Two-machine flowshop scheduling with consecutive availability constraints

被引:34
|
作者
Cheng, TCE [1 ]
Wang, GQ
机构
[1] Hong Kong Polytech Univ, Off Vice President Res & Postgrad Studies, Kowloon, Hong Kong
[2] Jinan Univ, Dept Business Adm, Guangzhou, Peoples R China
[3] Hong Kong Polytech Univ, Dept Management, Kowloon, Hong Kong
关键词
algorithms; flowshop scheduling; worst-case analysis;
D O I
10.1016/S0020-0190(99)00094-0
中图分类号
TP [自动化技术、计算机技术];
学科分类号
0812 ;
摘要
In this paper we study a special case of the two-machine flowshop problem with an availability constraint imposed on each machine. The two availability constraints are consecutive. We establish some basic properties for the semiresumable case, i.e. if a job cannot be finished before the next down period of a machine, then the job will be partially restarted when the machine becomes available again. We provide a heuristic for the problem and show that it has a worst-case error bound of 2/3 for the nonresumable case. (C) 1999 Published by Elsevier Science B.V. All rights reserved.
引用
收藏
页码:49 / 54
页数:6
相关论文
共 50 条
  • [31] Bicriteria Two-Machine Flowshop Scheduling using Metaheuristics
    Mansouri, S. Afshin
    Hendizadeh, S. Hamed
    Salmasi, Nasser
    GECCO 2007: GENETIC AND EVOLUTIONARY COMPUTATION CONFERENCE, VOL 1 AND 2, 2007, : 909 - 909
  • [32] Optimal algorithm for a two-machine flowshop scheduling problem with release dates and blocking constraints
    Jemmali, Mahdi
    Agrebi, Ines
    Alquhayz, Hani
    Ladhari, Talel
    JOURNAL OF THE CHINESE INSTITUTE OF ENGINEERS, 2021, 44 (05) : 440 - 447
  • [33] A two-machine flowshop scheduling heuristic with bicriteria objective
    Lee, CE
    Chou, FD
    INTERNATIONAL JOURNAL OF INDUSTRIAL ENGINEERING-APPLICATIONS AND PRACTICE, 1998, 5 (02): : 128 - 139
  • [34] Two-machine flowshop scheduling to minimize total tardiness
    Pan, JCH
    Fan, ET
    INTERNATIONAL JOURNAL OF SYSTEMS SCIENCE, 1997, 28 (04) : 405 - 414
  • [35] Two-machine flowshop scheduling heuristic with bicriteria objective
    Lee, Ching-En
    Chou, Fuh-Der
    International Journal of Industrial Engineering : Theory Applications and Practice, 1998, 5 (02): : 128 - 139
  • [36] An improved two-machine flowshop scheduling with intermediate transportation
    Dong, Jianming
    Wang, Xueshi
    Hu, Jueliang
    Lin, Guohui
    JOURNAL OF COMBINATORIAL OPTIMIZATION, 2016, 31 (03) : 1316 - 1334
  • [37] Batching and scheduling to minimize the makespan in the two-machine flowshop
    Cheng, TCE
    Wang, GQ
    IIE TRANSACTIONS, 1998, 30 (05) : 447 - 453
  • [38] Two-machine flowshop scheduling in a physical examination center
    Yadong Wang
    Baoqiang Fan
    Jingang Zhai
    Wei Xiong
    Journal of Combinatorial Optimization, 2019, 37 : 363 - 374
  • [39] An improved two-machine flowshop scheduling with intermediate transportation
    Jianming Dong
    Xueshi Wang
    Jueliang Hu
    Guohui Lin
    Journal of Combinatorial Optimization, 2016, 31 : 1316 - 1334
  • [40] Scheduling the fabrication and assembly of components in a two-machine flowshop
    Cheng, TCE
    Wang, GQ
    IIE TRANSACTIONS, 1999, 31 (02) : 135 - 143