Research on single-machine scheduling with position-dependent weights and past-sequence-dependent delivery times

被引:0
|
作者
Ji-Bo Wang
Bo Cui
Ping Ji
Wei-Wei Liu
机构
[1] Shenyang Aerospace University,School of Science
[2] The Hong Kong Polytechnic University,Department of Industrial and Systems Engineering
[3] Shenyang Sport University,Department of Science
来源
关键词
Delivery time; Position-dependent weight; Single-machine; Scheduling;
D O I
暂无
中图分类号
学科分类号
摘要
This article studies scheduling problems with past-sequence-dependent delivery times (denoted by psddt) on a single-machine, i.e., the delivery time of a job depends on its waiting time of processing. We prove that the total (discounted) weighted completion time minimization can be solved in O(nlogn)\documentclass[12pt]{minimal} \usepackage{amsmath} \usepackage{wasysym} \usepackage{amsfonts} \usepackage{amssymb} \usepackage{amsbsy} \usepackage{mathrsfs} \usepackage{upgreek} \setlength{\oddsidemargin}{-69pt} \begin{document}$$O(n\log n)$$\end{document} time, where n is the number of jobs, and the weight is a position-dependent weight. For common (denoted by con) and slack (denoted by slk) due-date assignment and position-dependent weights (denoted by pdw), we prove that an objective cost minimization is solvable in O(nlogn)\documentclass[12pt]{minimal} \usepackage{amsmath} \usepackage{wasysym} \usepackage{amsfonts} \usepackage{amssymb} \usepackage{amsbsy} \usepackage{mathrsfs} \usepackage{upgreek} \setlength{\oddsidemargin}{-69pt} \begin{document}$$O(n\log n)$$\end{document} time. The model (i.e., psddt and pdw) can also be extended to position-dependent (time-dependent) processing times.
引用
收藏
页码:290 / 303
页数:13
相关论文
共 50 条
  • [1] Research on single-machine scheduling with position-dependent weights and past-sequence-dependent delivery times
    Wang, Ji-Bo
    Cui, Bo
    Ji, Ping
    Liu, Wei-Wei
    JOURNAL OF COMBINATORIAL OPTIMIZATION, 2021, 41 (02) : 290 - 303
  • [2] Single-machine scheduling problems with past-sequence-dependent delivery times and position-dependent processing times
    Yang, S-J
    Yang, D-L
    JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 2012, 63 (11) : 1508 - 1515
  • [3] Single machine scheduling problems with general position-dependent processing times and past-sequence-dependent delivery times
    Zhao C.
    Tang H.
    Journal of Applied Mathematics and Computing, 2014, 45 (1-2) : 259 - 274
  • [4] Single-machine scheduling problems with past-sequence-dependent delivery times
    Koulamas, Christos
    Kyparisis, George J.
    INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2010, 126 (02) : 264 - 266
  • [5] Single-machine scheduling with past-sequence-dependent delivery times and release times
    Liu, Ming
    Zheng, Feifeng
    Chu, Chengbin
    Xu, Yinfeng
    INFORMATION PROCESSING LETTERS, 2012, 112 (21) : 835 - 838
  • [6] SINGLE-MACHINE SCHEDULING WITH PAST-SEQUENCE-DEPENDENT DELIVERY TIMES AND A LINEAR DETERIORATION
    Yin, Yunqiang
    Cheng, T. C. E.
    Xu, Jianyou
    Cheng, Shuenn-Ren
    Wu, Chin-Chia
    JOURNAL OF INDUSTRIAL AND MANAGEMENT OPTIMIZATION, 2013, 9 (02) : 323 - 339
  • [7] Single-machine scheduling with past-sequence-dependent delivery times and learning effect
    Yang, Suh-Jenq
    Hsu, Chou-Jung
    Chang, Teng-Ruey
    Yang, Dar-Li
    JOURNAL OF INDUSTRIAL AND PRODUCTION ENGINEERING, 2011, 28 (04) : 247 - 255
  • [8] New results on single-machine scheduling with past-sequence-dependent delivery times
    Liu, Ming
    Zheng, Feifeng
    Chu, Chengbin
    Xu, Yinfeng
    THEORETICAL COMPUTER SCIENCE, 2012, 438 : 55 - 61
  • [9] Single machine past-sequence-dependent delivery times scheduling with general position-dependent and time-dependent learning effects
    Shen, Lixin
    Wu, Yu-Bin
    APPLIED MATHEMATICAL MODELLING, 2013, 37 (07) : 5444 - 5451
  • [10] Single Machine Scheduling and Due Date Assignment with Past-Sequence-Dependent Delivery Times and General Position-Dependent Processing Times
    Zhao, Yufang
    ADVANCED DEVELOPMENT IN AUTOMATION, MATERIALS AND MANUFACTURING, 2014, 624 : 675 - 680