Field tests on large deformation control method for surrounding rock of deep tunnel in fault zone with high geostress

被引:0
|
作者
Wang, Dao-Yuan [1 ,2 ,3 ]
Liu, Jia [1 ]
Zhang, Chuo [4 ]
Yuan, Jin-Xiu [1 ]
Zhu, Yong-Quan [2 ,3 ]
Liu, Hui [5 ]
Cui, Guang-Yao [6 ]
机构
[1] Department of Civil Engineering, Hebei Jiaotong Vocational and Technical College, Shijiazhuang,050091, China
[2] Key Laboratory of Transportation Tunnel Engineering, Ministry of Education, Southwest Jiaotong University, Chengdu,610031, China
[3] School of Civil Engineering, Shijiazhuang Tiedao University, Shijiazhuang,050043, China
[4] PowerChina Hebei Electric Power Design & Research Institute Co., Ltd., Shijiazhuang,050031, China
[5] China Railway 19th Bureau Group Co., Ltd., Beijing,100176, China
[6] College of Architecture and Civil Engineering, North China University of Technology, Beijing,100144, China
关键词
In view of the actual situation of large buried depth; high crustal stress and large deformation of Xinlian tunnel; field tests on support force and deformation control methods are carried out with single-layer support; double-layer support; rigid strong support; advanced pilot tunnel + expansion scheme. The results show that: (1) The original design scheme No.1 is not strong enough to resist the deformation pressure of surrounding rock. The stress ratio of flat guide support exceeds the design stress value by 100%; the invading limit of support is serious; and the arch replacement rate is 100%. (2) The double-layer support scheme No.2 of combining resistance with resistance is adopted. The synchronous operation of lower bench and inverted arch simplifies the operation sequence; but it is not conducive to stress release. The inverted arch is uplift crack and the rate of changing arch of side wall is 84%. When the lower bench and the inverted arch are sectioned and operated; the stress in the inverted arch is slowly released; and the large deformation is controlled. (3) Scheme No. 3 of rigid strong support by 'H175 steel+large arch boot sleeve+lock foot anchor sleeve' is adopted; the overall rigidity of the arch is improved; the maximum convergence deformation rate is reduced by 42.4%; and the excavation per month can reach more than 90 m. (4) Scheme No. 4 of 'leading tunnel + enlarging excavation' is adopted to realize the stress release by stages; and the large deformation is effectively controlled. However; the application of fiber- reinforced concrete and the demolition of leading tunnel support increase the cost and process. Scheme No.3 is recommended of for its economical rationality; simple construction procedure; and flexible support adjustment. Scheme No.4 can be as a preparation scheme for larger deformation of surrounding rock. At the same time; the reserved deformation of vault can be approximately 1/2 of the reserved deformation of side wall. © 2020; Editorial Office of Chinese Journal of Geotechnical Engineering. All right reserved;
D O I
暂无
中图分类号
学科分类号
摘要
引用
收藏
页码:658 / 666
相关论文
共 50 条
  • [31] Study on Large Deformation Control Technology and Engineering Application of Tunnel with High Ground Stress and Weak Broken Surrounding Rock
    Kong, Xiangyong
    Chen, Xu
    Tang, Chun'an
    Sun, Zhaorui
    Hu, Enhuai
    STRUCTURAL ENGINEERING INTERNATIONAL, 2022, 32 (03) : 298 - 306
  • [32] Numerical investigation of geostress influence on the grouting reinforcement effectiveness of tunnel surrounding rock mass in fault fracture zones
    Xu, Xiangyu
    Wu, Zhijun
    Weng, Lei
    Chu, Zhaofei
    Liu, Quansheng
    Zhou, Yuan
    JOURNAL OF ROCK MECHANICS AND GEOTECHNICAL ENGINEERING, 2024, 16 (01) : 81 - 101
  • [33] Deep Fracturing of the Hard Rock Surrounding a Large Underground Cavern Subjected to High Geostress: In Situ Observation and Mechanism Analysis
    Feng, Xia-Ting
    Pei, Shu-Feng
    Jiang, Quan
    Zhou, Yang-Yi
    Li, Shao-Jun
    Yao, Zhi-Bin
    ROCK MECHANICS AND ROCK ENGINEERING, 2017, 50 (08) : 2155 - 2175
  • [34] Deep Fracturing of the Hard Rock Surrounding a Large Underground Cavern Subjected to High Geostress: In Situ Observation and Mechanism Analysis
    Xia-Ting Feng
    Shu-Feng Pei
    Quan Jiang
    Yang-Yi Zhou
    Shao-Jun Li
    Zhi-Bin Yao
    Rock Mechanics and Rock Engineering, 2017, 50 : 2155 - 2175
  • [35] Deformation analysis of a soft-hard rock contact zone surrounding a tunnel
    Feng, Wenkai
    Huang, Runqiu
    Li, Tianbin
    TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2012, 32 : 190 - 197
  • [36] Analysis on Loose Circle of Surrounding Rock of Large Deformation Soft-Rock Tunnel
    Wang, Rui
    Liu, Yiyuan
    Deng, Xianghui
    Zhang, Yu
    Huang, Xiaodong
    Ding, Xiao
    ADVANCES IN CIVIL ENGINEERING, 2020, 2020
  • [37] A Solution Method for Tunnel Supporting Structure System Incorporating the Active Control of Surrounding Rock Deformation
    Zhou, Zihan
    Chen, Ziquan
    He, Chuan
    Jiang, Changwei
    Li, Tiansheng
    INTERNATIONAL JOURNAL OF GEOMECHANICS, 2024, 24 (01)
  • [38] Engineering Properties of Soft Rock with High Geostress and the Performance Under Excavation of Deep Tunnel
    Yingdong Pan
    Heng Zhang
    Zihan Hao
    Gang Zhang
    Shougen Chen
    Lu Wang
    Arabian Journal for Science and Engineering, 2022, 47 : 13349 - 13364
  • [39] Study on the stability control of deep soft rock caverns in the high geostress
    Fu Zhiliang
    Wang Hanpeng
    3RD INTERNATIONAL SYMPOSIUM ON MODERN MINING & SAFETY TECHNOLOGY PROCEEDINGS, 2008, : 487 - 493
  • [40] Engineering Properties of Soft Rock with High Geostress and the Performance Under Excavation of Deep Tunnel
    Pan, Yingdong
    Zhang, Heng
    Hao, Zihan
    Zhang, Gang
    Chen, Shougen
    Wang, Lu
    ARABIAN JOURNAL FOR SCIENCE AND ENGINEERING, 2022, 47 (10) : 13349 - 13364