Analysis of Shield Tunneling Parameters and Research on Prediction Model of Tunneling Excavation Speed in Volcanic Ash Strata of Jakarta-Bandung High-Speed Railway Project

被引:0
|
作者
Fan, Xiaomin [1 ]
Tan, Zhongsheng [1 ]
Zhang, Baojin [1 ]
Zhao, Jinpeng [1 ]
Cao, Yuxin [2 ]
Jiang, Yongtao [2 ]
机构
[1] Beijing Jiaotong Univ, Key Lab Minist Educ Urban Underground Engn, Beijing 100044, Peoples R China
[2] Power China Railway Construct Co Ltd, Beijing 100044, Peoples R China
来源
APPLIED SCIENCES-BASEL | 2024年 / 14卷 / 11期
关键词
tunnel engineering; excavation parameters; volcanic ash strata; optimization; random forest; MACHINE; NETWORK;
D O I
10.3390/app14114623
中图分类号
O6 [化学];
学科分类号
0703 ;
摘要
Insufficient investigations have been conducted on the analysis of shield tunneling parameters and the prediction of the tunneling excavation speed in formations composed of volcanic ash strata. To address this issue, we employ a comprehensive approach utilizing literature research, mathematical statistics, and other methodologies, centered on the analysis of the No. 1 Tunnel of the Jakarta-Bandung High-Speed Railway. Our focus is on examining the evolution patterns and inter-relationships of shield tunneling parameters within volcanic ash strata. Subsequently, we propose an optimized strategy for these tunneling parameters. By employing six machine-learning algorithms to construct prediction models, we compare and analyze their performance in predicting the tunneling excavation speed. The results indicate a positive correlation between slurry pressure and tunnel depth in volcanic ash strata, suggesting that the grouting pressure should exceed the slurry pressure by approximately 0.22 MPa. In the composite stratum of "volcanic ash debris + round gravel", the cutter torque exhibits a strong negative correlation with the total thrust (-0.77). Due to tool wear and ground resistance, the excavation speed and cutter speed are weakly negatively correlated. Compared to other strata, shield tunneling in volcanic ash strata exhibits larger grouting pressure fluctuations, slower tunneling excavation speed, greater total thrust, higher cutter torque, and lower cutter speed. Regarding shield tunneling excavation speed prediction, the ranking of the algorithm performance is RF > DNN > ANN > BPNN > MNR > SVM, with RF achieving a decision coefficient of 0.829. The RF model is well-suited for predicting the shield structure tunneling excavation speed.
引用
收藏
页数:19
相关论文
共 33 条
  • [1] Research on the Program of Introducing Jakarta-Bandung High-speed Railway into Jakarta Terminal
    Wu, Bilong
    Journal of Railway Engineering Society, 2022, 39 (06): : 4 - 10
  • [2] Clarifying Misconceptions on The Jakarta-Bandung High-Speed Railway
    Xu Liping
    ChinaReportASEAN, 2023, 8 (10) : 33 - 33
  • [4] Optimal Selection of Earthquake Resisting Schemes for Jakarta-Bandung High-Speed Railway
    Quan, Wei
    Deng, Lin
    Liu, Xuzheng
    Gao, Bibo
    ADVANCES IN CIVIL ENGINEERING, 2022, 2022
  • [5] "Risk is not Measured, but Contested and Compromised": A Case Study of Jakarta-Bandung High-Speed Railway
    Wijaya, Trissia
    JOURNAL OF CONTEMPORARY ASIA, 2024,
  • [6] Shield tunneling analysis and measures under elevated high-speed railway
    Gong Quanmei
    Shan Yao
    You Xiaoming
    Zhou Shunhua
    GEOTECHNICAL ASPECTS OF UNDERGROUND CONSTRUCTION IN SOFT GROUND, 2014, : 303 - 308
  • [7] Model of cost management for the Jakarta Bandung High Speed Railway Project
    Salim, Indra Putra
    Simanjuntak, Manlian Ronald A.
    Jin, Oei Fuk
    PROCEEDINGS OF THE INSTITUTION OF CIVIL ENGINEERS-MANAGEMENT PROCUREMENT AND LAW, 2024,
  • [8] The Indonesia High-Speed Train Traveler Preference Analysis (Case Study: Jakarta-Bandung)
    Tjahjono, Tri
    Kusuma, Andyka
    Tinumbia, Nuryani
    Septiawan, Ahmad
    RECENT PROGRESS ON: MECHANICAL, INFRASTRUCTURE AND INDUSTRIAL ENGINEERING, 2020, 2227
  • [9] F-NAVI shield tunneling method - simultaneous excavation and segment erection for high-speed tunneling
    Hosaka, H
    Goto, K
    Goto, T
    Sakurai, H
    (RE)CLAIMING THE UNDERGROUND SPACE, VOLS 1 AND 2, PROCEEDINGS, 2003, : 701 - 706
  • [10] Research and Development of Key Technologies for China’s Autonomous Catenary System and Its Application in the Jakarta-Bandung High-Speed Railway
    Wang, Tongjun
    Luo, Jian
    Gu, Xiaodong
    Yang, Fan
    Zhongguo Tiedao Kexue/China Railway Science, 45 (06): : 1 - 10