Automatic Planning Method of Construction Schedule under Multi-Dimensional Spatial Resource Constraints

被引:0
|
作者
Wang, Luqi [1 ]
Li, Jinrui [1 ]
Ye, Qizhi [1 ]
Li, Yan [1 ]
Feng, Anqi [2 ]
机构
[1] Guangdong Univ Technol, Sch Civil & Transportat Engn, Guangzhou 510006, Peoples R China
[2] Guangzhou Univ, Sch Management, Guangzhou 510006, Peoples R China
基金
中国国家自然科学基金;
关键词
building information modelling (BIM); data-driven; spatial-constrained; schedule planning; building construction management; WORK BREAKDOWN STRUCTURE; GENERATION;
D O I
10.3390/buildings14103231
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
To enhance the application of building information modeling (BIM) in schedule management for engineering projects, improve spatial planning capabilities, and minimize subjective factors in schedule preparation, this paper presents a framework and method for automatic construction schedule planning based on BIM and data-driven approaches under multi-dimensional spatial resource constraints. The method includes data acquisition, construction process reasoning, time parameter calculation, and schedule generation and scheduling. Initially, the construction data from the BIM model and manual input are imported into the reasoning system to establish the logical relationships of the construction process. Construction time parameters and spatial resource requirements are then automatically calculated using MySQL. Subsequently, the spatial layout and resource allocation data exported from the BIM model are compared to assess whether the space meets the project requirements. Finally, a construction schedule that satisfies the space constraints is generated. The method was validated through a case study, demonstrating its effectiveness in automatic schedule planning under human-computer interaction. This study introduces an innovative approach that considers spatial conflicts in the automatic scheduling process, improving planning efficiency and reducing the risk of spatial conflicts on construction sites.
引用
收藏
页数:18
相关论文
共 50 条
  • [1] PLANNING OF CONSTRUCTION SCHEDULE WITH FLEXIBLE CONSTRAINTS
    Kulejewski, Janusz
    MODERN BUILDING MATERIALS, STRUCTURES AND TECHNIQUES, 10TH INTERNATIONAL CONFERENCE 2010, VOL I, 2010, : 442 - 445
  • [2] Evolutionary branching under multi-dimensional evolutionary constraints
    Ito, Hiroshi
    Sasaki, Akira
    JOURNAL OF THEORETICAL BIOLOGY, 2016, 407 : 409 - 428
  • [3] Multi-Agent Path Planning Under Observation Schedule Constraints
    Yang, Ziqi
    Tron, Roberto
    2020 IEEE/RSJ INTERNATIONAL CONFERENCE ON INTELLIGENT ROBOTS AND SYSTEMS (IROS), 2020, : 6990 - 6997
  • [4] A Method of Multi-Dimensional Information Spatial Partitioning and Intelligent Communication Path Planning of Metallurgical Equipment
    Kong, Jianyi
    Liu, Junwei
    Li, Yongbing
    Wang, Xingdong
    Zhou, Min
    APPLIED MATHEMATICS & INFORMATION SCIENCES, 2013, 7 (02): : 583 - 593
  • [5] A multi-dimensional model of Enterprise Resource Planning critical success factors
    Vargas, Marcela Alejandra
    Comuzzi, Marco
    ENTERPRISE INFORMATION SYSTEMS, 2020, 14 (01) : 38 - 57
  • [6] MULTI-DIMENSIONAL TREATMENT PLANNING
    GOITEIN, M
    MOULTON, G
    ABRAMS, M
    MEDICAL PHYSICS, 1984, 11 (03) : 410 - 410
  • [7] Planning under resource constraints
    Koehler, J
    ECAI 1998: 13TH EUROPEAN CONFERENCE ON ARTIFICIAL INTELLIGENCE, PROCEEDINGS, 1998, : 489 - 493
  • [8] S-Type Velocity Planning Using CNC Multi-Dimensional Constraints
    Wu J.
    Xu K.
    Zhou H.
    Fan D.
    Jisuanji Fuzhu Sheji Yu Tuxingxue Xuebao/Journal of Computer-Aided Design and Computer Graphics, 2023, 35 (09): : 1439 - 1449
  • [9] Multi-dimensional utility model for selection of a trenchless construction method
    Allouche, EN
    Ariaratnam, ST
    AbouRizk, SM
    CONSTRUCTION CONGRESS VI, PROCEEDING: BUILDING TOGETHER FOR A BETTER TOMORROW IN AN INCREASINGLY COMPLEX WORLD, 2000, : 543 - 553
  • [10] The multi-dimensional super-replication problem under gamma constraints
    Cheridito, P
    Soner, HM
    Touzi, N
    ANNALES DE L INSTITUT HENRI POINCARE-ANALYSE NON LINEAIRE, 2005, 22 (05): : 633 - 666