Analysis of Shear Stagger Deformation of Existing Shield Tunnel below Induced by Quasirectangular Shield Tunneling

被引:0
|
作者
Zhang, Kun [1 ]
Chen, Xi [1 ]
Yin, Wei [1 ]
Hu, Kun [1 ]
Zhu, ShengXue [1 ]
机构
[1] Huaiyin Inst Technol, Huaian 223003, Jiangsu, Peoples R China
关键词
EXCAVATION;
D O I
10.1155/2023/3195453
中图分类号
P3 [地球物理学]; P59 [地球化学];
学科分类号
0708 ; 070902 ;
摘要
To use urban underground space more efficiently is a research hotspot of urban underground development. Compared with conventional circular tunnels, quasirectangular tunnels have the characteristics of larger space utilization and higher economic benefits, gradually used in urban rail engineering in recent years. But the ground disturbance induced by the quasirectangular tunneling needs further researches. This paper derives the calculation formula of the additional stress of existing shield tunnel below caused by the quasirectangular shield tunneling by mirror image method and Mindlin solution. The existing shield tunnel is simplified as an elastic foundation short beam connected by tensile springs and shear springs. This paper establishes the energy-deformation coupling equation by principle of minimum potential energy so that the disturbance induced by quasirectangular tunneling to the existing shield tunnel below can be analyzed. The FEM is established with the actual engineering as the background. It is by comparing the numerical simulation results and field monitoring data that the theoretical prediction formula is verified. The research results show that the theoretical calculation results consist highly with numerical simulation results and field monitoring data, verifying practicality of formulas in this paper. Calculation results of shear stagger model are more accurate, which can be also used to analyze the staggered and splayed amount between segments. As the tunnel construction proceeds, uplift deformation, segment stagger, shear force, and segment splay of existing shield tunnel gradually increase, which are symmetrical about the central axis of new tunnel. After the shield machine passes through the central axis of the existing shield tunnel for 20 meters, stable disturbance to the existing shield tunnel occurs. Stagger amount and shear force between segments reach the minimum at the position with maximum uplift deformation of existing shield tunnel and reach the maximum at inflection point of the uplift deformation curve.
引用
收藏
页数:15
相关论文
共 50 条
  • [21] Deformation of Existing Shield Tunnel Adjacent to Deep Excavations: Simulation and Monitoring Analysis
    Han, Yufeng
    Xu, Qianwei
    Cui, Yuebang
    APPLIED SCIENCES-BASEL, 2024, 14 (10):
  • [22] ANALYSIS OF STRESS AND DEFORMATION OF TUNNEL DUE TO ADJACENT SHIELD TUNNELING WITH DIFFERENT SPACING
    He, Meide
    Liu, Jun
    Le, Guiping
    Zhang, Dingli
    Wang, Mengshu
    KEY TECHNOLOGIES OF RAILWAY ENGINEERING - HIGH SPEED RAILWAY, HEAVY HAUL RAILWAY AND URBAN RAIL TRANSIT, 2010, : 431 - 436
  • [23] NUMERICAL SIMULATION ANALYSIS OF SHIELD TUNNEL UNDERCROSSING EXISTING SUBWAY SHIELD SECTION
    Peng, Hua
    Shi, Jianze
    CONSTRUCTION AND MAINTENANCE OF RAILWAY INFRASTRUCTURE IN COMPLEX ENVIRONMENT, 2014, : 676 - 680
  • [24] Dislocation Deformation of Existing Longitudinal Tunnel Structure Induced by Shield Tunneling by Under-crossing Considering Influence of Lining Permeability
    Zhang, Zhi-Guo
    Cheng, Zhi-Xiang
    Zhang, Meng-Xi
    Ma, Shao-Kun
    Lu, Xi-Lin
    Zhongguo Gonglu Xuebao/China Journal of Highway and Transport, 2022, 35 (11): : 180 - 194
  • [25] Analysis of Pipeline Deformation Caused by Shield Tunnel Excavation that Obliquely Crosses Existing Pipelines
    Sheng-Wu Zhao
    Xiao-Li Li
    Xin Li
    Li-Guang Chen
    Tong Li
    Suo-Hui Li
    Yu Bai
    Arabian Journal of Geosciences, 2022, 15 (3)
  • [26] Deformation analysis of shield undercrossing and vertical paralleling excavation with existing tunnel in composite stratum
    Zhou, Zhong
    Zheng, Yi-di
    Hu, Jiang-feng
    Yang, Hao
    Gong, Chen-jie
    JOURNAL OF CENTRAL SOUTH UNIVERSITY, 2023, 30 (09) : 3127 - 3144
  • [27] Analysis of deformation of levee caused by large diameter shield tunneling in river crossing tunnel
    Lu, Zhongxiang
    Shou, Lingchao
    Abdullah, Rini Asnida
    Shahrin, Muhammad Irfan Bin
    Chen, Yintao
    Xin, Shao
    Fan, Wenju
    Islam, Amber
    Zhang, Hengxu
    REVISTA INTERNACIONAL DE METODOS NUMERICOS PARA CALCULO Y DISENO EN INGENIERIA, 2024, 40 (01):
  • [28] Analysis of longitudinal deformation of shield tunnel subjected to shield tail asymmetric thrust
    Zhang Zhi-wei
    Liang Rong-zhu
    Li Zhong-chao
    Sun Lian-wei
    Shen Wen
    Wu Wen-bing
    ROCK AND SOIL MECHANICS, 2023, 44 (01) : 88 - 98
  • [29] Analysis for Influence of Excavation on Adjacent Existing Shield Tunnel
    Cao, Jing
    Qian, Guowei
    Zuo, Haixi
    Liu, Haiming
    Ren, Yaliang
    Proceedings of the 2016 4th International Conference on Mechanical Materials and Manufacturing Engineering (MMME 2016), 2016, 79 : 650 - 657
  • [30] Prediction of ground deformation induced by shield tunneling construction
    Department of Civil Engineering, Zhejiang University City College, Hangzhou 310015, China
    Yanshilixue Yu Gongcheng Xuebao, 2009, 2 (418-424):