A precedence constrained flow shop scheduling problem with transportation time, breakdown times, and weighted jobs

被引:0
|
作者
Thangaraj, M. [1 ]
Kumar, T. Jayanth [1 ]
Nandan, K. R. [1 ]
机构
[1] Jain Deemed Univ, Fac Engn & Technol, Dept Basic Sci, Bangalore, Karnataka, India
关键词
Precedence constraint; Flow shop scheduling; Breakdown and transportation times;
D O I
10.5267/j.jpm.2022.4.002
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Job precedence can often be seen in various manufacturing process scenarios. For instance, in the context of flow shop scheduling, certain jobs must be processed before a specific job may be executed. Formally, this scenario is known as precedence constraint, which influences the optimal job sequence. Because of this practical significance, in this study, a two-machine flow shop scheduling problem in which transportation times, breakdown time, and weighted jobs are considered. In addition to that, an ordered precedence constraint is considered that ensures a successor job cannot start on any machine before its predecessor job has been done on all machines. This is the first study that deals with flow shop scheduling problems with transportation times, breakdown time, job weights, and precedence constraints altogether, to the best of theauthor's knowledge. To solve this problem, a simple and efficient solution methodology is developed that assures optimal or near-optimal solutions effectively. The developed algorithm is tested on various test instances and results are reported, which will be useful for future comparative studies. (C) 2022 Growing Science Ltd. All rights reserved.
引用
收藏
页码:229 / 240
页数:12
相关论文
共 50 条
  • [1] A precedence constrained flow shop scheduling problem with transportation time, breakdown times, and weighted jobs
    Thangaraja, M.
    Kumar, T. Jayanth
    Nandan, K. R.
    JOURNAL OF PROJECT MANAGEMENT, 2022,
  • [2] A Flow Shop Scheduling Problem with Transportation Time and Separated Setup Time of Jobs
    Agrawal, S.
    Gautam, A.
    Chauhan, D. K.
    Tiwari, L. M.
    Kapoor, S.
    INTERNATIONAL CONFERENCE ON MODELLING OPTIMIZATION AND COMPUTING, 2012, 38 : 1327 - 1332
  • [3] Scheduling Precedence-Constrained Jobs on Two Resources to Minimize the Total Weighted Completion Time
    Rajneesh, R.
    Elmaghraby, S. E.
    PROCEEDINGS OF 2013 INTERNATIONAL CONFERENCE ON INDUSTRIAL ENGINEERING AND SYSTEMS MANAGEMENT (IEEE-IESM 2013), 2013, : 592 - 598
  • [4] Metaheuristics for a Flow Shop Scheduling Problem with Urgent Jobs and Limited Waiting Times
    Jeong, BongJoo
    Han, Jun-Hee
    Lee, Ju-Yong
    ALGORITHMS, 2021, 14 (11)
  • [5] Maximizing the weighted number of just-in-time jobs in flow shop scheduling
    Byung-Cheon Choi
    Suk-Hun Yoon
    Journal of Scheduling, 2007, 10 : 237 - 243
  • [6] Maximizing the weighted number of just-in-time jobs in flow shop scheduling
    Choi, Byung-Cheon
    Yoon, Suk-Hun
    JOURNAL OF SCHEDULING, 2007, 10 (4-5) : 237 - 243
  • [7] Flow shop scheduling with jobs arriving at different times
    Li, Guo
    Li, Na
    Sambandam, Narayanasamy
    Sethi, Suresh P.
    Zhang, Faping
    INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2018, 206 : 250 - 260
  • [8] Scheduling precedence-constrained jobs with Stochastic processing times on parallel machines
    Skutella, M
    Uetz, M
    PROCEEDINGS OF THE TWELFTH ANNUAL ACM-SIAM SYMPOSIUM ON DISCRETE ALGORITHMS, 2001, : 589 - 590
  • [9] The Lagrangean Relaxation for the Flow Shop Scheduling Problem with Precedence Constraints, Release Dates and Delivery Times
    Fabri, Marcelus
    Ramalhinho, Helena
    de Souza, Mauricio C.
    Ravetti, Martin G.
    JOURNAL OF ADVANCED TRANSPORTATION, 2019, 2019
  • [10] Minimizing the Number of Tardy Jobs in Flow Shop Sequence Dependent Setup Times Scheduling Problem
    Varmazyar, Mohsen
    Salmasi, Nasser
    MECHANICAL AND AEROSPACE ENGINEERING, PTS 1-7, 2012, 110-116 : 4063 - 4069