THE KIDD-CREEK COPPER SMELTER - AN UPDATE ON PLANT PERFORMANCE

被引:0
|
作者
NEWMAN, CJ [1 ]
STOREY, AG [1 ]
MACFARLANE, G [1 ]
MOLNAR, K [1 ]
机构
[1] KIDD CREEK MINES LTD,COPPER SMELTER,TIMMINS,ONTARIO,CANADA
来源
CIM BULLETIN | 1992年 / 85卷 / 961期
关键词
SMELTER OPERATIONS; KIDD-CREEK MINES; COPPER OPERATIONS; FALCONBRIDGE-LIMITED;
D O I
暂无
中图分类号
TF [冶金工业];
学科分类号
0806 ;
摘要
The Kidd Creek copper smelter started operation in June 1981 using the Mitsubishi Continuous Smelting Process. A steady increase in plant production rates has been demonstrated, and the annual tonnage of concentrate smelted is now double the original design rate. This paper summarizes recent modifications made to increase concentrate feedrates, increase on-line time, reduce copper losses and control the impurity level in anode copper. It includes improvements made to furnace design, improvements to reduce downtime for boiler cleaning, and improvements made to the acid plant to allow handling of increased gas flowrates and higher gas strengths while maintaining low acid plant emission rates.
引用
收藏
页码:122 / 129
页数:8
相关论文
共 50 条
  • [31] SM-ND AND RB-SR DATING OF AN ARCHEAN MASSIVE SULFIDE DEPOSIT - KIDD-CREEK, ONTARIO
    MAAS, R
    MCCULLOCH, MT
    CAMPBELL, IH
    GEOLOGY, 1986, 14 (07) : 585 - 588
  • [32] CONTINUED DEVELOPMENT OF COPPER FLOTATION CONTROL AT THE KIDD CREEK CONCENTRATOR
    THWAITES, P
    CIM BULLETIN, 1983, 76 (860): : 41 - 46
  • [33] Automation of the zinc stripping process at the Kidd Creek zinc electrowinning plant
    Boissoneault, M
    Robinson, V
    Girard, G
    ZINC AND LEAD PROCESSING, 1998, : 843 - 859
  • [34] MULTIPLE HYDROTHERMAL AND METAMORPHIC EVENTS IN THE KIDD-CREEK VOLCANOGENIC MASSIVE SULFIDE DEPOSIT, TIMMINS, ONTARIO - EVIDENCE FROM TOURMALINES AND CHLORITES
    SLACK, JF
    COAD, PR
    CANADIAN JOURNAL OF EARTH SCIENCES, 1989, 26 (04) : 694 - 715
  • [35] Distributed control at the Kidd Creek grinding plant .2. Implementation
    Desbiens, A
    Flament, F
    Pomerleau, A
    CIM BULLETIN, 1997, 90 (1008): : 145 - 150
  • [36] STARTUP AND OPERATION OF THE KIDD CREEK ZINC SULFIDE PRESSURE LEACHING PLANT.
    Johnston, B.H.
    Doyle, B.N.
    Minerals and Metallurgical Processing, 1986, 3 (01): : 1 - 7
  • [37] CHARACTERIZATION AND SEPARATION OF METALLURGICAL RESIDUES FROM KIDD CREEK ZINC PROCESSING PLANT
    LASTRA, R
    ROWLANDS, N
    RAO, SR
    FINCH, JA
    TRANSACTIONS OF THE INSTITUTION OF MINING AND METALLURGY SECTION C-MINERAL PROCESSING AND EXTRACTIVE METALLURGY, 1987, 96 : C144 - C150
  • [38] Isasmelt - Mount Isa Copper Smelter progress update
    Bill, JL
    Briffa, TE
    Burrows, AS
    Fountain, CR
    Retallick, D
    Tuppurainen, JMI
    Edwards, JS
    Partington, P
    SULFIDE SMELTING 2002, 2002, : 181 - 193
  • [39] SELECTING AN OXYGEN PLANT FOR A COPPER SMELTER MODERNIZATION
    LARSON, KH
    HUTCHISON, RL
    JOM-JOURNAL OF THE MINERALS METALS & MATERIALS SOCIETY, 1994, 46 (10): : 19 - 21
  • [40] CHANGES IN THE COBALT MINERALOGY OF THE KIDD CREEK MASSIVE SULFIDE OREBODY AND THEIR EFFECT ON PLANT METALLURGY
    SCOTT, JD