The Construction Methods and Control Mechanisms for Subway Station Undercrossing an Existing Tunnel at Zero Distance

被引:6
|
作者
Zhou, Zihan [1 ,2 ,3 ]
Zhou, Xiaohan [1 ,2 ,3 ]
Li, Longping [4 ]
Liu, Xinrong [1 ,2 ,3 ]
Wang, Linfeng [1 ,2 ,3 ]
Wang, Ziqiang [1 ,2 ,3 ]
机构
[1] Chongqing Univ, Sch Civil Engn, Chongqing 400045, Peoples R China
[2] Chongqing Univ, Natl Joint Engn Res Ctr Geohazards Prevent Reservo, Chongqing 400045, Peoples R China
[3] Chongqing Univ, Key Lab New Technol Construct Cities Mt Area, Minist Educ, Chongqing 400045, Peoples R China
[4] China Railway Major Bridge Reconnaissance & Design, Wuhan 430056, Peoples R China
来源
APPLIED SCIENCES-BASEL | 2023年 / 13卷 / 15期
基金
中国国家自然科学基金;
关键词
subway station excavation; zero-distance undercrossing; existing metro tunnel; deformation control; numerical simulation; TWIN TUNNELS; EXCAVATION; DEFORMATION; MODEL;
D O I
10.3390/app13158826
中图分类号
O6 [化学];
学科分类号
0703 ;
摘要
The existing tunnel will inevitably be disturbed when the new subway station is constructed cross under it at zero distance. Three innovative construction schemes were proposed, their effects on deformation control were compared by numerical simulations, and the mechanism of the influence of different tunnel support and excavation methods on the deformation control in them was further explored in order to seek a better scheme in this paper. The results show that the settlement of the existing tunnel in Scheme I (L-type beam + full-face excavation) is the greatest, and that the one in Scheme III (temporary steel column + double-pilot tunnel) is the smallest, but the settlement during excavation changes significantly, along with the large deformation on the side walls of the undercrossing area. Scheme III is not recommended because it is difficult to control and the construction effect is mediocre. Due to the existence of a large free face, the settlement of both sides of the existing tunnel is larger when the L-type beam supports the tunnel, and the bottom of the middle wall bears large compressive stress. The settlement of the existing tunnel excavated by the double-pilot tunneling method is less than that of the full-face tunneling method under the same tunneling support method, and the increase in settlement during the tunneling with the L-type beams is greater than that with the pier columns. In comprehensive consideration, Scheme II (pier column + double-pilot tunnel method) or combined pier column + double-pilot tunnel can control the deformation better.
引用
收藏
页数:26
相关论文
共 50 条
  • [41] Control of existing tunnel deformation caused by shield adjacent undercrossing construction using interpretable machine learning and multiobjective optimization
    Chen, Hongyu
    Liu, Jun
    Shen, Geoffrey Qiping
    Feng, Zongbao
    Automation in Construction,
  • [42] Control of existing tunnel deformation caused by shield adjacent undercrossing construction using interpretable machine learning and multiobjective optimization
    Chen, Hongyu
    Liu, Jun
    Shen, Geoffrey Qiping
    Feng, Zongbao
    AUTOMATION IN CONSTRUCTION, 2025, 170
  • [43] Crossing construction methods of subway station under building
    Wang C.-B.
    Shao P.
    Zhejiang Daxue Xuebao (Gongxue Ban)/Journal of Zhejiang University (Engineering Science), 2019, 53 (01): : 69 - 77
  • [44] Deformation and mechanical characteristics of tunnel lining in tunnel intersection between subway station tunnel and construction tunnel
    Li, Yayong
    Jin, Xiaoguang
    Lv, Zhitao
    Dong, Jianghui
    Guo, Jincheng
    TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2016, 56 : 22 - 33
  • [45] CONSTRUCTION CONTROL OF SHIELD TUNNELING THROUGH EXISTING SUBWAY
    Peng, Xua
    Xie, Tongtong
    NEW TECHNOLOGIES OF RAILWAY ENGINEERING, 2012, : 737 - 742
  • [46] Model Test Study on Metro Shield Construction Undercrossing Existing Open-Cut Tunnel
    Liu Y.
    Cao Y.
    Wu X.
    Fan H.
    Zhou Y.
    Song Y.
    Lin J.
    Zhongguo Tiedao Kexue/China Railway Science, 2024, 45 (01): : 110 - 121
  • [47] Research on the Construction Impact and Control of Shield Crossing over Existing Tunnel at Close Distance
    Xing, Huitang
    Xu, Qianwei
    Liu, Hao
    Liu, Yi
    He, Xiang
    Wu, Bing
    Journal of Railway Engineering Society, 2021, 38 (09) : 61 - 67
  • [48] Construction of Chongwerimen station passing under existing subway with underground excavation method
    Ma, S. Z.
    Qiao, C. S.
    BOUNDARIES OF ROCK MECHANICS: RECENT ADVANCES AND CHALLENGES FOR THE 21ST CENTURY, 2008, : 343 - +
  • [49] Research on influence and monitoring of shield tunnel obliquely crossing beneath existing subway station
    Beijing Municipal Engineering Research Institute, Beijing 100037, China
    不详
    Yanshilixue Yu Gongcheng Xuebao, 2009, SUPPL. 1 (3186-3192):
  • [50] Analysis on the mechanical effect of metro tunnel construction of Chongqing North Station with zero distance stereo crossing
    地铁重庆北站零距离立体交叉暗挖施工力学效应分析
    1600, Chinese Society of Civil Engineering (50):