A deterministic approach to generation and transmission maintenance scheduling with network constraints

被引:28
|
作者
Marwali, MKC [1 ]
Shahidehpour, SM [1 ]
机构
[1] IIT, Dept Elect & Comp Engn, Chicago, IL 60616 USA
关键词
generation maintenance scheduling; transmission maintenance scheduling; benders decomposition;
D O I
10.1016/S0378-7796(98)00055-8
中图分类号
TM [电工技术]; TN [电子技术、通信技术];
学科分类号
0808 ; 0809 ;
摘要
Most unit maintenance scheduling packages consider the preventive maintenance schedule of generating units over a 1 or 2 year operational planning period in order to minimize the total operation cost while satisfying system energy requirements and maintenance constraints. In a global maintenance scheduling problem, we propose to consider transmission line maintenance scheduling in generation maintenance scheduling. The inclusion of network constraints in generation unit maintenance will increase the complexity of the problem, so we propose to decompose the global generator/transmission scheduling problem into a master problem and sub-problems using Benders decomposition. In the first stage, a master problem is solved to determine a solution for maintenance schedule decision variables. In the second stage, sub-problems are solved to minimize operation costs while satisfying the network constraints. Benders cuts based on the solution of the sub-problem are introduced to the master problem for improving the existing solution. The iterative procedure continues until an optimal or near optimal solution is found. (C) 1998 Published by Elsevier Science S.A. All rights reserved.
引用
收藏
页码:101 / 113
页数:13
相关论文
共 50 条
  • [21] Generation and Transmission Equipment Maintenance Scheduling with Load Transfer
    Zhu, Jizhong
    Xuan, Peizheng
    Xie, Pingping
    Hong, Chao
    Yan, Wei
    2017 IEEE POWER & ENERGY SOCIETY GENERAL MEETING, 2017,
  • [22] TS-based generation and transmission maintenance scheduling
    Yu, Dayang
    Zhang, Qiang
    Han, Xueshan
    Zhao, Jianguo
    2007 IEEE CONGRESS ON EVOLUTIONARY COMPUTATION, VOLS 1-10, PROCEEDINGS, 2007, : 2936 - 2941
  • [23] Energy transaction scheduling with network constraints and transmission losses
    Zhu, JZ
    Chang, CS
    FOURTH INTERNATIONAL CONFERENCE ON ADVANCES IN POWER SYSTEM CONTROL, OPERATION & MANAGEMENT, VOLS 1 AND 2, 1997, : 712 - 717
  • [24] Global Generation Maintenance Scheduling with Network Constraints, Spinning Reserve, Fuel, and Energy Purchase from Outside
    Niazi, Ahmad Norozpour
    Sheikholeslami, Abdolreza
    Varaki, Ali Reza Karimi
    2012 IEEE ELECTRICAL POWER AND ENERGY CONFERENCE (EPEC), 2012, : 330 - 336
  • [25] A two-stage stochastic programming approach for generation and transmission maintenance scheduling with risk management
    Fan, Aoyu
    Huang, Zhouchun
    Zheng, Qipeng
    Luo, Xiaodong
    COMPUTATIONAL OPTIMIZATION AND APPLICATIONS, 2024,
  • [26] Acquiring Constraints for a Non-linear Transmission Maintenance Scheduling Problem
    Barral, Hugo
    Gaha, Mohamed
    Dems, Amira
    Cote, Alain
    Nguewouo, Franklin
    Cappart, Quentin
    INTEGRATION OF CONSTRAINT PROGRAMMING, ARTIFICIAL INTELLIGENCE, AND OPERATIONS RESEARCH, PT I, CPAIOR 2024, 2024, 14742 : 34 - 50
  • [27] Generation and transmission equipment maintenance scheduling by transmission switching and phase shifting transformer
    Behnia, Hamid
    Akhbari, Mahdi
    INTERNATIONAL JOURNAL OF NUMERICAL MODELLING-ELECTRONIC NETWORKS DEVICES AND FIELDS, 2019, 32 (01)
  • [28] Generation scheduling with emissions trading scheme and transmission capacity constraints
    Kockar, Ivana
    INTERNATIONAL JOURNAL OF ENERGY SECTOR MANAGEMENT, 2011, 5 (03) : 361 - 380
  • [29] Study on Generation and Transmission Maintenance Scheduling Under Electricity Market
    Zhang Shuangmei
    Ge Ju
    2010 ASIA-PACIFIC POWER AND ENERGY ENGINEERING CONFERENCE (APPEEC), 2010,
  • [30] Automatic scheduling method using tabu search for maintenance outage tasks of transmission and substation system with network constraints
    Sawa, T
    Furukawa, T
    Nomoto, M
    Nagasawa, T
    Sasaki, T
    Deno, K
    Maekawa, T
    IEEE POWER ENGINEERING SOCIETY - 1999 WINTER MEETING, VOLS 1 AND 2, 1999, : 895 - 900