CONCRETE CREEP EFFECTS DURING BRIDGE SPAN CONSTRUCTION USING CANTILEVER CONCRETING TECHNOLOGY

被引:2
|
作者
Machelski, Czeslaw [1 ]
机构
[1] Wroclaw Univ Technol, Wydzial Budownictwa Ladowego & Wodnego, Wyb Wyspianskiego 27, PL-50370 Wroclaw, Poland
来源
ROADS AND BRIDGES-DROGI I MOSTY | 2019年 / 18卷 / 03期
关键词
assembly phase; cantilever concrete bridges; cantilever concreting technology; creep of concrete; monitoring; secondary moments;
D O I
10.7409/rabdim.019.013
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
A characteristic feature of many long-span cantilever prestressed concrete bridges are excessive deflections of their spans due to the rheological processes in the concrete and in the prestressing steel. Such bridges are subject to monitoring during which geodetic surveys are usually conducted. The latter reveal changes in the deflection curves of the spans. In this paper span displacements resulting from concrete creep are analysed. A specific situation occurring when the span static scheme is changed from the cantilever (assembly stage) to continuous beam (exploitation stage) is considered. Assuming a regular three-span structure, a general solution to the problem is obtained for the following bridge parameters: dead load, span length, and the variable concrete creep index. The proposed algorithm is used in calculation examples in which different creep index distributions along the cantilevers are assumed. The results of the analyses are compared with the behaviour of a monitored existing bridge of this type. The analyses presented in this paper can be useful for the design of spans and the assessment of the safety of such bridges which are in service.
引用
收藏
页码:193 / 210
页数:18
相关论文
共 50 条
  • [1] Effects of Solar Temperature Gradient on Long-Span Concrete Box Girder during Cantilever Construction
    Song, XuMing
    Melhem, Hani
    Li, Jun
    Xu, QingYuan
    Cheng, LiJun
    JOURNAL OF BRIDGE ENGINEERING, 2016, 21 (03)
  • [2] Transverse Analysis about Curved Continuous Rigid Frame Bridge Cantilever Concreting Construction Process
    Zhao, Ning
    Zhu, Bing
    Suo, Wenjia
    Du, Liang
    Wang, Fan
    SUSTAINABLE CITIES DEVELOPMENT AND ENVIRONMENT PROTECTION, PTS 1-3, 2013, 361-363 : 1380 - 1383
  • [3] THE RATIONALITY OF THE CONSTRUCTION ARRANGEMENT FOR THE LONG-SPAN BRIDGE BY CANTILEVER METHOD
    Rao, Rui
    Fu, Jiyang
    Liu, Airong
    INTERNATIONAL SYMPOSIUM ON LIFE-CYCLE PERFORMANCE OF BRIDGES AND STRUCTURES, 2010, : 1015 - 1019
  • [4] Rapid hardening concrete for the construction of a small span bridge
    Cangiano, Stefano
    Meda, Alberto
    Plizzari, Giovanni A.
    CONSTRUCTION AND BUILDING MATERIALS, 2009, 23 (03) : 1329 - 1337
  • [5] Parametric analysis on the stability of long-span rigid-frame bridge during cantilever construction
    School of Civil Engineering, Southwest Jiaotong University, Chengdu 610031, China
    不详
    Zhongguo Tiedao Kexue, 2007, 2 (32-38):
  • [7] Prediction of creep effect in segmental concrete bridge construction
    Khazanovich, Lev
    Transportation Research Record, 1994, (1458) : 28 - 31
  • [8] CREEP CHARACTERISTICS OF CONCRETE USED IN LONG-SPAN ARCH BRIDGE
    Wang, Yongbao
    Zhao, Renda
    Jia, Yi
    Liao, Ping
    BALTIC JOURNAL OF ROAD AND BRIDGE ENGINEERING, 2019, 14 (01): : 18 - 36
  • [9] Control technique for construction of long span prestressed concrete bridge
    Xiang, Mu-Sheng
    Zhang, Shi-Biao
    Zhang, Kai-Yin
    Shen, Dian-Dong
    Shen, Cheng-Wu
    Zhongguo Gonglu Xuebao/China Journal of Highway and Transport, 2002, 15 (04):
  • [10] Study of creep effects in a long-span concrete-filled steel tube arch bridge
    Zeng, Yong
    Zhong, Huadong
    Liu, Chengcai
    Tan, Hongmei
    Gu, An-bang
    PROCEEDINGS OF THE INSTITUTION OF CIVIL ENGINEERS-STRUCTURES AND BUILDINGS, 2018, 171 (08) : 642 - 658