Analysis of stratum deformation and pile foundation response during subway station built by pile-beam-arch construction method

被引:0
|
作者
School of Civil Engineering and Architecture, Beijing Jiaotong University, Beijing 100044, China [1 ]
不详 [2 ]
机构
来源
Beijing Jiaotong Daxue Xuebao | 2008年 / 3卷 / 30-36期
关键词
D O I
暂无
中图分类号
学科分类号
摘要
Based on the construction of Beijing subway line 10 of Guomao station, the influence law of surrounding stratum and adjacent pile foundation is analyzed as the large span separation-formula subway station is built by Pile-Beam-Arch construction method. The field measurement indicates that: (1) the longitudinal stratum settlement caused by the hole-pile construction can be described in three areas, named as: initial settlement, sudden settlement, and convergent area of the settlement. And the sudden depressed section can be defined in three stages: the lead-hole's construction, the buckle arch, the lower part's excavation; (2) The horizontal deformation conforms to the Peck curve and the affected area is 3-4 times of hole-diameter. Using three dimensions dynamic numerical simulation during construction process, the distortion of neighboring pile foundation as well as the surface settlement caused by station construction are analyzed. The result matches well with field monitoring data. It shows that the neighboring pile foundation's settlement and the deformation are consist of three steps: lead-hole's excavation, the buckle arch, the lower part's soil excavation, which is corresponded to the construction process. Some useful conclusion is drawn in this paper. Firstly, it is indicated that the key factor of settlement influence of construction to adjacent pile foundation is space position between the pile and station, such as the minimum distance between the pile foundation and the station structure etc.. Secondly, it is obtained that the stratum condition which near the pile end also contributes certain influences on this settlement; Further more, it is introduced that the disturbing influence of construction to adjacent pile foundation in the horizontal direction is extremely remarkable, the buckle arch construction has the biggest influence to the lateral deformation of neighboring pile foundation. At last, the deformation of the side pile, middle side pile, low side pile and the other neighboring pile foundations are summarized in the article.
引用
收藏
页码:30 / 36
相关论文
共 50 条
  • [31] Impact of Pile-Beam-Arch Tunnel Enlargement Method on Ground Movements and Building Damage
    Sedghi, M.
    Golshani, A.
    GEOTECHNICAL AND GEOLOGICAL ENGINEERING, 2024, 42 (04) : 2361 - 2386
  • [33] Monitoring and finite element analysis of deep horizontal displacement of foundation pit enclosure pile of a subway transfer station during construction
    Sun, Wei
    Chen, Haojie
    Li, Bing
    Liu, Yafeng
    2021 2ND INTERNATIONAL CONFERENCE ON BIG DATA & ARTIFICIAL INTELLIGENCE & SOFTWARE ENGINEERING (ICBASE 2021), 2021, : 319 - 323
  • [34] Deformation control and countermeasures for construction surface when using pile-beam-arch method in confined water-rich sand cross-stratification
    Xue-Gang, Zhang
    Song, Zhan-Ping
    Yuan, Chi-Yu
    Qu, Jian-Sheng
    Electronic Journal of Geotechnical Engineering, 2014, 19 (0Y): : 8727 - 8739
  • [35] Numerical Simulation Analysis on Construction Process of Pile Method Pilot Tunnel of a Subway Station in Xi ' an
    Wang, Zhao-Jun
    Ren, Jian-Xi
    Chi-gan, Xiang-Ming
    Zhang, Liang
    Zhang, Yang
    2022 8TH INTERNATIONAL CONFERENCE ON HYDRAULIC AND CIVIL ENGINEERING: DEEP SPACE INTELLIGENT DEVELOPMENT AND UTILIZATION FORUM, ICHCE, 2022, : 664 - 667
  • [36] Dynamic Simulation Analysis of Large Space Subway Station Construction with Cavern-Pile Method
    Gong, Zhiqun
    Zhang, Fen
    Zhang, Yantao
    Gong, Yijun
    Gao, Dongbo
    ELECTRONIC JOURNAL OF GEOTECHNICAL ENGINEERING, 2019, 24 (05): : 1345 - 1361
  • [37] Analytical Solution of Loosening Pressure Model for Shallow Tunnel Based on Pile-Beam-Arch Method
    Tao Li
    Zhongyu Zhang
    Muchi Luo
    Bo Liu
    Yanlong Wang
    Lingfeng Li
    KSCE Journal of Civil Engineering, 2022, 26 : 3648 - 3662
  • [38] Analytical Solution of Loosening Pressure Model for Shallow Tunnel Based on Pile-Beam-Arch Method
    Li, Tao
    Zhang, Zhongyu
    Luo, Muchi
    Liu, Bo
    Wang, Yanlong
    Li, Lingfeng
    KSCE JOURNAL OF CIVIL ENGINEERING, 2022, 26 (08) : 3648 - 3662
  • [39] Comparison of shallow tunneling method with pile and rib method for construction of subway station in soft ground
    Sina Amiri
    Ali Naghi Dehghan
    Frontiers of Structural and Civil Engineering, 2022, 16 : 704 - 717
  • [40] Comparison of shallow tunneling method with pile and rib method for construction of subway station in soft ground
    Sina AMIRI
    Ali Naghi DEHGHAN
    Frontiers of Structural and Civil Engineering, 2022, 16 (06) : 704 - 717