Modelling and calibration of a five link elastic boom of a mobile concrete pump

被引:2
|
作者
Meiringer, M. [1 ]
Kugi, A. [1 ,2 ]
Kemmetmueller, W. [1 ]
机构
[1] TU Wien, Automat & Control Inst ACIN, Vienna, Austria
[2] Austrian Inst Technol AIT, Ctr Vis Automat & Control, Vienna, Austria
关键词
large-scale manipulator; mobile concrete pump; flexible multibody system; model calibration; computer vision; Euler-Bernoulli; Saint-Venant; MANIPULATORS; SIMULATION;
D O I
10.1080/13873954.2023.2177311
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
Large-scale manipulators, such as the boom of a mobile concrete pump, typically rely on lightweight construction to maximize their operational range. As a result, significant elastic deformations occur during operation. Various automation and control applications require computationally fast and accurate mathematical models of the manipulator's motion. In this work, a mathematical model for the boom of a mobile concrete pump with 5 individual joints is presented. This model takes into account the elastic bending in two directions and the torsion of the boom. To reach a high model accuracy, calibration is required. This is challenging due to the large dimension and the outdoor operation, which makes the accurate measurement of the boom position difficult. A camera-based measurement setup is proposed in this work that is tailored for the considered problem. It is shown by measurements that the model is able to achieve a high accuracy with rather small computational costs.
引用
收藏
页码:41 / 68
页数:28
相关论文
共 50 条
  • [31] Co-simulation on automatic pouring of truck-mounted concrete boom pump
    Zhou, Shuwen
    Zhang, Siqi
    2007 IEEE INTERNATIONAL CONFERENCE ON AUTOMATION AND LOGISTICS, VOLS 1-6, 2007, : 928 - +
  • [32] Numerical simulation and vibration characteristics of boom system of concrete pump truck test rig
    Ren, Wu
    Wu, Yunxin
    Hua, Guangjun
    Zhang, Zhaowei
    Zeng, Yihui
    Zhongnan Daxue Xuebao (Ziran Kexue Ban)/Journal of Central South University (Science and Technology), 2014, 45 (04): : 1065 - 1070
  • [33] Strength and Finite Element Analysis of the Boom System of Truck-mounted Concrete Pump
    Zhou, Xinxiang
    Cui, Yu
    Ren, Nannan
    Tang, Yanling
    Guo, Shujun
    Tian, Rongliang
    MANUFACTURING SCIENCE AND TECHNOLOGY, PTS 1-3, 2011, 295-297 : 2079 - 2082
  • [34] Simulation Control of Concrete Pump Truck Boom Based on PSO and Adaptive Robust PD
    Wang, Tie
    Wang, Gannan
    Liu, Kun
    CCDC 2009: 21ST CHINESE CONTROL AND DECISION CONFERENCE, VOLS 1-6, PROCEEDINGS, 2009, : 960 - +
  • [35] Estimation and control of the tool center point of a mobile concrete pump
    Henikl, J.
    Kemmetmueller, W.
    Kugi, A.
    AUTOMATION IN CONSTRUCTION, 2016, 61 : 112 - 123
  • [36] State-of-the-Art Time Link Calibration with a mobile TWSTFT Station
    Feldmann, Thorsten
    Balu, Arvind
    Molard, Cedric
    Schaefer, Wolfgang
    Piester, Dirk
    2012 EUROPEAN FREQUENCY AND TIME FORUM (EFTF), 2012, : 462 - 468
  • [37] Optimization of Welding Sequence of Concrete Pump Truck Boom and Development of Automated Welding Analysis Program
    Jeong, Seung Hyun
    TRANSACTIONS OF THE KOREAN SOCIETY OF MECHANICAL ENGINEERS A, 2023, 47 (12) : 1031 - 1038
  • [38] Research on rigid-flexible coupling dynamic characteristics of boom system in concrete pump truck
    Tang, Hongbin
    Ren, Wu
    ADVANCES IN MECHANICAL ENGINEERING, 2015, 7 (03) : 1 - 7
  • [39] Hydro-Mechanical Modelling of the Boom Clay Excavation, Convergence and Contact with Concrete Lining
    Francois, Bertrand
    Neve, Jerome
    Levasseur, Severine
    Dizier, Arnaud
    Gerard, Pierre
    ENERGY GEOTECHNICS, SEG-2018, 2019, : 418 - 425
  • [40] Research on Non-Random Vibration Analysis of Concrete Pump Truck Boom Based on Dynamic Excitation
    Zhou, Weixin
    Xu, Wubin
    Li, Bing
    Xiao, Yuanbin
    Liu, Xianyu
    Zhang, Hanwen
    Xu, Bo
    APPLIED SCIENCES-BASEL, 2025, 15 (04):