Major Factors Causing Delay in the Delivery of Manufacturing and Building Projects in Saudi Arabia

被引:28
|
作者
Abdellatif, Hussein [1 ]
Alshibani, Adel [2 ]
机构
[1] KFUPM, Elect Engn Dept, Dhahran 31261, Saudi Arabia
[2] KFUPM, Construct Engn & Management, Dhahran 31261, Saudi Arabia
关键词
industrial projects; delay factors; scheduling; RII; building projects; RESOURCE-BASED THEORY; CONSTRUCTION PROJECTS; COST; ORGANIZATION; ECONOMICS; OVERRUNS; INDUSTRY; RANKING; MODEL; RISK;
D O I
10.3390/buildings9040093
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
There have been many studies done on the causes of delay on construction projects and building projects all around the world. They use different methods, on different geographical areas, and they come up with different results. There are, however, few studies on industrial and building projects. This paper focuses on industrial/manufacturing projects in Saudi Arabia. The aim of this paper is to identify the major causes of delay in the manufacturing projects in Saudi Arabia. The top causes of delay have been identified through a literature survey and interviews with experts from the industrial field in Saudi Arabia. Twenty-two factors have been identified and listed in a survey that was distributed to professionals in the same field. Two categorizations were made: the first is based on the impact of the cause, and the second is based on the frequency of occurrence of the identified cause. It has been found that the top five impacted causes of delay in the delivery of industrial projects in Saudi Arabia are: difficulties in financing project by contractor/manufacturer, late procurement of materials, late delivery of materials, delay in progress payments, and delay in approving design documents, respectively. In terms of frequency, the top five identified causes are: delay in progress payments, difficulties in financing project by contractor/manufacturer, slowness in decision making, late procurement of materials, and delay in approving design documents, respectively. The diversity of the participants is an important point; therefore, the respondents were from different job positions (management, engineering, etc.), and different categories (contractor, owner, manufacturer, consultant, etc.). It is worth noting that this paper serves not only as an authentic study of the causes of delay in the delivery of industrial projects in Saudi Arabia which is a field that is not widely covered, but also as a fresh paper that gives an indication of the changes that happen to the business over time as compared to previous work.
引用
收藏
页数:15
相关论文
共 50 条
  • [31] Critical Success Factors of Public-Private Partnership for Urban Infrastructure Projects in Saudi Arabia
    Alqahtani, Fahad K.
    Alagha, Eid
    Mohamed, Ahmed Gouda
    CONSTRUCTION RESEARCH CONGRESS 2024: CONTRACTING, DELIVERY, SCHEDULING, ESTIMATING, ECONOMICS, AND ORGANIZATIONAL MANAGEMENT AND PLANNING IN CONSTRUCTION, 2024, : 525 - 536
  • [32] Major factors contributing to the construction waste generation in building projects of Iraq
    Khaleel, Tareq
    Al-Zubaidy, Ahmed
    3RD INTERNATIONAL CONFERENCE ON BUILDINGS, CONSTRUCTION AND ENVIRONMENTAL ENGINEERING, BCEE3-2017, 2018, 162
  • [33] Evaluating the critical safety factors causing accidents in high-rise building projects
    Manzoor, Bilal
    Othman, Idris
    Manzoor, Muneeb
    AIN SHAMS ENGINEERING JOURNAL, 2021, 12 (03) : 2485 - 2492
  • [34] Appraising critical success factors in sustainable housing projects: A comparative study of PPP modalities in Saudi Arabia
    Alqahtani, Fahad K.
    Al-Jadhai, Saad
    Alromihy, Hosam
    Alsaud, Mohammed
    Sherif, Mohamed
    Mohamed, Ahmed Gouda
    HELIYON, 2024, 10 (12)
  • [35] Challenging Tendering-Phase Factors in Public Construction Projects-A Delphi Study in Saudi Arabia
    Alahmadi, Nawaf
    Alghaseb, Mohammed
    BUILDINGS, 2022, 12 (07)
  • [36] Significant Factors Causing Delay of Ethiopian Road Construction Projects performing by Foreign General Contactors
    Darsa, Mohammadzen Hasan
    Negash, Biniyam Tsegu
    INTERNATIONAL JOURNAL OF SUSTAINABLE CONSTRUCTION ENGINEERING AND TECHNOLOGY, 2023, 14 (04): : 103 - 116
  • [37] Prevalence and Risk Factors of Speech Delay in Children Less Than Seven Years Old in Saudi Arabia
    Alzahrani, Lena D.
    Aldharman, Sarah S.
    Almuzaini, Ahmed S.
    Aljishi, Arwa A.
    Alrabiah, Nouf M.
    Binshalhoub, Fahad H.
    Alhassun, Joud A.
    Ghmaird, Asmaa S.
    CUREUS JOURNAL OF MEDICAL SCIENCE, 2023, 15 (11)
  • [38] Identifying and assessing critical success factors of value management implementation in Saudi Arabia building construction industry
    Alsolami, Badr M.
    AIN SHAMS ENGINEERING JOURNAL, 2022, 13 (06)
  • [39] Influencing Factors of Cost Control and Environmental Sustainability in Saudi Arabia for Low-Rise Building Construction
    Alhammadi, S. A.
    CIVIL AND ENVIRONMENTAL ENGINEERING, 2022, 18 (02) : 408 - 423
  • [40] Endocrinopathies in beta-thalassemia major Prevalence, risk factors, and age at diagnosis in Northwest Saudi Arabia
    Habeb, Abdelhadi M.
    Al-Hawsawi, Zakaria M.
    Morsy, Mohamed M.
    Al-Harbi, Abdallah M.
    Osilan, Adnan S.
    Al-Magamsi, Mohamed S.
    Zolaly, Mohamed A.
    SAUDI MEDICAL JOURNAL, 2013, 34 (01) : 67 - 73