Trade-off Between Cost and Safety To Cope with Station Blackout in A PWR in A Deregulated Electricity Market

被引:0
|
作者
Ahmad Khanbeigi, Ghafour [1 ]
Jahanfarnia, Gholamreza [1 ]
Sharifloo, Naser Mansour [1 ]
Sheikh-el-Eslami, Mohamad Kazem [2 ]
Karimi, Kaveh [3 ]
机构
[1] Islamic Azad Univ, Dept Nucl Engn, Sci & Res Branch, Tehran, Iran
[2] Tarbiat Modares Univ, Power Syst Lab, Tehran, Iran
[3] Islamic Azad Univ, East Tehran Branch, Tehran, Iran
关键词
PWR safety; Station blackout; Payback period; Economics; COMPLEMENTARITY MODELS; POWER-PLANTS; ENERGY;
D O I
10.1007/s42835-020-00488-5
中图分类号
TM [电工技术]; TN [电子技术、通信技术];
学科分类号
0808 ; 0809 ;
摘要
In this paper a close solution is presented to determine the trade-off between cost and safety to cope with station blackout (SBO) in Pressurized Water Reactors (PWRs). To compute the profit of each generation unit, a Supply Function Equilibrium (SFE) model swhich considers carbon tax is used in a uniform electricity market. A hierarchical heuristic method is applied for decision making on safety improvement of Nuclear Power Plants (NPPs). In this method the break-even point is used as a criterion to make a decision on comparing cost of safety improvement and profit of NPP in a deregulated electricity market. This method is applied in a case of adding an Emergency Water Supply (EWS) and an Emergency Diesel Generator (EDG) to a NPP where impacts of its investment cost and its profit are investigated. The achieved results show that the break-even point of investment cost and net profit of the NPP by adding the EDG is one month later than NPP with addition of EWS.