MANAGING PROJECT ACTIVITY DURATION UNCERTAINTIES

被引:18
作者
ARSHAM, H
机构
[1] University of Baltimore, Md
来源
OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE | 1993年 / 21卷 / 01期
关键词
PROJECT MANAGEMENT; PERT; LP;
D O I
10.1016/0305-0483(93)90043-K
中图分类号
C93 [管理学];
学科分类号
12 ; 1201 ; 1202 ; 120202 ;
摘要
The critical path method (CPM), project evaluation and review technique (PERT), and stochastic PERT, the most widely used tools for project management, each require different forms of activity duration information: fixed time, three-time estimates and an a priori distribution function, respectively. While PERT and stochastic PERT allow for uncertainty in activity durations unfortunately they require a number of strong statistical assumptions. In this paper, uncertainty in project activity duration is treated in a managerial context rather than as random factors. A linear programming (LP) formulation of the project activity network is constructed and a new simplex-type tabular solution algorithm is developed to find a critical path (CP). While the proposed approach requires a time estimate for each activity duration, it provides the manager with the allowable simultaneous, independent or dependent changes of the estimates that will preserve the current CP. The results of these analyses empower the project planner and manager to assess and monitor various types of activity-duration uncertainties encountered in real life situations. It is assumed the reader is familiar with LP terminology.
引用
收藏
页码:111 / 122
页数:12
相关论文
共 31 条
[1]   A SIMULATION TECHNIQUE FOR ESTIMATION IN PERTURBED STOCHASTIC ACTIVITY NETWORKS [J].
ADLAKHA, VG ;
ARSHAM, H .
SIMULATION, 1992, 58 (04) :258-267
[3]   POSTOPTIMALITY ANALYSES OF THE TRANSPORTATION PROBLEM [J].
ARSHAM, H .
JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 1992, 43 (02) :121-139
[4]  
ASSAD AA, 1988, INTERFACES, V18, P75
[5]   SENSITIVITY ANALYSIS IN LINEAR-PROGRAMMING MODELS WITH COMMON INPUTS [J].
CAMM, JD ;
BURWELL, TH .
DECISION SCIENCES, 1991, 22 (03) :512-518
[6]   RESOURCE CONSTRAINED PROJECT CRASHING [J].
DECKRO, RF ;
HEBERT, JE .
OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE, 1989, 17 (01) :69-79
[7]  
ELMAGHRABY SE, 1977, ACTIVITY NETWORKS PR
[8]  
Evans JR, 1992, OPTIMIZATION ALGORIT
[9]  
GAITHER N, 1975, DECISION SCI, V6, P797, DOI DOI 10.1111/J.1540-5915.1975.TB01063.X
[10]   PERT ASSUMPTIONS REVISITED [J].
GOLENKOGINZBURG, D .
OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE, 1989, 17 (04) :393-396