MILP models to minimise makespan in additive manufacturing machine scheduling problems

被引:75
|
作者
Kucukkoc, Ibrahim [1 ]
机构
[1] Balikesir Univ, Dept Ind Engn, Cagis Campus, Balikesir, Turkey
关键词
Additive manufacturing; 3D printing; Scheduling; Mathematical modelling; MILP; BATCH PROCESSING MACHINES; ARBITRARY JOB SIZES; OPTIMIZATION; COMPLEXITY;
D O I
10.1016/j.cor.2019.01.006
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
Additive manufacturing (AM), also known as 3D printing, is gaining enormous importance in the production of highly customised quality and lightweight products in low quantities. In addition to AM's use in producing fully functional industrial components, it is also seen as a technology of the future that will enable civilisation in space. Although the cost structures for AM facilities have been sufficiently studied in the literature, no effort has been made to investigate the scheduling problem of AM machines with the aim of optimising processing time-related performance measures. This paper focuses on the scheduling problem of single and multiple AM machines and proposes mathematical models for optimisation. Mixed-integer linear programming models allocate parts into jobs to be produced on AM machines to minimise makespan. The problem was handled by considering different machine configurations (i.e. single machine, parallel identical machines, and parallel non-identical machines). The models were coded in IBM ILOG CPLEX Optimization Studio (v12.8.0) and solved through the CPLEX solver. This paper presents detailed solutions for numerical examples. A comprehensive computational study was also conducted, and the results are presented. The optimum solutions are reported for most problems. The best solutions obtained within the time limit (i.e. 1800 and 2400 s) are reported for the parallel identical and non-identical AM machine scheduling problems if optimum solution could not be verified. (C) 2019 Elsevier Ltd. All rights reserved.
引用
收藏
页码:58 / 67
页数:10
相关论文
共 50 条
  • [1] A reinforcement learning iterated local search for makespan minimization in additive manufacturing machine scheduling problems
    Alicastro, Mirko
    Ferone, Daniele
    Festa, Paola
    Fugaro, Serena
    Pastore, Tommaso
    COMPUTERS & OPERATIONS RESEARCH, 2021, 131
  • [2] Advanced constraint programming formulations for additive manufacturing machine scheduling problems
    Cakici, Eray
    Kucukkoc, Ibrahim
    Akdemir, Mustafa
    JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 2025, 76 (03) : 590 - 605
  • [3] MILP models and effective heuristic for energy-aware parallel machine scheduling with shared manufacturing
    Cheng, Junheng
    Cheng, Jingya
    Lin, Yanhong
    Lu, Shu
    Wu, Peng
    EXPERT SYSTEMS WITH APPLICATIONS, 2025, 271
  • [4] Heuristics for the two-machine flowshop scheduling problem to minimise makespan with bounded processing times
    Allahverdi, Ali
    Aydilek, Harun
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2010, 48 (21) : 6367 - 6385
  • [5] Identical parallel machine scheduling to minimise makespan and total weighted completion time: a column generation approach
    Xu, Jingyang
    Nagi, Rakesh
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2013, 51 (23-24) : 7091 - 7104
  • [6] Scheduling in Kanban-Controlled Flowshops to Minimise the Makespan of Containers
    G.V. Ramanan
    C. Rajendran
    The International Journal of Advanced Manufacturing Technology, 2003, 21 : 348 - 354
  • [7] Scheduling in kanban-controlled flowshops to minimise the makespan of containers
    Ramanan, GV
    Rajendran, C
    INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2003, 21 (05): : 348 - 354
  • [8] Single-machine scheduling problem with flexible maintenance and non-resumable jobs to minimise makespan
    Chen, Yarong
    Huang, Chenjun
    Chou, Fuh-Der
    Huang, Shenquan
    IET COLLABORATIVE INTELLIGENT MANUFACTURING, 2020, 2 (04) : 174 - 181
  • [9] Scheduling multiprocessor tasks to minimise the makespan on two dedicated processors
    Manaa, Adel
    Chu, Chengbin
    EUROPEAN JOURNAL OF INDUSTRIAL ENGINEERING, 2010, 4 (03) : 265 - 279
  • [10] Single-Machine Scheduling Problems with Two Agents Competing for Makespan
    Ding, Guosheng
    Sun, Shijie
    LIFE SYSTEM MODELING AND INTELLIGENT COMPUTING, PT I, 2010, 6328 : 244 - 255