4D CAD model updating using image processing-based construction progress monitoring

被引:90
|
作者
Kim, Changyoon [1 ]
Kim, Byoungil [1 ]
Kim, Hyoungkwan [1 ]
机构
[1] Yonsei Univ, Dept Civil Engn, Seoul 120749, South Korea
基金
新加坡国家研究基金会;
关键词
3D CAD; 4D CAD; Cable-stayed bridge; Image processing; Progress monitoring; Project scheduling; APPLICABILITY; MANAGEMENT;
D O I
10.1016/j.autcon.2013.03.005
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
For a four-dimensional (4D) computer-aided design (CAD) model to be useful for users throughout a construction project, the model must be updated in a timely and accurate manner during the construction. Only when it has been properly updated can the 4D CAD model reflect the real progress of a construction site to inform managerial decision making. However, updating a 4D CAD model is time-consuming and labor-intensive because the full updating process, from site data acquisition to 4D model regeneration, is typically conducted manually. This difficulty in updating a 4D model discourages industry practitioners from actively adopting 4D models. This paper presents an image processing-based methodology for the automatic updating of a 4D CAD model. Characterized by 3D CAD-based image mask filters, color-based noise removal, and area-based progress calculation, the image processing approach provides as-built schedule information. The schedule information is then automatically integrated with an existing 3D CAD model in batch-processing modes to produce the updated 4D CAD model. The proposed methodology was applied and verified in a cable-stayed bridge construction project and is expected to facilitate the wider use of 4D CAD models in the construction industry. (c) 2013 Elsevier B.V. All rights reserved.
引用
收藏
页码:44 / 52
页数:9
相关论文
共 50 条
  • [41] Segmentation of cardiac MR and CT image sequences using model based registration of a 4D statistical model
    Perperidis, Dimitrios
    Mohiaddin, Raad
    Edwards, Philip
    Rueckert, Daniel
    MEDICAL IMAGING 2007: IMAGE PROCESSING, PTS 1-3, 2007, 6512
  • [42] Improvement of Link Process in 4D CAD Viewer by Using Interface Board for Construction Project Management
    Leen, Seok Kang
    Hyoun, Seong Kim
    Hyoun, Seok Moon
    Chang, Hak Kim
    2009 THIRD INTERNATIONAL CONFERENCE ON ADVANCED ENGINEERING COMPUTING AND APPLICATIONS IN SCIENCES (ADVCOMP 2009), 2009, : 83 - +
  • [43] Visualizing high-rise building construction strategies using linear scheduling and 4D CAD
    Russell, Alan
    Staub-French, Sheryl
    Tran, Ngoc
    Wong, William
    AUTOMATION IN CONSTRUCTION, 2009, 18 (02) : 219 - 236
  • [44] Construction of a 4D Brain Atlas and Growth Model Using Diffeomorphic Registration
    Schuh, Andreas
    Murgasova, Maria
    Makropoulos, Antonios
    Ledig, Christian
    Counsell, Serena J.
    Hajnal, Jo V.
    Aljabar, Paul
    Rueckert, Daniel
    SPATIO-TEMPORAL IMAGE ANALYSIS FOR LONGITUDINAL AND TIME-SERIES IMAGE DATA, 2015, 8682 : 27 - 37
  • [45] Integration of Radio-Frequency Identification and 4D CAD in Construction Management
    胡文发
    TsinghuaScienceandTechnology, 2008, (S1) : 151 - 157
  • [46] 4D CAD models to support the coordination of construction activities between contractors
    Trebbe, Martijn
    Hartmann, Timo
    Doree, Andre
    AUTOMATION IN CONSTRUCTION, 2015, 49 : 83 - 91
  • [47] 4D Ultrasound Adaptive Image Pre-processing
    Elnokrashy, Ahmed F.
    Kadah, Yasser M.
    2018 35TH NATIONAL RADIO SCIENCE CONFERENCE (NRSC), 2018, : 214 - 222
  • [48] Application of VR Technology linked with 4D CAD System for Construction Project
    Kang, Leen-Seok
    Moon, Hyoun-Seok
    Park, Seo-Young
    Kim, Hyoun-Seong
    Kim, Chang-Hak
    2009 INTERNATIONAL CONFERENCE ON NEW TRENDS IN INFORMATION AND SERVICE SCIENCE (NISS 2009), VOLS 1 AND 2, 2009, : 1058 - +
  • [49] Comparison of simulation-driven construction operations visualization and 4D CAD
    Kamat, VR
    Martinez, JC
    PROCEEDINGS OF THE 2002 WINTER SIMULATION CONFERENCE, VOLS 1 AND 2, 2002, : 1765 - 1770
  • [50] Construction schedule simulation and its application to hydrojunctions of water diversion project based on 4D CAD
    Zhong, DH
    Liu, JM
    Fu, JQ
    Xiong, KZ
    SYSTEM SIMULATION AND SCIENTIFIC COMPUTING, VOLS 1 AND 2, PROCEEDINGS, 2005, : 400 - 405