DOT shield tunneling beneath residential districts in Nagoya City's subway construction

被引:0
|
作者
Kawamura, T [1 ]
Miki, K [1 ]
Takeda, A [1 ]
Miki, T [1 ]
机构
[1] Nagoya Municipal Govt, Transportat Bur, Nagoya, Aichi, Japan
关键词
D O I
暂无
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
In Nagoya City, five subways with a combined length of 78.2 km are currently in service, and a new 11.3 km long line is currently under construction. The Double O Tube (DOT) shield tunneling method was adopted for seven out of the nine shield tunnel work areas, and excavation of four tunnel work areas has already been completed. The DOT method is a shield tunneling method for constructing a double-track tunnel of rational cross-sectional shape and has so far been used in four projects in Japan. This paper reports on the planning and construction of the Motoyama North Area, the longest tunnel section whose excavation began first and has already been completed. With an excavation length of 1,23 8.4 m, a maximum overburden depth of only 32.3 m and a longer-than-one-kilometer section that needs to be driven under a residential district, the tunnel section posed a challenge for the DOT method. A mucking system combining a continuous in-tunnel belt conveyor and a vertical belt conveyor was developed. The shield tunneling machine was launched on October 2, 2000, and the machine reached Motoyama Station on June 1, 2001.
引用
收藏
页码:707 / 713
页数:7
相关论文
共 8 条
  • [1] CONSTRUCTION CONTROL OF SHIELD TUNNELING THROUGH EXISTING SUBWAY
    Peng, Xua
    Xie, Tongtong
    NEW TECHNOLOGIES OF RAILWAY ENGINEERING, 2012, : 737 - 742
  • [2] Analysis of influence of undercrossing subway shield tunneling construction on the overlying tunnel
    Fang, Yong
    He, Chuan
    Tiedao Xuebao/Journal of the China Railway Society, 2007, 29 (02): : 83 - 88
  • [3] Controlling of construction parameters on metro shield tunneling traversing adjacently under the existing subway tunnel
    Zou, Chunhua
    Zhou, Shunhua
    Sun, Yuyong
    Dai, Renping
    Wang, Changdan
    PROCEEDINGS OF 2009 INTERNATIONAL SYMPOSIUM ON RISK CONTROL AND MANAGEMENT OF DESIGN, CONSTRUCTION AND OPERATION IN UNDERGROUND ENGINEERING, 2009, : 208 - 212
  • [4] Type selection matching and construction practice of shield tunneling machine for confined water stratum of subway tunnel
    地铁隧道承压水地层盾构机选型配套及施工实践
    Liu, Xuquan (664927880@qq.com), 1600, Chinese Society of Civil Engineering (53):
  • [5] Coupled fluid-mechanical analysis of DOT shield tunnel construction beneath adjacent existing underpass
    Chen Yu
    Zhang Qing-he
    Zhu Ji-wen
    Yao Hai-ming
    ROCK AND SOIL MECHANICS, 2010, 31 (06) : 1950 - +
  • [6] Coupled fluid-mechanical analysis of DOT shield tunnel construction beneath adjacent existing underpass
    Chen, Yu
    Zhang, Qing-He
    Zhu, Ji-Wen
    Yao, Hai-Ming
    Yantu Lixue/Rock and Soil Mechanics, 2010, 31 (06): : 1950 - 1955
  • [7] Report on the construction of the triple circular-face shield tunneling at Iidabashi Station (provisional name) on Metropolitan Subway Route 12
    Kaigome, A
    Kajiyama, M
    Yamamori, N
    CHALLENGES FOR THE 21ST CENTURY, VOL. 2: COMMUNICATION TUNNELS/MISCELLANEOUS INCLUDING WATER TUNNELS/MECHANISED TUNNELLING, 1999, : 885 - 894
  • [8] World's largest slurry shield tunneling report in Trans-Tokyo Bay Highway construction
    Funasaki, T
    Izumi, Y
    Kanai, M
    Miki, K
    1997 RAPID EXCAVATION AND TUNNELING CONFERENCE, PROCEEDINGS, 1997, : 591 - 604