Time dependent start-up thermal analysis of a Super Fast Reactor

被引:5
|
作者
Sutanto [1 ]
Oka, Yoshiaki [1 ]
机构
[1] Waseda Univ, Shinjuku Ku, Tokyo 1698555, Japan
关键词
Startup; Upward flow; Recirculation system; Cladding temperature; Heat flux; Super FR; LIGHT-WATER-REACTOR; SUPERCRITICAL-PRESSURE;
D O I
10.1016/j.nucengdes.2013.04.014
中图分类号
TL [原子能技术]; O571 [原子核物理学];
学科分类号
0827 ; 082701 ;
摘要
The startup system of a supercritical pressure light water cooled fast reactor (Super FR) is studied by time dependent thermal-hydraulic analysis. The plant analysis code is developed based on an innovative upward flow pattern in all the assemblies of the Super FR. A recirculation system consisting of a steam drum, a circulation pump, and a heat exchanger is used for the startup. Detailed procedures are performed and the maximum cladding surface temperature (MCST) at rated power, 640 degrees C, is used as the criterion. Firstly a small constant nuclear power is used for rising the core feed water temperature to be 280 degrees C through the recirculation system. Secondly, pressurization is done in the recirculation system from atmospheric to operating pressure, 25 MPa, by raising the power. Thirdly, line-switching from recirculation mode to once-through direct-cycle is performed while turbines are started by supercritical steam at supercritical pressure. Finally the power is raised to be 100% of power followed by raising the flow rate. During pressurization the heat flux margin is large due to low power used for pressurization and the MCST is much lower than the criterion. The MCST is not sensitive to the inlet temperature, the flow rate, and the gap volume of the core because of high flow to power ratio. Smaller dimension of steam drum can be used for pressurization stably. The MCST satisfies the criterion both during subcritical pressure and during power-raising. (c) 2013 Elsevier B.V. All rights reserved.
引用
收藏
页码:129 / 137
页数:9
相关论文
共 50 条
  • [21] START-UP OF A CATALYTIC REACTOR BY FUZZY CONTROLLER
    YAMASHITA, Y
    MATSUMOTO, S
    SUZUKI, M
    JOURNAL OF CHEMICAL ENGINEERING OF JAPAN, 1988, 21 (03) : 277 - 282
  • [22] DIGITAL START-UP CONTROL OF A RESEARCH REACTOR
    TAKAHASH.Y
    TAKAMATS.S
    IEEE TRANSACTIONS ON NUCLEAR SCIENCE, 1965, NS12 (04) : 355 - &
  • [23] Start-up performance of anaerobic baffled reactor
    He, Shijun
    Huang, Yongheng
    Wang, Jianlong
    2006, Press of Tsinghua University (46):
  • [24] Experimental investigations on start-up performance of static nuclear reactor thermal prototype
    Tang, Simiao
    Wang, Chenglong
    Liu, Xiao
    Tian, Zhixing
    Su, G. H.
    Tian, Wenxi
    Qiu, Suizheng
    INTERNATIONAL JOURNAL OF ENERGY RESEARCH, 2020, 44 (04) : 3033 - 3048
  • [25] START-UP AND DYNAMIC BEHAVIOR OF A CHEMICAL REACTOR
    BROOKS, BW
    CHEMICAL ENGINEERING SCIENCE, 1979, 34 (12) : 1417 - 1419
  • [26] Analysis of start-up and thermal performance of super-hydrophilic porous wick loop heat pipe
    Guo, Hao
    Ji, Xianbing
    Zhou, Ruhong
    Peng, Jialüe
    Xu, Jinliang
    Huagong Jinzhan/Chemical Industry and Engineering Progress, 2020, 39 (04): : 1227 - 1234
  • [27] L-REACTOR START-UP DELAYED
    SMITH, RJ
    SCIENCE, 1983, 221 (4608) : 345 - 345
  • [28] Start-up, shutdown, and transition timescale analysis in biomass reactor operations
    Kung, Kevin S.
    Thengane, Sonal K.
    Ghoniem, Ahmed F.
    Lim, C. Jim
    Cao, Yankai
    Sokhansanj, Shahabaddine
    ENERGY, 2022, 248
  • [29] A model for the analysis of pump start-up transients in Tehran Research Reactor
    Farhadi, Kazem
    Bousbia-Salah, Anis
    D'Auria, Franscesco
    PROGRESS IN NUCLEAR ENERGY, 2007, 49 (07) : 499 - 510
  • [30] Analysis of thermal stresses in a boiler drum during start-up
    Taler, J
    Weglowski, B
    Zima, W
    Gradziel, S
    Zborowski, M
    JOURNAL OF PRESSURE VESSEL TECHNOLOGY-TRANSACTIONS OF THE ASME, 1999, 121 (01): : 84 - 93