Research on the cost estimation of transmission line project with case-based reasoning

被引:0
|
作者
Yi, Tao [1 ]
Cui, Shanshan [1 ]
Zhang, Yi [1 ]
机构
[1] Department of Management science and Engineering, North China Electric Power University, Beijing, China
来源
关键词
Case based reasoning - Cost engineering - Cost estimating - Forecasting - Investments - Multivariant analysis;
D O I
暂无
中图分类号
学科分类号
摘要
Investment estimation phase of power transmission line project is an important stage of project cost control, the traditional unit investment forecasting methods, however, cannot meet the need of engineering rapid estimation. The research objective of this paper is to forecast the unit investment of the Transmission Line Project applying the case-based reasoning system. Based on the factor analysis tools of multivariate statistical software SPSS, the correlation coefficient matrix of characteristics factors are identified, and weight coefficient of characteristics factors is calculated. Based on the formula of European weighted distance, the similarity is calculated and case similarity is retrieved. Finally, the model is constructed to predict the unit investment of Transmission Line project, and the correctness and usefulness of the model is verified. It is shown that this case-based reasoning system of unit investment can achieve real-time updating of cost index database. The primary contribution of this research is the combination of the cost forecast and Case-based reasoning system of artificial intelligence. It is expected that this work will provide a reference and guidance for transmission line project investment decision in estimating phase.
引用
收藏
页码:1034 / 1041
相关论文
共 50 条
  • [31] Research on Case-based Reasoning combined with Rule-based Reasoning for emergency
    Da Shimin
    Shen Huizhang
    Liu Hong
    PROCEEDINGS OF THE 2007 IEEE INTERNATIONAL CONFERENCE ON SERVICE OPERATIONS AND LOGISTICS, AND INFORMATICS, 2007, : 510 - +
  • [32] Combining case-based reasoning with genetic algorithm optimization for preliminary cost estimation in construction industry
    Kim, Sangyong
    Shim, Jae Heon
    CANADIAN JOURNAL OF CIVIL ENGINEERING, 2014, 41 (01) : 65 - 73
  • [33] Case-based reasoning and improved adaptive search for project scheduling
    Schirmer, A
    NAVAL RESEARCH LOGISTICS, 2000, 47 (03) : 201 - 222
  • [34] CASE-BASED REASONING
    EHRENBERG, D
    PETERSOHN, H
    WIRTSCHAFTSINFORMATIK, 1994, 36 (02): : 166 - 168
  • [35] CASE-BASED REASONING
    LEHNERT, W
    AI MAGAZINE, 1990, 11 (03) : 29 - 29
  • [36] Planning of a Case-based Reasoning Logistics Service Project System
    Bai, Shiqiang
    Liu, Qiuping
    IEEE/SOLI'2008: PROCEEDINGS OF 2008 IEEE INTERNATIONAL CONFERENCE ON SERVICE OPERATIONS AND LOGISTICS, AND INFORMATICS, VOLS 1 AND 2, 2008, : 2387 - 2390
  • [37] CASE-BASED REASONING
    LEAKE, DB
    KNOWLEDGE ENGINEERING REVIEW, 1994, 9 (01): : 61 - 64
  • [38] Case-Based Reasoning
    Aha, DW
    AI MAGAZINE, 1995, 17 (01) : 92 - 92
  • [39] Research on case-based reasoning in automatic weapon design
    Hu, Liangming
    Xu, Cheng
    Tian, Shiyin
    Zhang, Jingzhu
    Li, Feng
    PROCEEDINGS OF THE INTERNATIONAL CONFERENCE ON MECHANICAL ENGINEERING AND MECHANICS 2007, VOLS 1 AND 2, 2007, : 1811 - 1814
  • [40] Research on innovative methods based on clustering and case-based reasoning
    Shang, Kun
    2021 INTERNATIONAL CONFERENCE ON IMAGE, VIDEO PROCESSING, AND ARTIFICIAL INTELLIGENCE, 2021, 12076