Design and construction of Morocco's Asfalou dam

被引:0
|
作者
Chraibi, A. [1 ]
Mekboul, M. [1 ]
Monkachi, M. [1 ]
机构
[1] INGEMA, Morocco
来源
关键词
Construction - Drainage - Foundations - Geotechnical engineering - Hydroelectric power - Rivers - Spillways - Structural design - Structural geology - Water supply;
D O I
暂无
中图分类号
学科分类号
摘要
The design and construction of the recently completed 107 m-high Asfalou arch dam in Morocco is described. The structure is a major element in the development of the Ouergha river for water supply and hydropower. This article presents in particular the geological and geotechnical background as well as the main features of the dam, bottom outlet, power station, spillway, diversion tunnel, grouting and drainage galleries, foundation treatment, drainage curtain, and monitoring equipment. Execution of works for the dam arch and spillway are likewise discussed.
引用
收藏
页码:62 / 66
相关论文
共 50 条
  • [21] Practical issues in design and construction of dam earthworks
    Neeve D.
    Brown A.J.
    Neeve, David (david.neeve@arup.com), 2018, ICE Publishing (28) : 153 - 167
  • [22] Design, construction and performance monitoring of the submerged toe drain at Inco's rock dam
    Semenoff, KJ
    Plewes, HD
    Remington, G
    TAILINGS AND MINE WASTE '99, 1999, : 249 - 258
  • [23] RCC dams design and construction in Morocco - specific aspects
    Chraibi, AF
    ROLLER COMPACTED CONCRETE DAMS, 2003, : 229 - 231
  • [24] DESIGN AND CONSTRUCTION OF THE LENIHAN DAM OUTLET TUNNEL AND SHAFT
    Desai, Hemang
    Mainer, Brett
    Murray, Mike
    Spreng, Shawn
    2009 RAPID EXCAVATION AND TUNNELING CONFERENCE, PROCEEDINGS, 2009, : 171 - +
  • [25] CURRENT TAILINGS DAM DESIGN AND CONSTRUCTION METHODS.
    Klohn, Earle J.
    Mining Engineering, 1981, 33 (07) : 798 - 808
  • [26] DESIGN, CONSTRUCTION AND PERFORMANCE OF COW GREEN EMBANKMENT DAM
    VAUGHAN, PR
    LOVENBURY, HT
    HORSWILL, P
    GEOTECHNIQUE, 1975, 25 (03): : 555 - 580
  • [27] Design and underground construction at the Xiaolangdi Multipurpose Dam site
    Wang, X
    Solymar, ZV
    TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 1997, 12 (04) : 461 - 472
  • [28] Reconstructed Carsington Dam: Design and performance, and construction - Discussion
    Chalmers, RW
    Vaughan, PR
    Coats, DJ
    MacDonald, A
    Dawson, GM
    Coleshill, DC
    Pontin, JMA
    Cox, DW
    Reid, JM
    Rocke, G
    PROCEEDINGS OF THE INSTITUTION OF CIVIL ENGINEERS-WATER MARITIME AND ENERGY, 1995, 112 (04): : 375 - 380
  • [29] The Upper Paunglaung RCC dam-design and construction
    Zaw, U. Myint
    Han, U. Thaung
    Rohrer, Ch.
    Steiger, K. M.
    DAMS AND RESERVOIRS UNDER CHANGING CHALLENGES, 2011, : 559 - 567
  • [30] Ralco dam, Chile - features of its design and construction
    Croquevielle, D
    Uribe, L
    Mutis, R
    Forbes, BA
    ROLLER COMPACTED CONCRETE DAMS, 2003, : 589 - 596