Effects of Creep on Shield Tunnelling Through Squeezing Ground

被引:8
|
作者
Leone, Thomas [1 ]
Nordas, Alexandros N. [1 ]
Anagnostou, Georgios [1 ]
机构
[1] Swiss Fed Inst Technol, Zurich, Switzerland
关键词
Tunnel boring machine; Creep; Perzyna; Shield jamming; Lining overstressing; Standstill; BEHAVIOR; EXCAVATION; MODEL; ROCK;
D O I
10.1007/s00603-023-03505-x
中图分类号
P5 [地质学];
学科分类号
0709 ; 081803 ;
摘要
The present work aims to improve the reliability of shield jamming and lining damage risk assessment in squeezing ground by analysing the effects of creep on the evolution of rock pressure over time. The study is based on numerical simulations of typical mechanised tunnelling processes, generally consisting of shield advance phases alternating with shorter or longer standstills for lining installation, maintenance, etc. A linear elastic-viscous plastic constitutive model based upon Perzyna's overstress theory is employed, which considers the time-dependency of plastic deformations via a single viscosity parameter. The investigations demonstrate the following: (i) shield loading during advance increases with increasing viscosity under certain conditions, which contradicts the common perception in many existing works that creep is thoroughly favourable for shield jamming; (ii) creep is thoroughly unfavourable for shield loading during long standstills and long-term lining loading, due to the additional viscoplastic ground deformations manifested over time; (iii) the commonly adopted simplifying assumption of continuous excavation with the gross advance rate is adequate only where standstills are very short (e.g., for lining erection during the stop-and-go shield tunnelling process), but otherwise underestimates the shield loading, even in cases of regular inspection and maintenance standstills lasting only a few hours. Two application examples, the Frejus safety gallery and the Gotthard Base tunnel, demonstrate the need to consider creep and the accuracy of modelling tunnel construction by a semi-discrete approach, where only the very short standstills for lining erection are considered via an average advance rate, but longer standstills are explicitly simulated. Assessment of the effect of creep on TBM shield loading.Assessment of the effect of creep on long-term lining loading.Analysis of a counter-intuitive, adverse effect of advance rate on shield loading.Discussion of alternative methods of considering excavation standstills.Development of a semi-discrete model for estimating shield loading during standstills.
引用
收藏
页码:351 / 374
页数:24
相关论文
共 50 条
  • [1] Effects of Creep on Shield Tunnelling Through Squeezing Ground
    Thomas Leone
    Alexandros N. Nordas
    Georgios Anagnostou
    Rock Mechanics and Rock Engineering, 2024, 57 : 351 - 374
  • [2] Creep Versus Consolidation in Tunnelling Through Squeezing Ground—Part A: Basic Time Effects
    Leone, Thomas
    Nordas, Alexandros N.
    Anagnostou, Georgios
    Rock Mechanics and Rock Engineering, 57 (08): : 5519 - 5536
  • [3] The Interaction Between Shield, Ground and Tunnel Support in TBM Tunnelling Through Squeezing Ground
    Ramoni, M.
    Anagnostou, G.
    ROCK MECHANICS AND ROCK ENGINEERING, 2011, 44 (01) : 37 - 61
  • [4] The Interaction Between Shield, Ground and Tunnel Support in TBM Tunnelling Through Squeezing Ground
    M. Ramoni
    G. Anagnostou
    Rock Mechanics and Rock Engineering, 2011, 44 : 37 - 61
  • [5] Creep Versus Consolidation in Tunnelling Through Squeezing Ground-Part A: Basic Time Effects
    Leone, Thomas
    Nordas, Alexandros N.
    Anagnostou, Georgios
    ROCK MECHANICS AND ROCK ENGINEERING, 2024, 57 (08) : 5519 - 5536
  • [6] Creep Versus Consolidation in Tunnelling through Squeezing Ground-Part B: Transferability of Experience
    Nordas, Alexandros N.
    Leone, Thomas
    Anagnostou, Georgios
    ROCK MECHANICS AND ROCK ENGINEERING, 2024, 57 (08) : 5537 - 5555
  • [7] Quantification of extrusion-induced excavation volume in shield tunnelling through squeezing cohesive-frictional ground
    Thomas, Pferdekamper
    Georgios, Anagnostou
    SCIENTIFIC REPORTS, 2025, 15 (01):
  • [8] Tunnelling methods for squeezing ground
    Schubert, W
    Moritz, B
    Sellner, P
    NINTH INTERNATIONAL CONGRESS ON ROCK MECHANICS, VOLS 1 & 2, 1999, : 233 - 236
  • [9] Basic considerations on tunnelling in squeezing ground
    Kovari, K
    Staus, J
    ROCK MECHANICS AND ROCK ENGINEERING, 1996, 29 (04) : 203 - 210
  • [10] Interpretation of Core Extrusion Measurements When Tunnelling Through Squeezing Ground
    Cantieni, L.
    Anagnostou, G.
    Hug, R.
    ROCK MECHANICS AND ROCK ENGINEERING, 2011, 44 (06) : 641 - 670