Nuclear reactors' construction costs: The role of lead-time, standardization and technological progress

被引:0
|
作者
Berthélemy, Michel [1 ,2 ]
Escobar Rangel, Lina [2 ]
机构
[1] Institut de technico-économie des systemes énergétiques (I-tésé), Commissariat a l'Energie Atomique, Université Paris Saclay, Gif-sur-Yvette Cedex,91191, France
[2] Centre d'Economie Industrielle, École des Mines de Paris, PSL Research University, Paris,75006, France
关键词
Nuclear reactors - Cost benefit analysis;
D O I
暂无
中图分类号
学科分类号
摘要
This paper provides an econometric analysis of nuclear reactor construction costs in France and the United States based on overnight costs data. We build a simultaneous system of equations for overnight costs and construction time (lead-time) to control for endogeneity, using change in expected electricity demand as instrument. We argue that the construction of nuclear reactors can benefit from standardization gains through two channels. First, short term coordination benefits can arise when the diversity of nuclear reactors' designs under construction is low. Second, long term benefits can occur due to learning spillovers from past constructions of similar reactors. We find that construction costs benefit directly from learning spillovers but that these spillovers are only significant for nuclear models built by the same Architect-Engineer. In addition, we show that the standardization of nuclear reactors under construction has an indirect and positive effect on construction costs through a reduction in lead-time, the latter being one of the main drivers of construction costs. Conversely, we also explore the possibility of learning by searching and find that, contrary to other energy technologies, innovation leads to construction costs increases. © 2015 Elsevier Ltd.
引用
收藏
页码:118 / 130
相关论文
共 26 条
  • [1] Nuclear reactors' construction costs: The role of lead-time, standardization and technological progress
    Berthélemy, Michel
    Escobar Rangel, Lina
    Energy Policy, 2015, 82 (01) : 118 - 130
  • [2] Nuclear reactors' construction costs: The role of lead-time, standardization and technological progress
    Berthelemy, Michel
    Rangel, Lina Escobar
    ENERGY POLICY, 2015, 82 : 118 - 130
  • [3] ROLE OF STANDARDIZATION IN TECHNOLOGICAL PROGRESS
    ALDEN, AE
    JOURNAL OF THE SOCIETY OF MOTION PICTURE TELEVISION ENGINEERS, 1966, 75 (09): : 876 - &
  • [4] Delivery lead-time model of construction supply chain
    Gong, Daihua
    Liu, Xuemei
    PROCEEDINGS OF 2007 INTERNATIONAL CONFERENCE ON CONSTRUCTION & REAL ESTATE MANAGEMENT, VOLS 1 AND 2, 2007, : 804 - 807
  • [5] Progress in the construction of nuclear reactors from hot nuclear fusion
    Polaczek, Jerzy
    PRZEMYSL CHEMICZNY, 2022, 101 (04): : 230 - 231
  • [6] Historical construction costs of global nuclear power reactors
    Lovering, Jessica R.
    Yip, Arthur
    Nordhaus, Ted
    ENERGY POLICY, 2016, 91 : 371 - 382
  • [7] Manufacturing lead-time rules: Customer retention versus tardiness costs
    Slotnick, SA
    Sobel, MJ
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2005, 163 (03) : 825 - 856
  • [8] UNDERSTANDING THE LEAD-TIME EFFECTS IN STOCHASTIC INVENTORY SYSTEMS WITH DISCOUNTED COSTS
    SONG, JS
    OPERATIONS RESEARCH LETTERS, 1994, 15 (02) : 85 - 93
  • [9] A reply to "Historical construction costs of global nuclear power reactors"
    Koomey, Jonathan
    Hultman, Nathan E.
    Grubler, Arnulf
    ENERGY POLICY, 2017, 102 : 640 - 643
  • [10] Production lead-time hedging and coordination in prefabricated construction supply chain management
    Zhai, Yue
    Zhong, Ray Y.
    Li, Zhi
    Huang, George
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2017, 55 (14) : 3984 - 4002