Development of time–cost trade-off optimization model for construction projects with MOPSO technique

被引:0
|
作者
Agarwal A.K. [1 ]
Chauhan S.S. [1 ]
Sharma K. [1 ]
Sethi K.C. [3 ]
机构
[1] Science, Madhya Pradesh, Gwalior
[2] Civil Engineering Department, Centurion University of Technology and Management, Gajapati
关键词
Construction projects; MOPSO; Multi-mode activities; Pareto-optimal solutions; TCT;
D O I
10.1007/s42107-024-01063-3
中图分类号
学科分类号
摘要
Balancing cost and time present a critical yet conflicting challenge in scheduling of construction projects. In today;s highly competitive construction market, achieving a subtle balance in optimizing objectives (time and cost) is vital for success of projects, requiring project participants to make essential trade-offs. With multi-objective particle swarm optimization (MOPSO), this study presents a time–cost trade-off (TCT) optimization model to overcome the challenges and constraints associated with existing TCT models. The focus is on multi-mode construction project activities, where each mode represents a different option for a construction activity requiring varying amounts of resources, time, and cost. The paper aims to select the best alternatives for project activities. For demonstrating the effectiveness of the developed MOPSO method in generating a set of Pareto-optimal solutions, it is applied to a real case study project. The working of proposed method in simultaneously optimizing two objectives is evaluated against existing trade-off optimization methods. The project team is provided with trade-off plots and an a priori approach to select one of the generated Pareto-optimal solutions. Additionally, this research will benefit the project;s stakeholders by maximizing profits, and the findings of this study can assist organizations and project teams in improving their scheduling choices. © The Author(s), under exclusive licence to Springer Nature Switzerland AG 2024.
引用
收藏
页码:4529 / 4539
页数:10
相关论文
共 50 条
  • [31] Development of time-cost trade-off optimization model for Indian highway construction projects using non-dominated sorting genetic algorithm-II methodology
    Kandipilli Mehar Kumar
    Deepanshu Agrawal
    Vinod Kumar Vishwakarma
    Mohammad Azim Eirgash
    Asian Journal of Civil Engineering, 2024, 25 (8) : 5975 - 5988
  • [32] A New Model for Solving Time-Cost-Quality Trade-Off Problems in Construction
    Fu, Fang
    Zhang, Tao
    PLOS ONE, 2016, 11 (12):
  • [33] Integrating Quality and Safety in Construction Scheduling Time-Cost Trade-Off Model
    Panwar, Abhilasha
    Jha, Kumar Neeraj
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2021, 147 (02)
  • [34] A Multi-Objective Trade-Off Model in Sustainable Construction Projects
    Wu, Guangdong
    SUSTAINABILITY, 2017, 9 (11)
  • [35] A novel multi criteria decision making model for optimizing time-cost-quality trade-off problems in construction projects
    Monghasemi, Shahryar
    Nikoo, Mohammad Reza
    Fasaee, Mohammad Ali Khaksar
    Adamowski, Jan
    EXPERT SYSTEMS WITH APPLICATIONS, 2015, 42 (06) : 3089 - 3104
  • [36] Construction time–cost–resources–quality trade-off optimization using NSGA-III
    Trivedi M.K.
    Sharma K.
    Asian Journal of Civil Engineering, 2023, 24 (8) : 3543 - 3555
  • [37] Multiobjective Trade-Off Optimization of Time, Cost, Quality, and Carbon Emission in the Building Construction Stage
    Wang, Haixin
    Chen, Xin
    Wang, Jiaqi
    Guan, Wenfeng
    Wei, Shengsong
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2025, 151 (04)
  • [38] Construction time-cost trade-off analysis using ant colony optimization algorithm
    Kuang Ya-ping
    Xiong Ying
    PROCEEDINGS OF THE 2006 INTERNATIONAL CONFERENCE ON MANAGEMENT SCIENCE & ENGINEERING (13TH), VOLS 1-3, 2006, : 2039 - 2044
  • [39] Development of discrete opposition-based NSGA-III model for optimizing trade-off between discrete time, cost, and resource in construction projects
    Sethi K.C.
    Rathinakumar V.
    Harishankar S.
    Bhadoriya G.
    Pati A.K.
    Asian Journal of Civil Engineering, 2024, 25 (6) : 4633 - 4644
  • [40] MINLP optimization model for the nonlinear discrete time-cost trade-off problem
    Klansek, Uros
    Psunder, Mirko
    ADVANCES IN ENGINEERING SOFTWARE, 2012, 48 : 6 - 16