] Univ Colorado Denver, Dept Civil Engn, 1200 Larimer, Denver, CO 80204 USA
关键词
Repetitive construction projects; Linear scheduling; Optimization; Construction planning and scheduling; Linear programing; Resource driven scheduling; SCHEDULING METHOD; PATH; LOB;
D O I
10.1061/(ASCE)ME.1943-5479.0000936
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
This study developed a linear optimization model for scheduling repetitive construction projects with varying quantities of work in repetitive units. The model provides new capabilities that enable planners to identify an optimal/near-optimal schedule that minimizes project total cost and number of times crew work is interrupted. It is capable of identifying the optimal/near-optimal order of executing repetitive units to achieve further reduction in project time and cost. The model was developed in three main phases: (1) identifying input data such as quantities and crew productivity rates; (2) optimizing the construction schedule of repetitive units by identifying decision variables, formulating objective functions, and constraints, and executing model computations; and (3) visualizing the generated optimal/near-optimal schedule, crew interruption, project duration and cost, and order of executing repetitive units. Two case studies of 105 and 6 repetitive units were analyzed to evaluate the model performance. The model resulted in 0.13% and 4.2% additional reduction in project total cost and indirect cost, respectively, for the optimal order of repetitive units compared with the best model in the literature. (C) 2021 American Society of Civil Engineers.
引用
收藏
页数:15
相关论文
共 50 条
  • [1] Stochastic scheduling optimization of repetitive construction projects to minimize project duration and cost
    Hassan, Abbas
    El-Rayes, Khaled
    Attalla, Mohamed
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2023, 23 (09) : 1447 - 1456
  • [2] Linear Scheduling Optimization Model for Planning Repetitive Construction Projects
    Monghasemi, Shahryar
    Abdallah, Moatassem
    Clevenger, Caroline
    CONSTRUCTION RESEARCH CONGRESS 2020: PROJECT MANAGEMENT AND CONTROLS, MATERIALS, AND CONTRACTS, 2020, : 1129 - 1138
  • [3] Linear Optimization Model for Scheduling Repetitive Construction Projects with Multiple Crews
    Monghasemi, Shahryar
    Abdallah, Moatassem
    CONSTRUCTION RESEARCH CONGRESS 2022: PROJECT MANAGEMENT AND DELIVERY, CONTRACTS, AND DESIGN AND MATERIALS, 2022, : 461 - 471
  • [4] Multipurpose linear programming optimization model for repetitive activities scheduling in construction projects
    Diego Garcia-Nieves, Juan
    Luis Ponz-Tienda, Jose
    Ospina-Alvarado, Angelica
    Bonilla-Palacios, Mateo
    AUTOMATION IN CONSTRUCTION, 2019, 105
  • [5] Multiobjective Optimization Model for Planning Repetitive Construction Projects
    Altuwaim, Ayman
    El-Rayes, Khaled
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2021, 147 (07)
  • [6] Hybrid Time-Cost Optimization of Nonserial Repetitive Construction Projects
    Ezeldin, A. Samer
    Soliman, Ahmed
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2009, 135 (01) : 42 - 55
  • [7] SCHEDULING OF REPETITIVE PROJECTS WITH COST OPTIMIZATION
    MOSELHI, O
    ELRAYES, K
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1993, 119 (04): : 681 - 697
  • [8] Optimizing the Scheduling of Repetitive Construction to Minimize Interruption Cost
    Altuwaim, Ayman
    El-Rayes, Khaled
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2018, 144 (07)
  • [9] Fuzzy Linear and Repetitive Scheduling for Construction Projects
    Katsuragawa, Clara Mariana
    Lucko, Gunnar
    Isaac, Shabtai
    Su, Yi
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2021, 147 (03)
  • [10] Cost optimization in projects with repetitive nonserial activities
    Hegazy, T
    Wassef, N
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2001, 127 (03): : 183 - 191