Construction schedule and cost risk for large and small light water reactors

被引:9
|
作者
Stewart, W. Robb [1 ,2 ]
Shirvan, Koroush [1 ]
机构
[1] MIT, Dept Nucl Sci & Engn, Cambridge, MA 02139 USA
[2] Boston Atom LLC, Boston, MA USA
关键词
Boiling water reactors - Cost benefit analysis - Cost estimating - Errors - Modular construction - Pressurized water reactors - Risk perception - Uncertainty analysis;
D O I
10.1016/j.nucengdes.2023.112305
中图分类号
TL [原子能技术]; O571 [原子核物理学];
学科分类号
0827 ; 082701 ;
摘要
Capital cost and construction schedule estimates for nuclear projects often under-estimate the realized costs upon project completion. Uncertainty quantification of nuclear construction project cost estimates have seldom been used in open-literature and have not shown to effectively bound the realized schedules and costs. Building on recent studies of advanced light water reactor costs and construction schedules, this paper explored the risk of different construction delay drivers and the implication on total installed cost. Using data from previous nuclear projects, as well as other megaprojects and analyses, we modeled the impact of supply chain delays, human error, change orders, and productivity on four different reactor architectures: a large passively safe PWR, a large modular BWR, small modular BWR, and a multi-module PWR. The probability and impact of supply chain delays and change orders were modeled based on the AP1000 construction experience at Vogtle Units 3 & 4, while the human error and productivity models came from non-nuclear sources. The estimated risk to cost overrun and schedule delays were found to be significant. The multi-module plant was the most susceptible to construction delays, and the small modular BWR was the least susceptible. However, the risk mitigation by a small reactor only offset the lost economy of scale in a few scenarios relative to the large reactors, because there was still significant onsite work despite modularization. Access to large labor markets mitigated the upper bound cost and schedule risks significantly for all reactor types. Finally, design changes and the resulting productivity hits were the largest driver of construction delays, and human error was the second largest driver, but supply chain delays only accounted for a small fraction of the delays for the assessed water-cooled concepts.
引用
收藏
页数:9
相关论文
共 50 条
  • [1] Impact of modularization and site staffing on construction schedule of small and large water reactors
    Stewart, W. Robb
    Gregory, Jeremy
    Shirvan, Koroush
    NUCLEAR ENGINEERING AND DESIGN, 2022, 397
  • [2] Expert assessments of the cost of light water small modular reactors
    Abdulla, Ahmed
    Azevedo, Ines Lima
    Morgan, M. Granger
    PROCEEDINGS OF THE NATIONAL ACADEMY OF SCIENCES OF THE UNITED STATES OF AMERICA, 2013, 110 (24) : 9686 - 9691
  • [3] OPTIMIZATION OF REFUELING SCHEDULE FOR LIGHT-WATER REACTORS
    MOTODA, H
    HERCZEG, J
    SESONSKE, A
    NUCLEAR TECHNOLOGY, 1975, 25 (03) : 477 - 496
  • [4] OPTIMIZATION OF REFUELING SCHEDULE FOR LIGHT-WATER REACTORS
    MOTODA, H
    HERCZEG, J
    SESONSKE, A
    TRANSACTIONS OF THE AMERICAN NUCLEAR SOCIETY, 1973, 17 (NOV): : 307 - 308
  • [5] CONSTRUCTION AND OPERATING EXPERIENCE WITH LIGHT WATER REACTORS
    不详
    NUCLEAR ENGINEERING INTERNATIONAL, 1976, 21 (238): : 53 - 56
  • [6] Cost and Schedule Risk Analysis of Bridge Construction in Pakistan: Establishing Risk Guidelines
    Choudhry, Rafiq M.
    Aslam, Mohammad A.
    Hinze, Jimmie W.
    Arain, Faisal M.
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2014, 140 (07)
  • [7] Integration of Schedule, Cost, Traffic, and Risk into the Determination of Construction Contract Times
    Yin, Yangtian
    Choi, Kunhee
    Jeong, H. David
    Touran, Ali
    JOURNAL OF MANAGEMENT IN ENGINEERING, 2022, 38 (06)
  • [8] CONSTRUCTION AND OPERATING EXPERIENCE WITH LIGHT-WATER REACTORS IN FRG
    WECKESSER, A
    KORNBICHLER, H
    KELLER, W
    ATOMWIRTSCHAFT, 1972, 17 (9-10): : 479 - +
  • [9] TRANSFER OF MANUFACTURING TECHNOLOGY FOR LARGE LIGHT-WATER REACTORS
    SCIAGATA, R
    TRANSACTIONS OF THE AMERICAN NUCLEAR SOCIETY, 1982, 42 : 103 - 103
  • [10] Application of probabilistic cost and schedule risk assessment and risk management to large infrastructure projects
    McGrath, T. C.
    Roberds, W. J.
    Keizur, A. E.
    del Olmo, A. Gutierrez
    Barbato, I.
    SAFETY AND RELIABILITY FOR MANAGING RISK, VOLS 1-3, 2006, : 2093 - +